That Cabinet a greed the contract sum submitted by BAM Construction Ltd for the construction of Brynmenyn Primary School, and approved the awarding of the contract to BAM Construction Ltd as the main contractor, subject to: (a) Obtaining Welsh Government funding approval and receipt of the appropriate funding in due course, and the final contract being approved by the Corporate Director Education and Family Support, in consultation with the Corporate Director Operational and Partnership Services and the Section 151 Officer.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is to seek Cabinet approval to accept the contract sum provided by BAM Construction Ltd for the construction of Brynmenyn Primary School and approve the awarding of the contract, subject to Welsh Government funding approval.
2. Connection to Corporate Plan/Other Corporate Priorities
2.1The school modernisation programme supports many of the corporate priorities, in particular:
Supporting a successful economy Smarter use of resources
Background
3.1On 3rd March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend. Five key principles were set out to inform the organisation and modernisation of our schools:
Commitment to high standards and excellence in provision. Equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend. Inclusive schools, which cater for the learning needs of all their pupils. Community focussed schools, where the school actively engages with its local community. Value for money.
3.2The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice.
3.3The principles which are particularly relevant in the context of this project are the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness (“narrowing the gap between the most and the least expensive provision currently”).
3.4In order to relieve the pressure on primary school places in the Valleys Gateway area, Cabinet gave approval for statutory procedures to be followed to make a regulated alteration in respect of an enlargement to Brynmenyn Primary School and also gave approval for the proposed enlarged primary school to be relocated from its existing site at Bryn Road, Brynmenyn CF32 9LA to the site adjacent to Coleg Cymunedol Y Dderwen, Heol yr Ysgol, Ynysawdre CF32 9EL. The relocation of the school was not subject to statutory procedures as the proposed school site would be less than 1 mile from the existing school site.
3.5The statutory process was undertaken as prescribed by the School Organisation Code. There were no objections to the proposal and on 1st September 2015, Cabinet determined to implement the proposal to open the enlarged primary school with effect from 1st January 2018. Subsequently a decision notice was issued in this regard on 7th September 2015.
3.6Cross directorate meetings were held to determine the best way forward regarding the design and construction of the school. Officers agreed that the preferred option would be to utilise the existing, South East Wales Schools Capital Procurement Framework (SEWSCAP). Cabinet approved the use of the SEWSCAP framework in their meeting held on 27th October 2015 and Cabinet authorised the Director of Education and Transformation to determine the appropriate form of the contract for the design and build process based upon the recommendation of the appointed project manager and cost manager.
3.7It was agreed in due course that the Council would pursue an NEC3 Option A fixed cost contract. The appointed project manager from Chandler KBS and cost manager from Mott Macdonald would look after the Council’s interest in the project and manage the NEC contract on a day to day basis.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
1005School Modernisation Programme: Outcome of the Second Stage of the Tender Process for the Design and Construction of Brynmenyn Primary SchoolThis decision
School Modernisation Programme: Outcome of the Second Stage of the Tender Process for the Design and Construction of Brynmenyn Primary SchoolThis decision
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.