Resolved
That Cabinet approved the award of contract to Contractor 5 (Total Ground Care Ltd) for the delivery of Service Level 2, as detailed in the report.
Cabinet approved this item on Tuesday 15 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet approved the award of contract to Contractor 5 (Total Ground Care Ltd) for the delivery of Service Level 2, as detailed in the report.
BRIDGEND COUNTY BOROUGH COUNCIL
REPORT TO CABINET
15 MARCH 2016
REPORT OF THE CORPORATE DIRECTOR COMMUNITIES
HIGHWAY & OPEN SPACE GRASS CUTTING ARRANGEMENTS 2016
1. Purpose of Report.
1.1The purpose of the report is to seek Cabinet approval :
i. for the preferred service level for highway and open space grass and hedge cutting, and ii. for the award of the contract for the provision of grass and hedge cutting services, as detailed in this report.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1The review and subsequent outsourcing of the highway and open space grass cutting service provided by the Council, formed part of the Communities Directorate response to reconciling operational levels of service with the financial settlement at the time and was in accordance with the improvement priorities detailed in the Corporate Plan under Priority 6 - (Working Together to Make Best Use of Our Resources). This report for the second award of contract for grass and hedge cutting also falls under Priority 6 – Best use of resources.
3. Background.
3.1As part of the Medium Term Financial Strategy (MTFS) for 2015/16 the Grounds Maintenance and Bereavement Services had a savings target of £437,000 to achieve. In seeking to meet this target a comprehensive review of the staffing structures and management arrangements within the Parks and Playing Fields Service area was initiated. However, it was not possible to achieve all of the savings required from this structural review alone, and it was, therefore, necessary to also review operational practices and procedures. Part of this review identified the cutting of highway and open space grass across the County Borough as an area where savings could be made. Following a review of grass cutting arrangements, tenders were sought from selected contractors for a range of service level options.
3.2The cutting of open space is to all intents and purposes driven by aesthetic considerations. In extreme circumstances i.e. little or no cutting taking place, health and safety concerns may arise i.e. fire risk in dry summers. The cutting of grass alongside highways - high speed roads, is driven more by safety considerations - maintaining sight lines, vision splays etc., with aesthetics being a secondary consideration. There is no stipulation in highway legislation of minimum maintenance levels. The obligation is simply to implement a regime of maintenance. The level of maintenance adopted is, in principle, a decision for the Council. That said, best practice based on the general requirements of codes of practice are available and no doubt reference will be made to the relevant recommendations these contain should any incident occur which results in legal action against the Council.
3.3Cabinet on the 3rd February 2015, made a decision to award the contract to the lowest priced tenderer and to reduce the service level from 9 annual urban cuts and 5 annual rural cuts to 7 and 4 cuts respectively – a number of areas were also identified where more ‘relaxed’ regimes of maintenance could be used ie meadow and herbaceous regimes. This change resulted in a net budget saving to the Council of approx. £132,000 – approximate contract value of £157,000. This along with other measures identified by the review would achieve the balance of the savings required to meet the saving target without undue impact on the remainder of the service area.
3.4The performance of the contract on balance was acceptable, however, the contractor, whilst keen to continue providing the service for the Council, was of the opinion that he was unable to do this for a second year on the basis of the existing contract.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways and Open Space Grass Cutting Arrangements 2016Report | 83 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.