That Cabinet: 1) Delegated authority to the Corporate Director, Education and Family Support to award the Contract to the bidder submitting the most economically advantageous tender, subject to the tender price being acceptable to the S151 Officer, and subject to receipt of Welsh Government funding approval. 2) Subject to the Contract being awarded in accordance with paragraph 8.1.1. of the report, delegated authority to the Corporate Director, Education and Family Support to enter into a construction Contract with any relevant ancillary agreements thereto, in consultation with the Director of Operational and Partnership Services, and arrange for execution of the same on behalf of the Council. 3) Noted that Cabinet will in due course receive an Information Report detailing the outcome of the tender process.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1Delegate authority to the Corporate Director, Education and Family Support to award the contract to the bidder submitting the most economically advantageous tender for the construction of the Betws Primary School and Ysgol Gynradd Gymraeg Cwm Garw, i.e. Garw Valley South, subject to the tender price being acceptable to the S151 Officer and receipt of Welsh Government funding approval;
1.2Delegate authority to the Corporate Director, Education and Family Support to enter into a construction contract with the successful tenderer and any relevant ancillary agreements in consultation with the Director of Operational and Partnership Services and arrange for execution of the same on behalf of the Council;
1.3note that an information report will be presented to Cabinet in due course, advising of the outcome of the tender process.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1This report supports the following priorities in the Corporate Plan 2016 - 2020:
Supporting a successful economy, and Smarter use of resources.
2.2The Council aims to help all young people to thrive and make the best of their talents. One of the barriers to achieving this aim that the Council has identified is a serious need to modernise our schools.
2.3In March 2015, the Council set out 5 key principles to inform the organisation and modernisation of our schools:
1. Commitment to high standards and excellence in provision 2. Equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend 3. Inclusive schools, which cater for the learning needs of all their pupils 4. Community focussed schools, where the school actively engages with its local community 5. Value for money
Background
3.1On the 16th September 2014 Cabinet agreed to participate and be a signatory to the South East Wales Schools Capital Procurement Framework (SEWSCAP Framework) for a four year period, commencing April 2015.
3.2On 31st March 2015 Cabinet agreed to proceed with a replacement of Betws Primary School on land which has been used as the playing fields of the existing school site, and which is also an area of public open space. On 1st September 2015 Cabinet approved the proposal to relocate Ysgol Gynradd Gymraeg Cwm Garw to the existing Betws Primary School site with effect from September 2018.
3.3A planning application for the new schools (reference P/15/791/BCB) was submitted on 25th November 2015.
3.4On 16th February 2016, Cabinet approved the publication of a S122(2A) Local Government Act 1972 Notice to consult on the appropriation of land at Betws Primary School in order to change the use from public open space to educational purposes.
3.5As the JCT Standard form of Contract with Quantities had been omitted from the SEWSCAP Framework, on 15th March 2016 Cabinet approval was received to undertake a separate OJEU compliant tendering exercise for the construction of the Garw Valley South schools.
3.6In addition, and on the same date, subject to the successful appropriation of land at Betws Primary School and obtaining of appropriate planning permission in respect of the planning application, approval was given to issue an invitation to tender for the construction of the new schools.
4. Current Situation
4.1Upon completion of the consultation process in relation to the appropriation of land at Betws Primary School, Cabinet approval was received on 12th April 2016 to change the purpose of the land held for a leisure function to educational purposes.
4.2Planning approval in respect of the scheme was received on 5th May 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.