Community, Health and Housing Committee decided this item on Monday 4 December 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY that: 1. That the Committee authorises Officers to investigate in more detail the following: i. Options in relation to the development of the Council’s Housing Garage sites including modular housing. ii. Options in relation to developing a local assembly plant within the Borough to provide modular housing. 2. That a further report on the options as set out above is provided to the next Community, Health & Housing Committee. Reasons for Recommendation To enable BBC to maintain its responsibilities and fulfil its obligations as a landlord. A review of all the Council’s garage sites would be required to ensure asset management decisions were based on sound information. It was vital that the Council had up to date information about condition of the HRA stock in order to support its investment decisions each year. The risks in not having this information include the failure to provide adequate resources to tackle repairs and maintenance that subsequently led to the need for replacement at a much higher cost.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1At the 18th October 2017 Ordinary Council, the following Motion was moved by Cllr Hossack, seconded by Cllr Poppy and was carried unanimously.
‘That this Council investigates the opportunity that the use of modular construction homes, in conjunction with the utilisation of our multiple garage site assets, could present in addressing the need to meet our housing supply needs quickly and efficiently whilst at the same time addressing the need for affordability.
That the council also considers as part of this project, the opportunity for social return by of having a local assembly plant within the Borough that would provide the opportunity for employment, skills and apprenticeships and the support of local supply businesses whilst at the same time, meeting the housing need at source.’
1.2This report sets out the initial issues and options regarding the future provision of the housing garage sites.
2. Recommendation(s)
2.1That the Committee authorises Officers to investigate in more detail the following:
i. Options in relation to the development of the Council’s Housing Garage sites including modular housing. ii. Options in relation to developing a local assembly plant within the Borough to provide modular housing.
2.2That a further report on the options as set out above is provided to the next Community, Health & Housing Committee. 3. Introduction and Background
3.1A total of 83 Garage sites were reviewed as part of the Pilot Housing Scheme. The sites supplied for the study were identified by the Housing Department as garage buildings together with a limited number of parking spaces, these were understood to be a true reflection of the current ownership by the Council. The Desktop Study was suggested to become a ‘live database’ to be added to and progressed into a Site Register, ultimately creating a continuously current database of assessed capacity sites to meet the growing housing need.
3.2In December 2015 a report was presented to committee, Min 267 refers, which set out the stages involved in the Study to support the preparation of a Site Register for the Housing Department. The Study set out a Three Stage Process to review all garage sites on the database in more detail.
3.3Stage 1 was conducted as a Desktop Study of garage sites currently under council ownership and the identification of their potential for conversion to accommodate residential development as part of the Pilot Housing Scheme.
3.4Stage 2 was conducted as a series of contextual site appraisals for a quantity of sites immediately identified following the Stage 1 Desktop Study.
3.5A total of 83 sites were reviewed within Stage 1; using desk based information only these were sorted into a ‘traffic light’ system signalling sites with no potential at this stage for further study, these were coded ‘RED’ which was a total of 37 sites. Sites with potential for further contextual appraisal and study but which had with constraints were coded ‘AMBER’ which was a total of 36 sites. Sites for immediate Stage 2 contextual appraisal were coded as ‘GREEN’ which were 10 in total.
3.6Stage 2 study concluded that out of the 10 ‘GREEN’ sites 6 had the potential to be transferred to Stage 3, whereby detailed Architectural and Planning Feasibility could be undertaken. Stage 3 is proposed to be outsourced given the specialist analysis and design information necessary to produce an informed approach to the Pilot Housing Scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community, Health and Housing Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies