Resolved

RESOLVED UNANIMOUSLY : 1. That the committee recommends to Ordinary Council, that the Statement of Common Ground (SCG), and attached as Appendix A of the report, prepared by ASELA be approved as a guide to the preparation of a Joint Strategic Plan. Reasons for Recommendation In order to fulfil the obligation of the Duty to Co-operate as was required for the Brentwood LDP to be accepted, and to promote and deliver much needed infrastructure and economic growth, Brentwood must engage with the surrounding boroughs.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Policy, Projects and Resources Committee

Executive summary

1.1The purpose of this report is to update members of the PPR committee on the status of the work undertaken by Leaders and Chief Executives of South Essex Councils, now known as the Association of South Essex Local Authorities (ASELA).

1.2South Essex Councils are defined as Brentwood, Basildon, Thurrock, Southend, Rochford, Castle Point and Essex CC

2. Recommendation(s)

2.1That the committee recommends to Ordinary Council, that the Statement of Common Ground (SCG), and attached as Appendix A, prepared by ASELA be approved as a guide to the preparation of a Joint Strategic Plan.

3. Introduction and Background

3.1Since the last written report to the PPR committee, 6th February 2018, work has continued, as ASELA have agreed to explore a common approach to supporting the development of growth, housing and key infrastructure over the next 20 years, in the South Essex area.

3.2As part of the Council’s production of a Local Development Plan, it will need to demonstrate a “duty to co-operate” with surrounding neighbouring authorities. The JSP will facilitate a co-ordinated approach to strategic growth in the South Essex area, enabling new development, whilst maximising economic opportunities for the region and will be aligned to improvements in infrastructure 3.3 To support this aim, ASELA has drafted a 'Statement of Common Ground' (SCG). This sets out the next steps and is an important part in focusing economic growth across the region.

3.4The SCG, along with preparing a Joint Strategic Plan (JSP) for south Essex, would assist future plans for development to ensure new transport links, health and social infrastructure, business and skill opportunities are all included and will ensure that the 90,000 homes that have been identified as being needed across south Essex over the next twenty years are built.

3.5The JSP, if agreed, will provide much valued input to the review of the Council’s LDP once it has been adopted

3.6Members are reminded that the Leaders and Chief Executives of ASELA have agreed on eight industrial and infrastructure strategic priorities for the area;

1. Place leadership, proposition and brand

2. Opening up spaces for development (green infrastructure, housing and commercial)

3. Transforming transport connectivity

4. Supporting our seven sectors of industrial opportunity:  Advanced manufacturing  Construction  Environmental technologies and energy  Digital and creative services  Finance and business services  Life sciences and healthcare  Transport and logistics

5. Shaping local labour and skills markets

6. Creating a fully digitally-enabled place

7. Securing a sustainable energy supply

8. Enhancing health and social care through co-ordinated planning. 4. Issue, Options and Analysis of Options

4.1The co-operation in South Essex and determination to succeed for the prosperity of the whole of the South Essex area requires this activity and there are no real delivery vehicles other than ASELA that can achieve this with acceptable timeframes.

Reasons for recommendation

5.1In order to fulfil the obligation of the Duty to Co-operate as required for the Brentwood LDP to be accepted, and to promote and deliver much needed infrastructure and economic growth, Brentwood must engage with the surrounding boroughs.

Consultation

6.1No formal consultation has been undertaken

7. References to Corporate Plan

7.1The Council is committed to make Brentwood a Borough where people feel safe, healthy and supported.

8. Implications

Financial Implications Name & Title: Jacqueline Vanmellaerts, Interim Chief Financial Officer Tel & Email: 01277 312829 [email protected]

8.1Financial implications are currently being determined for the collaboration. The Council has sufficient reserves to fund any financial costs that may arise and will be reported back to Committee appropriately.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ASELA 2050 UpdateReport 107 KB DownloadRead as text
PDF
ASELA JSP Statement of Common Ground June 2018 FINALReport 752 KB Download

At this meeting

Whole meeting

Who was there

18 of 21 attended
ML
Councillor Mrs Louise McKinlayChair, present
JK
Councillor John KerslakeVice-Chair, present
GB
Councillor Gareth BarrettCommittee Member, present
RH
Councillor Roger HirstCommittee Member, present
CH
Councillor Chris HossackCommittee Member, present
DK
Councillor David KendallCommittee Member, present
PM
Councillor Philip MynottCommittee Member, present
KP
Councillor Keith ParkerCommittee Member, present
ML
Councillor Ms Louise RowlandsCommittee Member, present
TB
Councillor Thomas BridgeSubstitute, in attendance
PR
Philip RuckOfficer, present
ZB
Zoe BormanOfficer, expected

All 21 on the meeting page

On this subject at Brentwood

Search all
  1. ASELA 2050 UpdateThis decision
  2. South Essex Local Authorities (ASELA) Update and proposed Governance StructureNoted

More from Brentwood Policy, Projects and Resources Committee

All decisions
MeetingDecisionOutcome
18 Sep 2018 2018/19 General Fund Revenue, Housing Revenue Account, Capital Budget Monitoring and Treasury Activity UpdateRESOLVED UNANIMOUSLY: 1. To agree the projected outturn position for 2018/19 of the Council’s General Fund Revenue bu... Agreed Open
18 Sep 2018 Department for Communities and Local Government (MHCLG) Pilot Programme for 75% Business Rates Retention - 2019/20RESOLVED UNANIMOUSLY: 1. Members note the content of the report and its potential implications for the forthcoming bu... Agreed Open
18 Sep 2018 Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on... Approved Open
18 Sep 2018 Feasibility Study for Parking on Housing GreensRESOLVED UNANIMOUSLY: 1. To instruct officers to identify possible sites for parking on Housing Greens and undertake ... Decided Open
18 Sep 2018 Leisure StrategyThat Members agree the and action plan at Appendix A. Reasons for Recommendation As part of the Council’s due diligen... Agreed Open