Assets, Projects & Strategy Committee, Wednesday 3 December 2025 at 7.00pm

Brentwood Centre Master Plan and Business Case

Approved Committee 8 papers

AI summaryBrentwood Council's Assets Committee approves Option 3 to redevelop and refurbish the Brentwood Centre, with a £25m scheme to come back to committee in March 2026 for final sign-off.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to final business case in March 2026
Money£25,000,000 estimated total cost£23m from council, £2m grant funding expected
What happens nextFinal business case to March 2026 committeePlanning application due March 2026
Who it affectsBrentwood Centre users and residentsIncludes new 3G pitches, fitness suite, spa

What was decided

The committee approved Option 3: partial redevelopment of the main building, three new 3G pitches, enhanced car parking and additional informal leisure spaces, subject to the budget and a detailed business case being agreed at a future meeting in March 2026. Report P1, 3.6, 3.7

Delegated authority was granted to the Director of Assets and Investment, in consultation with the committee chair, to submit a planning application, approve the procurement strategy, and negotiate variations to the existing leisure services agreement with Everyone Active Ltd. Report P2

The committee recommended to Council that the capital budget proposal be included in the 2026-2027 capital programme, funded by capital receipts from the sale of Childerditch, subject to the final business case in March 2026. Report P3, P82

Why

The current Brentwood Centre is ageing, with parts of the building needing significant modernisation, and is the only pay and play leisure facility in the borough, attracting over 350,000 visits a year. Report 1.4, 1.7, 2.3

There is a documented shortfall of 8 third-generation (3G) football pitches in the borough, and a strategy states the site is key for leisure investment. Report P25, P26

Officers recommend Option 3 over a full rebuild because replacing both swimming pools and the International Hall would take longer, cause more disruption, and far exceed the available budget. Report 3.7

What happens next

Officers will bring the final detailed business case, cost plan and programme of works to the Assets, Projects and Strategy Committee in March 2026. Report P5

A planning application is scheduled to be submitted in March 2026, with a decision expected in June or July 2026, subject to pre-application discussions on Green Belt, sport facility replacement, surface water flooding and traffic impacts. Report P62, 7.2, 7.4

Pool hall refurbishment works are due to start from 5 January 2026, and capital budget approval by full Council is scheduled for 11 February 2026. Report P61, P62

The money

  • £25,000,000 Estimated total cost of the Brentwood Centre redevelopment project Report P82
  • £2,000,000 Anticipated grant funding towards the project Report P82
  • £23,000,000 Total funding required from the Council for the project Report P82
  • £1,024,000 Budget already allocated for the pool and changing rooms refurbishment from modernisation funding Report P81
  • over £2m Current annual social value delivered by the centre, expected to rise after redevelopment Report 2.5

Options considered

  • Chosen: Option 3: Partial redevelopment and refurbishment of the Brentwood Centre, plus 3G pitches and car park reconfiguration. Recommended as the preferred option. Avoids the longer timeline, greater disruption and higher cost of a full rebuild, and fits the available budget. Report P1, 3.6, 3.7
  • Rejected: Procurement Option 1: Council directly procures a contractor and carries out all works itself. Requires significant council resource to manage multiple contracts and co-ordinate works, with risk of disputes with Everyone Active over the Authority Change process. Report P65, P67, 9.2
  • Chosen: Procurement Option 2: Council funds the project and appoints Everyone Active under a development agreement to deliver the centre works, with the Council procuring the 3G pitches and car park. Recommended as it allows delivery at pace, transfers day-to-day build management risk, and lets the Council focus on the 3G pitches and car parking. Report P66, 9.2
  • Rejected: Do nothing. Centre is ageing and the only pay and play facility in the borough, with documented shortfalls in facilities. Report P22, 1.7, 2.3
  • Rejected: Refurbishment only of the leisure centre. One of the four feasibility options but not the recommended one. Report P22
  • Rejected: Full redevelopment including the Brentwood Centre event hall (Option 4). Costs, timeline and disruption would not meet the Council's aims and would far exceed available budget. Report 3.7

Implications

  • Financial: Estimated £25m project cost, with £23m to come from council capital receipts (including from the sale of Childerditch) and £2m in expected grant funding. Football Foundation grant for 3G pitches is not guaranteed; if it fails, the 3G pitch element will be reconsidered. Report P82, P83
  • Legal: Recommendations are within the Council's powers under the Local Government (Miscellaneous Provisions) Act 1976, Localism Act 2011 and Local Government Act 1972, and the Council must continue to meet its best value duty and procurement rules, including potential Procurement Act 2023 implications. Report P74, P75, P76, P77
  • Equalities: An Equality Impact Assessment has been undertaken and will be refined as the project develops, with the redevelopment intended to provide inclusive and accessible facilities for all ages. Report P80, P90, P89
  • Climate: Some of the building will be demolished and replaced with a more energy efficient extension to reduce carbon footprint, with construction methods being designed to reduce environmental impact, supporting the Council's aim to be carbon neutral by 2030. Report P93, P94, P95
  • Risk: Key risks identified are planning, cost overruns, funding gaps and stakeholder opposition; the project will be managed through stage gateways, a project board and monthly highlight reports. Report 4.1, P44, 10.1, P72

Who and where

  • Users of the Brentwood Centre, including the 350,000 annual visitors Report 2.3
  • Brentwood Town Football Club, who have a 25-year lease from August 2024 and a potential later-phase expansion zone Report 1.3, 1.6
  • Everyone Active Ltd, the leisure operator on a 15-year management contract from 1 April 2025 (with possible 5-year extension) Report P2
  • Local football clubs and pitch users, given a borough-wide shortfall of 8 3G pitches Report P26
  • Brentwood Council residents, as the project will be funded by capital receipts from the sale of Childerditch Report P82
  • Local economy and staff: over 90% of centre staff are local and nearly 69% of users are from Brentwood postcodes

Timeline

  • 17 September 2025: Asset, Projects and Strategy Committee approval of project principles, master planning and concept design Report P61
  • 3 December 2025: Committee approves Option 3 business case to proceed to detailed design stage Report P61
  • From 5 January 2026: Pool Hall refurbishment (Phase 1) works start Report P61
  • February 2026: Football feasibility report to be considered Report P62
  • 11 February 2026: Ordinary Council capital budget approval scheduled Report P62
  • March 2026: Submit planning application Report P62
  • March 2026: Football Hub Stage 3 outline design Report P62
  • March 2026: Final detailed business case, cost plan and programme to come back to Assets, Projects and Strategy Committee Report P5
  • June/July 2026: Outcome of planning decision expected Report P62

Plain English for the jargon

  • 3G pitch: A third-generation artificial grass football pitch, suitable for higher levels of competitive play.
  • Everyone Active (EA): The leisure operator that manages the Brentwood Centre under a 15-year management contract starting 1 April 2025.
  • Option 3: The preferred scheme combining partial redevelopment of the main Brentwood Centre building with refurbishment, three new 3G pitches, an upgraded car park and informal leisure spaces.
  • RIBA 1: An early-stage indicative cost estimate produced under the Royal Institute of British Architects' work stages.
  • Childerditch: A site whose sale is expected to provide capital receipts to fund the Brentwood Centre redevelopment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item288

Resolved

RESOLVED UNANIMOUSLY . Resolved: R1: The committee approved the preferred option 3 as set out in the report: the redevelopment and refurbishment of the Brentwood Centre subject to approval of (i) the budget and (ii) the detailed Business Case and cost plan at a future meeting of this committee in March 2026 as detailed in this report. R2: That delegated authority is granted to the Director of Assets and Investment in consultation with the Chair of the Assets, Projects and Strategy Committee to: i) Progress to the next stage of delivery for the scheme which includes Submission of a planning application for the refurbishment and partial redevelopment of the Brentwood Centre site as set out in Appendix A to the report and for the 3G pitches and other external works including reconfiguration of the car park ii) Approve the procurement strategy for the main work packages for the Brentwood Centre, 3G pitches and the car park. iii) Negotiate and agree variations to the existing leisure services agreements with Everyone Active Ltd to include the new demise for the Brentwood Centre and the 3G pitches. R3: The committee recommended to Council that the capital budget proposal as set out in Appendix D to the report be included in the Council’s Capital Programme for 2026-2027, subject to the final detailed Business Case which will be brought back to Committee in March 2026. R4: Delegated authority be granted to the Director of Community and Health to submit any applications for external funding to support the redevelopment and enter into all necessary agreements to accept funding. R5: That Officers will bring the final detailed Business Case, cost plan and a programme of works to the Asset, Projects and Strategy Committee scheduled for March 2026. The Chair closed the meeting at 7:30pm
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Assets, Projects & Strategy Committee

