What was decided
The Committee approved the draft Capital Strategy for 2026/27 to 2029/30 for inclusion in the Capital and Investment Strategy, the 2026/27 budget-setting process and the 2026/27 to 2029/30 Medium Term Financial Strategy. Report P1, P6
Members noted that all cost assumptions for major projects in the Capital Programme are indicative and final costs are subject to confirmation following further decisions on individual projects. Report P6
The Committee noted the funding hierarchy of capital receipts and external grants before borrowing. Report P3, P12
Why
The programme aligns with strategic objectives and statutory responsibilities, and has been developed through a review and appraisal process to ensure affordability within the Medium-Term Financial Strategy and compliance with the Prudential Code. Report P1
It includes targeted growth proposals designed to stimulate economic development, enhance housing delivery and improve environmental sustainability, supported by business cases and funding strategies. Report P2
Approval enables timely delivery of these initiatives, leveraging external funding where possible and ensuring long-term value for money. Report P2
What happens next
The Capital Strategy will be incorporated into the 2026/27 budget-setting process and the Medium Term Financial Strategy. Report P6
Detailed business cases for major projects will be prepared and reported back to the Committee. Report P6
Funding confirmation and procurement outcomes will be monitored and presented at key gateways. Report P6
The money
- £7.677m General Fund capital programme for 2026/27 to 2029/30 Report P3
- £32,303m Regeneration programme total Report P3
- £25.0m Brentwood Centre redevelopment within the regeneration programme Report P3
- £1.625m Growth proposed in the report Report P4
- £62k Approximate annual revenue cost per £1m borrowed at current interest rates Report P12
Options considered
- Chosen: Update the capital programme within existing resource constraints. Set out in the report as the basis for the update Report P7
- Noted: Add new schemes if specific additional resources are identified. Identified as a possibility within resource constraints Report P7
- Noted: Consider alternative options for new capital spending as part of budget setting. To be considered in the light of available funding and overall financial position Report P8
Implications
- Financial: The capital programme will be funded through capital receipts, reserves and borrowing; the sale of Childerditch Industrial Estate has reduced reliance on borrowing. Report P12
- Financial: Projects requiring borrowing will incur revenue implications through interest and MRP charges, with each £1m borrowed costing approximately £62k annually at current interest rates. Report P12
- Risk: Key risks include cost escalation, income underperformance, interest rate volatility and political risk from elections; mitigation includes early grant agreements, fixed borrowing rates, sinking funds and stakeholder engagement. Report P14
- Equalities: An Equality Impact Assessment concluded that schemes will be positive for a range of communities and groups, including improved play park provision, disabled facilities grants, affordable accommodation and community or sports facilities. Report P20, P21, P22
- Equalities: The Council must have due regard to the Public Sector Equality Duty under s.149 of the Equality Act 2010. Report P16, P17, P18
- Climate: The updated capital programme is expected to deliver a positive contribution to carbon reduction objectives, with schemes to be assessed for environmental impact and adaptation. Report P27, P28
- Legal: There are no legal implications other than the requirement to update the capital programme and approve strategies prior to the start of each financial year. Report P11
- Other: The programme is expected to support health, wellbeing and community safety through investment in public spaces, leisure facilities, housing infrastructure, lighting and secure design. Report P24, P25
Who and where
- Brentwood residents, including vulnerable individuals and families Report P20, P21, P22
- Children, young people and families using play parks Report P22
- Local businesses and supply chains Report P34, P35
- Parish councils and partner organisations Report P32
Timeline
- 22 September 2022: Assets, Projects & Strategy Committee approved capital investment in regeneration schemes Report P46
- 20 September 2023: Assets, Projects & Strategy Committee approved strategic asset projects update Report P43
- 18 September 2024: Assets, Projects & Strategy Committee approved Baytree Centre redevelopment implications Report P41
- 13 February 2025: Full Council approved Budget & Capital Programme 2025/26 Report P39
- 2025-12-03: Assets, Projects & Strategy Committee approved the draft Capital Strategy 2026/27 to 2029/30
- 2026/27: Capital Strategy to be incorporated into the budget-setting process and MTFS Report P6
Plain English for the jargon
- MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document
- MRP: Minimum Revenue Provision, the revenue charge set aside to repay borrowing
- PSED: Public Sector Equality Duty under s.149 of the Equality Act 2010
- EIA: Equality Impact Assessment