Resolved
That Cabinet approved the appropriation of land shown hatched red on the plan in appendix 1 to the report which included land forming part of an open space currently held for a leisure function for educational purposes.
Cabinet approved this item on Tuesday 12 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet approved the appropriation of land shown hatched red on the plan in appendix 1 to the report which included land forming part of an open space currently held for a leisure function for educational purposes.
1.1To consider the appropriation of land that is currently held for a Leisure Function for educational purposes at Bettws Road, Bettws that currently forms part of an open space.
2. Connection to Corporate Improvement Plan / Other Corporate Priorities
2.1The school modernisation programme supports the following corporate priorities:
Smarter use of resources Supporting a successful economy
2.2In 2006, Cabinet considered a report entitled ‘Learning Communities: Schools of the future – Strategy, Principles, Policy and Planning Framework’ and agreed to support the report as the basis for taking forward proposals for school modernisation. The framework was subsequently adopted by the Council in September 2006 (‘Learning communities – schools of the future – strategy, principles, policy and planning framework’). 2.3 On 3rd March 2015, Cabinet approved revised principles which were adopted as a framework for school organisation in Bridgend (Cabinet Report 3rd March 2015 ‘Principles Document”) 2.4 The framework includes 5 key principles that inform the organisation and modernisation of our schools:
1. Commitment to high standards and excellence in provision
2. Equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend
3. Inclusive schools, which cater for the learning needs of all their pupils
4. Community focused schools, where the school actively engages with its local community
5. Value for money Particularly relevant to this report are 1 and 5. The framework provides that primary schools need to be large enough to secure the full range of necessary provision and that value for money and efficiency are achieved.
3.1The land hatched in red on the plan contained in Appendix 1 was acquired by the former Ogmore & Garw Urban District Council on 13 December 1957. An agreement was reached in late 1969 / early 1970 between Ogmore & Garw UDC and Glamorgan County Council that the land be developed for joint use by both Authorities as playing fields.
3.2Council records indicate that Betws Primary School has had exclusive use of the open space during school hours for school activities since 1970.
3.3The Council’s Parks Department have inspected and maintained the play equipment located within the land shown hatched red on the attached plan and Betws Primary School has maintained the playing fields.
3.4On 31st March 2015 Cabinet agreed to proceed with a replacement of Betws Primary School on the playing fields of the existing school site. On 1st September 2015 Cabinet approved the proposal to relocate Ysgol Gynradd Gymraeg Cwm Garw to the existing Betws Primary School site with effect from September 2018.
3.5A planning application for the new schools (reference P/15/791/BCB) was submitted on 25th November 2015 that encompassed both the existing primary school site and the adjacent school playing fields and open space. As part of the planning process an objection has been received to the proposed loss of public open space.
3.6Due to the existing dual use of the land, as playing fields and open space, appropriation of the land under Section 122 (1) Local Government Act 1972 for educational purposes was recommended by the Council’s legal officer, as the land is currently held for Leisure purposes but used for educational purposes during the school day, and informal recreational space outside school hours.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
160412 9 School Modernisation Programme Land at Bettws AppendixAppendix | 399 KB | Download |
PDF |
School Modernisation Programme: Outcome of Consultation on Appropriation of Land for Educational Purposes at Bettws Road, BettwsReport | 89 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.