Recommendation

R1. That the committee approves the preferred option 3 as set out in the report: the redevelopment and refurbishment of the Brentwood Centre subject to approval of (i) the budget and ii) the detailed Business Case and cost plan at a future meeting of this committee in March 2026 as detailed in this report.

R3. That delegated authority is granted to the Director of Assets and Investment in consultation with the Chair of the Assets, Projects and Strategy Committee to: i) Progress to the next stage of delivery for the scheme which includes Submission of a planning application for the refurbishment and partial redevelopment of the Brentwood Centre site as set out in Appendix A and for the 3G pitches and other external works including reconfiguration of the car park ii) Approve the procurement strategy for the main work packages for the Brentwood Centre, 3G pitches and the car park. iii) Negotiate and agree variations to the existing leisure services agreements with Everyone Active Ltd to include the new demise for the Brentwood Centre and the 3G pitches.

R4. That the committee recommends to Council that the capital budget proposal as set out in Appendix D is included in the Council’s Capital Programme for 2026-2027, subject to the final detailed Business Case which will be brought back to Committee in March 2026.

R5. That delegated authority is granted to the Director of Community and Health to submit any applications for external funding to support the redevelopment and enter into all necessary agreements to accept funding.

R6. That Officers bring the final detailed Business Case, cost plan and a programme of works to the Asset, Projects and Strategy Committee scheduled for March 2026. _______________________________________________________________________

Background and Supporting Information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project UpdateAppendix A Copy on its way
PDF
Project UpdateAppendix A 13 MB Download
PDF
Brentwood RisksAppendix B Copy on its way
PDF
Brentwood RisksAppendix B 56 KB Download
PDF
EQIA Brentwood Business CaseAppendix C Copy on its way
PDF
EQIA Brentwood Business CaseAppendix C 125 KB Download
PDF
Brentwood Centre Master Plan and Business CaseReport 150 KB DownloadRead as text
PDF
Brentwood Centre Master Plan and Business Case_v1Report Copy on its way

At this meeting

Whole meeting

On this subject at Brentwood

Search all
  1. Brentwood Centre Master Plan and Business CaseThis decision
  2. Brentwood Centre Progress UpdateNoted
  3. Brentwood Centre Swimming Pool EnhancementsApproved
  4. Leisure Contract - Brentwood Centre and Hartswood Pavilion in King George's Playing FieldsAgreed
  5. Brentwood Centre ProcurementNoted
  6. Brentwood Leisure Centre - EXEMPTDecided

More from Brentwood Assets, Projects & Strategy Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Brentwood Borough Council Response to Proposed reforms to the National Planning Policy Framework (NPPF) and other changes to the planning system, 2025RESOLVED UNANIMOUSLY. Resolution: R1: Members approved the draft response to the Government’s consultation on propose... Approved Open
11 Mar 2026 Compliance Dashboard Quarterly UpdateRESOLVED UNANIMOUSLY. Resolution: R1: Members noted the update and actions taken to date. Noted Open
11 Mar 2026 2025-26 Quarter 3 PerformanceRESOLVED UNANIMOUSLY. Resolution: R1: Members received and noted the Quarter 3 2025-26 Performance Report, which prov... Noted Open
11 Mar 2026 Brentwood Centre Progress UpdateRESOLVED UNANIMOUSLY. Resolutions: R1: Noted the progress to date on the redevelopment and refurbishment of the Brent... Noted Open
11 Mar 2026 Asset Management Strategy - Action Plan UpdateRESOLVED UNANIMOUSLY . Resolutions: R1: The Committee noted the progress on the Priority Action Plan as set out in th... Noted Open