What was decided
Additional works up to £495,786 were approved for inclusion in the pool refurbishment programme at the Brentwood Centre.
The extra cost is to be funded by bringing forward £242,189 from the main build budget and increasing the Phase One refurbishment budget by £253,597, reducing the main build budget from £25,000,000 to £24,757,811.
The Director of Assets and Investment was given delegated authority to include the work packages and the final contract sum of £1,519,786 in a deed of variation to the original Leisure Management Agreement with Everyone Active.
Why
The committee considered additional identified works as outlined in the report for the pool refurbishment programme.
What happens next
The Director of Assets and Investment will finalise a deed of variation with Everyone Active covering the additional work packages and the final contract sum of £1,519,786.
The money
- £495,786 Additional identified works approved for the pool refurbishment
- £242,189 Brought forward from the main build into the pool refurbishment element
- £25,000,000 Original main build budget before reduction
- £24,757,811 Main build budget after reduction of £242,189
- £253,597 Increase in the Phase One pool refurbishment programme budget
- £1,519,786 Final contract sum to be included in the deed of variation
Implications
- Legal: A deed of variation is required to amend the existing Leisure Management Agreement with Everyone Active.
- Financial: Funding is reallocated between the main build and the pool refurbishment budgets, with no net new spend identified in the decision wording.
Who and where
- Brentwood Centre swimming pool users
- Everyone Active, as the existing leisure management contractor
- The council's main build and Phase One refurbishment budgets
Timeline
- 2026-02-25: Committee approved the additional works and delegated authority for the deed of variation
Plain English for the jargon
- Deed of variation: A legal document that changes the terms of an existing contract.
- Everyone Active: The leisure management contractor holding the existing Leisure Management Agreement with the council.
- Phase One pool refurbishment: The first stage of the swimming pool improvement works at the Brentwood Centre.
- Leisure Management Agreement: The contract between the council and Everyone Active for running the Brentwood Centre.