Coychurch Crematorium Joint Committee approved this item on Wednesday 3 May 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1) The Joint Committee confirmed and approved the revenue budget and capital expenditure to be adopted for 2017-18. 2) The Joint Committee approved the increase in fees and charges with effect from 1 April 2017 outlined in Appendix 1.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is to inform the Joint Committee of the projected financial performance for the Crematorium for 2016-17, and to obtain approval from the Joint Committee for the proposed budget and fees and charges for 2017-18.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1There are no direct connections to the Council’s Corporate priorities, although the ongoing monitoring of budget and performance form part of ensuring a better use of resources.
Background
3.1The 2016-17 Revenue Budget was approved by the Committee at its meeting on 4 March 2016. The current budget position and projected outturn for 2016-17 is outlined below, together with the proposed budget for 2017-18.
4. Current Situation
Estimated Revenue Outturn 2016-17
4.1Table 1 below shows the financial position at 31 January 2017 and the projected outturn for 2016-17. Table 1- Comparison of budget against projected spend at 31st January 2017.
4.2When the budget was set, there was an anticipated budget surplus of £122,000. The actual projected outturn as at the end of January is a surplus of £258,000 which will require a transfer to earmarked reserves.
An explanation of the main variances between the Budget and Projected Outturn is detailed below:
The underspend of £57,000 on Premises is made up of Planned Maintenance (£40,000), Gas (£13,000) and Business Rates (£2,000). The underspend in Planned Maintenance is due to a delay in the Organ Repairs (£20,000), Landscaping (£10,000), and underspend on the Flat Roof (£8,625). The Organ Repairs are now scheduled to take place in 2017-18.
The underspend of £35,000 on Supplies, Services & Transport is made up of savings on Items for Resale (£33,000) and Audit Fees (£4,900). These are offset by small overspends of Uniform/Protective Clothing (£2,000) and Printing (£1,000).
Also included in the projected outturn for Supplies, Services & Transport is the write off of an unidentified debtor of £2,356, which has been recorded in the accounts since 1999.
Income has been higher than budgeted by £66,000 resulting from increased cremation fees (£60,000) and income in relation to the sale of items (£6,000). The BCBC contribution is calculated using salary costs of two staff members. As the new structure wasn’t in place until June, the charge will be less (£1,000) than was originally budgeted. 2017-18 Proposed Budget
4.3The following table shows the proposed revenue budget for 2017-18
Table 2 – Proposed Budget 2017-18
Category Budget 2017-18 £’000 Expenditure Employees 311 Premises 217 Supplies, services & transport 158 Agency / contractors 90 Administration 48 Capital financing costs 429 Gross Expenditure 1,253 Income Fees & charges (1,190) Contribution from BCBC (28) Total Income (1,218) Net (Surplus)/Deficit 35 Transfer to/(from reserves) (35)
4.4The following table shows the breakdown of the Administration budget for 2017-18
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies