School Modernisation Programme: Outcome of Consultation on Proposal to Make a Regulated Alteration in the Form of an Enlargement to Brynmenyn Primary School and Relocate it into a New Building on Surplus Land Adjacent To Coleg Cymunedol Y Dderwen
ApprovedExecutive1 paper
Cabinet approved this item on Tuesday 16 June 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED : That Cabinet: 1. Considered the outcome of the consultation with all parties; 2. Approved the consultation report for publication; 3. Authorised the publication of a Public Notice on the proposal with a modified opening date of 1 st January 2018. </AI14> <AI15>
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1This report is to inform Cabinet of the outcome of the consultation on the proposal to make a regulated alteration in the form of an enlargement to Brynmenyn Primary School and relocate it into a new building on surplus land adjacent to Coleg Cymunedol Y Dderwen (CCYD) - and to present to Cabinet the findings of the consultation in a detailed consultation report (see Appendix A) intended for publication.
2 Connection to Corporate Plan / Other Corporate Priorities
2.1The school modernisation programme supports many of the corporate priorities and in particular:
• Working Together To Raise Ambitions And Drive Up Educational Achievement
2.2We aim to help all young people to thrive and make the best of their talents. As part of this, there is a serious need to modernise our schools.
Background
3.1In September 2006, the Council adopted a policy of providing continuity of education from ages 3 to 11 where possible. On 3rd March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend; five key principles were set out to inform the organisation and modernisation of our schools:
i. Commitment to high standards and excellence in provision. ii. Equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend. iii. Inclusive schools, which cater for the learning needs of all their pupils. iv. Community focussed schools, where the school actively engages with its local community. v. Value for money.
3.2The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice. 3.3 The principles which are particularly relevant in the context of this proposal concern the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness and the provision of local schools, planning new provision to reflect changes in the distribution of the population.
3.4There is growing pressure on the number of school places in the Valleys Gateway Area of the County Borough due to recent, current and planned housing developments in the area. The three primary schools serving the Valleys Gateway area are:
• Brynmenyn Primary School • Bryncethin Primary School • Tondu Primary School
3.5The relocation and enlargement of Brynmenyn Primary is considered to be the preferred means available to the Council in order to address growing pressure on the number of school places in the Valleys Gateway Area.
3.6The relocation and enlargement, should it go ahead, would also require changes to the existing catchments of the three schools to take the pressure off both Bryncethin Primary and Tondu Primary. Consultation on catchment area changes would be undertaken as a separate exercise and would not affect those pupils already attending either of those primary schools. This would mean that Bryncethin Primary could continue as it currently is with 235 places 4-11 plus nursery and Tondu Primary could be brought together on one site, as a one form entry school.
3.7This report outlines the responses to the consultation and seeks approval to continue the process to the next stage.
4 Current situation
4.1In order to progress the proposal, consultation exercises were carried out between 23rd March 2015 and 5th May 2015 with staff, governors, parents, pupils and also the wider community in accordance with the statutory School Organisation Code. A copy of the consultation document was also made available during this time on the Councils website:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
School Modernisation Programme: Outcome of Consultation on Proposal to Make a Regulated Alteration in the Form of an Enlargement to Brynmenyn Primary School and Relocate it into a New Building on Surplus Land Adjacent To Coleg Cymunedol Y DderwenReport
712School Modernisation Programme: Outcome of Consultation on Proposal to Make a Regulated Alteration in the Form of an Enlargement to Brynmenyn Primary School and Relocate it into a New Building on Surplus Land Adjacent To Coleg Cymunedol Y DderwenThis decision
School Modernisation Programme: Outcome of Consultation on Proposal to Make a Regulated Alteration in the Form of an Enlargement to Brynmenyn Primary School and Relocate it into a New Building on Surplus Land Adjacent To Coleg Cymunedol Y DderwenThis decision
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.