Community, Health and Housing Committee agreed this item on Monday 4 December 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY that: 1. Members to agree in principle to a project to construct new DDA compliant access ramps and steps to the lower public bowls green at King George’s Playing Fields. 2. Members agree to Officers applying to the Health and Wellbeing Board and also the Disabled Facilities to use the Better Cars Fund monies to fund the project. 3. Members delegate authority to Officers to engage with both Brentwood Bowls Club and Central Essex Bowls Club to progress a final design for the access point and then if successful in obtaining funding to proceed and complete works before the start of the 2018 playing season. Reasons for Recommendation To allow Officers to progress applications to the Health and Wellbeing Board and also the Better Care Fund scheme for funding to improve the ramped access to the bowls facility at King George’s Playing Fields. To allow for the degraded and now unusable disabled access to the lower green at King George’s Playing Fields bowls facility to be rebuilt in line with DDA requirements to improve and enhance access to the facility. To ensure that works can be completed before the commencement of the 2018 playing season. The meeting concluded at 10:05pm
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1King George’s Playing Fields is home to two of the Council’s three public amenity lawn bowls greens and the two resident clubs of Brentwood Bowls Club and Central Essex Bowls Club respectively.
1.2Due to the age of the greens and a lack of investment over the last decade the infrastructure, in particular access arrangements is limited and not suited to a modern club wanting to attract new Members from all walks of life including and especially those with limited physical mobility.
1.3The report before Members is requesting an agreement in principle to apply to both the Health and Wellbeing Board and also the Disabled Facilities Grant to jointly fund access improvements to the public bowling greens in the form of new DDA compliant ramps and steps leading to the lower of the two public greens.
2. Recommendation(s)
2.1Members to agree in principle to a project to construct new DDA compliant access ramps and steps to the lower public bowls green at King George’s Playing Fields.
2.2Members agree to Officers applying to the Health and Wellbeing Board and also the Disabled Facilities Grant to fund the project. 2.3 Members delegate authority to Officers to engage with both Brentwood Bowls Club and Central Essex Bowls Club to progress a final design for the access point and then if successful in obtaining funding to proceed and complete works before the start of the 2018 playing season.
3. Introduction and Background
3.1King George’s Playing Fields is home to two of the Council’s three public amenity lawn bowls greens which are also home to the two resident clubs of Brentwood Bowls Club and Central Essex Bowls Club.
3.2The first green was constructed in the 1960’s with the second added in the late 1970’s due to the demand on the facilities.
3.3Due to the age of the facilities they understandably do not meet current legislation in terms of access and in particular disability access.
3.4The clubs have been enquiring with the Council to improve access to the site for a number of years but due to resource restrictions this has, to date, sadly not been possible.
3.5The two resident clubs have well over a hundred members between them with both clubs being active in trying to recruit new members throughout the playing season, especially those that may have restricted mobility. Both clubs also have active social sections which form an important part of the bowls experience for many that may otherwise not interact on such a varied and frequent basis. This undoubtable would have a positive effect on the individuals mental well being.
3.6The access ramp and steps to the lower of the two public greens is now in a state of disrepair and no longer fit or safe to use without immediate action prior to the 2018 season. This will mean that only fully abled bowlers will be able to use the lower green which is likely to impact on the clubs ability to utilise this facility.
3.7The proposed works are to rebuild and widen the degraded access ramp and steps to the lower green to meet current DDA standards and to also widen the access ramp to the club house leading from the main park, again in line with current DDA standards.
3.8It is anticipated, pending a final design, that these works will cost in the region of £20,000 - £25,000. 3.9 There are currently insufficient funds within the Council’s own resources to undertake the works needed to instigate these improvements and, so it is Officers intentions to apply to both the Health and Wellbeing Board and also the Disabled Facilities Grant to fund these works in there entirety.
4. Issue, Options and Analysis of Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community, Health and Housing Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.