That Cabinet: 1. Approved for the Corporate Director-Communities to enter into a trial arrangement with Bellavail (IMS) where they are engaged to bring the highways for an identified area or areas to be decided upon by the Corporate Director - Communities to an adoptable standard utilising the bond supporting the main agreement, and in order for the trial to take place Cabinet authorise under Rule 3.6 waiver of the Council’s Contract Procedure Rules to enter into the agreement with Bellavail (IMS). 2. Upon completion of the trial the results of the trial be reported back to Cabinet and if the trial is deemed to be successful and the service offered is still required then arrangements will be made for tender documents to be prepared and issued in accordance with the appropriate procurement processes to engage the services of a specialised consultancy service.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
STATUTORY HIGHWAY AGREEMENTS– UN-ADOPTED ROADS AND PATHS THAT ARE SUBJECT TO SUCH AGREEMENTS
1. Purpose of Report.
1.1To seek approval to trial the services of a specialist consultant to complete works in connection with selected outstanding statutory highway agreements so that roads and paths that are subject to such Agreements within developments can be adopted by the Highway Authority without having to use public funds.
2. Connection to Corporate Improvement Plan / Other Corporate Priority.
2.1The current Corporate Improvement Plan 2013-2017 has six Improvement Priorities. The first of these is to “improve the local economy”. In order to do this, it is necessary to have a functioning, well-maintained highway network to facilitate movement of people and goods.
2.2The sixth Improvement Priority in the Corporate Improvement Plan is to “work together to make the best use of our resources”. One of the ways that the Plan says we will achieve this is to “explore innovative and flexible ways of delivering services, including commissioning.” As a result of current staffing levels and current workload, it is not possible to “call in the Bond” as required by the signed statutory highway Agreements for problem sites using our own staff. Consequently, it will be necessary to seek the services of an external specialist Consultant in such matters, in order to achieve any progress for such sites.
3. Background.
3.1The Council has powers as a Highway Authority under Section 38 of the Highways Act 1980 (Section 38 Agreements) to enter into Legal Agreements with developers (or other persons) to adopt highways (roads and/or paths) that they build as part of their developments for future maintenance at public expense.
3.2The criteria for the adoption of highways include that they must be of sufficient public utility, constructed to agreed standards, maintained for the maintenance period by the developer, and be used as a highway during the maintenance period.
3.3Those elements of a highway may include carriageways cycle-ways, footways, verges, service strips, street lighting and highway drains where no public sewer has been provided.
3.4A Section 38 Agreement provides for a developer to bear the costs of the construction and maintenance of the highway and other appropriate matters. A bond or cash deposit is deposited to cover the cost of bringing the road up to an adoptable standard should a developer become insolvent or is otherwise unable to meet their obligations under the Agreement.
3.5Most residents in buying a new property seek assurance via their solicitors that the highway will eventually be adopted under the mechanism of a Section 38 Agreement. The existence of a Section 38 Agreement and Bond is revealed on a Local Land Charges Search which is part of the conveyancing process.
3.6It is prudent for the Council in its capacity as the Highway Authority not to adopt a highway until a development is completed. This ensures that wear or damage through the use of the road by construction traffic is not rectified at the public expense but by the developer.
3.7The time taken for a highway to become adopted and maintainable at the public expense is dependent upon the developer and how long it takes for a development to be completed to the stage that the highway is of adoption standard. In some cases a small development may only take a matter of months to complete and the highway may then be ready for adoption in a short timeframe. In other cases with much larger developments it can be several years before the roads are ready for adoption. In addition the economic climate can have an impact on the speed with which developments are brought to the stage when the highway can be adopted.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.