Resolved
That the projected revenue and capital outturn position for 2016-17.
Cabinet decided this item on Tuesday 26 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the projected revenue and capital outturn position for 2016-17.
3.1On 10th March 2016, Council approved a net revenue budget of £254.891 million for 2016-17, along with a capital programme for the year of £43.553 million, which was recently revised to £49.530 million. As part of the Performance Management Framework, budget projections are reviewed regularly and reported to Cabinet on a quarterly basis. The delivery of agreed budget reductions is also kept under review and reported to Cabinet as part of this process.
4.0Current Situation
4.1Summary financial position at 30th June 2016.
4.1.1 The Council’s net revenue budget and projected outturn for 2016-17 is shown in Table 1 below. Table 1- Comparison of budget against projected outturn at 30th June 2016
Directorate/Divisions Revised Projected Projected Over Budget Over / (Under) Projected / (Under) Spend Outturn Spend 2016-17 2016-17 Qtr 1 2016-17 Qtr 1 2015-16 £'000 £'000 £'000 £'000 Directorate
Education and Family Support 108,202 108,489 287 7 Social Services and Wellbeing 59,650 59,899 249 60 Communities 24,677 25,083 406 145 Operational and Partnership Services 14,900 14,773 (127) (79) Chief Executives and Finance 4,318 4,067 (251) (140) Total Directorate Budgets 211,747 212,311 564 (7) Council Wide Budgets
Capital Financing 10,128 10,128 0 0 Precepts and Levies 6,959 6,959 0 0 Sleep Ins 800 800 0 0 Council Tax Reduction Scheme 14,304 13,904 (400) 0 Insurance Costs 1,559 1,559 0 0 Building Maintenance 900 900 0 (100) Centrally held Budget Pressures 1,394 1,394 0 0 Other Corporate Budgets 7,100 7,100 0 0 Total Council Wide Budgets 43,144 42,744 (400) (100)
Total 254,891 255,055 164 (107)
4.1.2 The overall projected position as at 30th June 2016 is a net over spend of £164,000, comprising £564,000 net over spend on directorates and £400,000 under spend on corporate budgets. A detailed analysis of the more significant projected under and over spends is set out in section 4.3.
4.1.3 The net budget for the financial year assumes full implementation of the current year budget reduction requirements across the Council’s budget which amount to £7.477 million. Where proposals to meet this requirement have been delayed or are not achievable directorates have been tasked with identifying alternative proposals to meet their requirements such as vacancy management, or bringing forward alternative budget reduction proposals.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
160726 4 Appendix 1 2015-16 Budget Reductions Monitoring Qtr 1Appendix | 77 KB | Download |
PDF |
160726 4 Appendix 2 2016-17 Budget Reduction Monitoring Qtr 1Appendix | 97 KB | Download |
PDF |
160726 4 Appendix 3 Revenue Monitoring Qtr 1Appendix | 61 KB | Download |
PDF |
160726 4 Appendix 4 Capital Monitoring Qtr 1Appendix | 110 KB | Download |
PDF |
Budget Monitoring: Quarter 1 2016-17Report | 130 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.