CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bridgend County Borough Council

Proposed Revenue Budget 2020-21

Noted Committee 2 papers

Coychurch Crematorium Joint Committee noted this item on Friday 6 March 2020. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

That the Joint Committee:- (1) Noted the projected financial performance for 2019-20. (2) Confirmed and approved the revenue budget to be adopted for 2020-21. Approved the increase in fees and charges with effect from 1 April 2020, outlined in Appendix 1 to the report.
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Coychurch Crematorium Joint Committee

Purpose of the report

1.1The purpose of this report is to inform the Joint Committee of the projected financial performance for the Crematorium for 2019-20, and to obtain approval from the Joint Committee for the Proposed Budget and Fees and Charges for 2020-21.

2. Connection to Corporate Improvement Objectives/Other Corporate Priorities

2.1This report assists in the achievement of the following corporate priority:-

Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.

Background

3.1The 2019-20 Revenue Budget was approved by the Committee at its meeting on 8 March 2019. The current budget position and projected outturn for 2019-20 is outlined below, together with the proposed budget for 2020-21.

4. Current Situation / Proposal

Estimated Revenue Outturn 2019-20

4.1Table 1 below shows the financial position as at 31 January 2020 and the projected outturn for 2019-20. Table 1- Comparison of budget against projected spend as at 31 January 2020.

Budget Category Adjusted Projected Projected Actual Outturn Over (Under) Spend

2019-20 1/4/19 to 2019-20 2019-20 31/1/20 £’000 £’000 £’000 £’000 329 Employees 241 315 (14) 248 Premises 220 264 16 178 Supplies, Services & 121 168 (10) Transport 102 Agency / Contractors 78 105 3 36 Administration 27 36 0 776 Capital Financing Costs 165 179 (597) 1,669 Gross Expenditure 852 1067 (602) (1,303) Fees & Charges (920) (1,353) (50) (30) BCBC Contribution (22) (30) 0 336 (Surplus)/Deficit (90) (316) (652) (336) Transfer to/(from) 90 316 652 Reserve

4.2When the budget was set there was an anticipated budget deficit of £336,000. The projected outturn as at the end of January is a surplus of £316,000, which will require a transfer to the Crematorium’s Accumulated Surplus.

An explanation of the main variances between the Budget and Projected Outturn is detailed below:

 The underspend of £14,000 on Employees is made up of a part year vacancy of the Groundsperson/Relief Crematorium Technician post, and full year vacancy of the Weekend Attendant post .

 The overspend of £16,000 on Premises is made up of overspends in Planned Maintenance (£10,000), Gas (£3,000), Electricity (£4,000) and Grounds Maintenance (£2,000), which is offset by underspends on Property Insurance (£2,000) and Business Rates (£1,000).

 The underspend of £10,000 on Supplies, Services & Transport is made up of an overspend on Purchase of Equipment (£2,500), being offset by underspends made on Equipment Repairs (£5,000), Uniforms/Protective Clothing (£3,000), Printing (£2,000) Security Services (£1,500) and Conference Fees (£1,000).

 Table 2 below shows a breakdown of the Planned Maintenance Budget along with the Projected Outturn and Variances for 2019-20. Table 2 – Planned Capital Maintenance 2019-20

Budget Projected Projected 2019-20 2019-20 Outturn Variance £’000 £’000 £’000 Organ upgrade 96 101 5 Flower Court Extension 300 28 (272) Site Lighting 300 0 (300) Flat Roof Repairs - Waiting Room 30 32 2 Mess Room Refurbishment 30 18 (12) Electricity Distribution Boards 20 0 (20) Total 776 179 597

 The underspend on the Flower Court Extension is due to only surveys being paid for in 2019-20. The balance of £272,000 and £300,000 for Site Lighting will be carried forward and form part of the 2020-21 Planned Capital Maintenance budget.

 Income is higher than budgeted by £50,000, resulting from increased cremation fees.

2020-21 Proposed Budget

4.3The following table shows the proposed revenue budget for 2020-21:-

Table 3 – Proposed Budget 2020-21

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 236 KB Download
PDF
Proposed Revenue Budget 2020-21Report 94 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 16 attended
PB
Philip BeamanOfficer, in attendance
GC
Councillor Geoff CoxCommittee Member, present
R-
Room - Committee Room 2Officer, expected
R-
Room - Committee Room 3Officer, expected
SE
Councillor Stewart EdwardsCommittee Member, present
MG
Mark GalvinOfficer, in attendance
JH
Joanna HamiltonOfficer, in attendance
GH
Councillor Geraint HopkinsCommittee Member, absent
GJ
Councillor Gwyn JohnCommittee Member, present
CJ
Cynghorydd John SpanswickCommittee Member, present
ET
Eilish ThomasOfficer, in attendance
RK
Councillor Roger K TurnerCommittee Member, present

All 16 on the meeting page

On this subject at Bridgend

Search all
  1. Proposed Revenue Budget 2020-21This decision
  2. Financial Performance 2022-23 and Proposed Revenue Budget 2023-24Noted
  3. Financial Performance 2021-22 and Proposed Revenue Budget 2022-23Noted
  4. Proposed Revenue Budget 2019-20Noted
  5. Proposed Revenue Budget 2017-18Approved
  6. Proposed Revenue Budget 2016-17Approved

More from Bridgend Coychurch Crematorium Joint Committee

All decisions
MeetingDecisionOutcome
1 Sep 2023 Approval of MinutesThat the minutes of a meeting of the Coychurch Crematorium Joint Committee dated 9 June 2023, be approved as a true a... Approved Open
1 Sep 2023 Green Flag AwardThe Committee thanked the staff and management at Coychurch Crematorium for their continued hard work and stewardship... Noted Open
1 Sep 2023 Revenue Monitoring Statement 1 April to 30 June 2023 & Annual Accounting Statement 2022-23 updateThe Committee noted and approved the Revenue Monitoring Statement, noting that there is considerable value for money ... Noted Open
1 Sep 2023 Urgent ItemsNone Decided Open
9 Jun 2023 Election of Chairperson (from Rhondda Cynon Taf County Borough Council members)That Councillor B Stephens be appointed as Chairperson of the Coychurch Crematorium Joint Committee for the ensuing y... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies