That the Joint Committee:- (1) Noted the projected financial performance for 2019-20. (2) Confirmed and approved the revenue budget to be adopted for 2020-21. Approved the increase in fees and charges with effect from 1 April 2020, outlined in Appendix 1 to the report.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is to inform the Joint Committee of the projected financial performance for the Crematorium for 2019-20, and to obtain approval from the Joint Committee for the Proposed Budget and Fees and Charges for 2020-21.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1This report assists in the achievement of the following corporate priority:-
Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
Background
3.1The 2019-20 Revenue Budget was approved by the Committee at its meeting on 8 March 2019. The current budget position and projected outturn for 2019-20 is outlined below, together with the proposed budget for 2020-21.
4. Current Situation / Proposal
Estimated Revenue Outturn 2019-20
4.1Table 1 below shows the financial position as at 31 January 2020 and the projected outturn for 2019-20. Table 1- Comparison of budget against projected spend as at 31 January 2020.
Budget Category Adjusted Projected Projected Actual Outturn Over (Under) Spend
4.2When the budget was set there was an anticipated budget deficit of £336,000. The projected outturn as at the end of January is a surplus of £316,000, which will require a transfer to the Crematorium’s Accumulated Surplus.
An explanation of the main variances between the Budget and Projected Outturn is detailed below:
The underspend of £14,000 on Employees is made up of a part year vacancy of the Groundsperson/Relief Crematorium Technician post, and full year vacancy of the Weekend Attendant post .
The overspend of £16,000 on Premises is made up of overspends in Planned Maintenance (£10,000), Gas (£3,000), Electricity (£4,000) and Grounds Maintenance (£2,000), which is offset by underspends on Property Insurance (£2,000) and Business Rates (£1,000).
The underspend of £10,000 on Supplies, Services & Transport is made up of an overspend on Purchase of Equipment (£2,500), being offset by underspends made on Equipment Repairs (£5,000), Uniforms/Protective Clothing (£3,000), Printing (£2,000) Security Services (£1,500) and Conference Fees (£1,000).
Table 2 below shows a breakdown of the Planned Maintenance Budget along with the Projected Outturn and Variances for 2019-20. Table 2 – Planned Capital Maintenance 2019-20
The underspend on the Flower Court Extension is due to only surveys being paid for in 2019-20. The balance of £272,000 and £300,000 for Site Lighting will be carried forward and form part of the 2020-21 Planned Capital Maintenance budget.
Income is higher than budgeted by £50,000, resulting from increased cremation fees.
2020-21 Proposed Budget
4.3The following table shows the proposed revenue budget for 2020-21:-
Table 3 – Proposed Budget 2020-21
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.