Resolved
That Cabinet approved the modification of the decision to amend the opening date of the new Pencoed Primary School from 1 April 2018 to 5 September 2018.
Cabinet approved this item on Tuesday 25 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet approved the modification of the decision to amend the opening date of the new Pencoed Primary School from 1 April 2018 to 5 September 2018.
1.1This report is to request Cabinet approval to modify the decision in respect of the opening date of the replacement Pencoed Primary School from 1 April 2018 to 5 September 2018.
2. Connection to Corporate Improvement Objectives/other corporate priorities
2.1The school modernisation programme supports many of the corporate priorities, in particular:
Smarter use of resources Supporting a successful economy
2.2On 3 March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend. The following five key principles were set out to inform the organisation and modernisation of our schools:
Commitment to high standards and excellence in provision Equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend Inclusive schools, which cater for the learning needs of all their pupils Community focussed schools, where the school actively engages with its local community Value for money
2.3The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice.
2.4The principles which are particularly relevant in the context of this proposal concern the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness and the provision of local schools, planning new provision to reflect changes in the distribution of the population.
3. Background 3.1 On 6 September 2016, Cabinet approved the proposal to make a regulated alteration to Pencoed Primary School, by relocating the school, including the Heol- y-Cyw Campus, to a new-build school on the site of Pencoed Primary School playing fields at Penprysg Road, Pencoed with effect from 1 April 2018.
3.2On 4 October 2016, Cabinet authorised the invitation of tenders for the construction of the new Pencoed Primary School.
3.3The Pencoed scheme was tendered via the SEWSCAP Framework, with tender submissions received on 13 February 2017.
3.4Of the five tenders received, only two were compliant (the remainder disqualified) and both of the compliant tenders contained tender sums significantly in excess of the construction budget available for the scheme. Consequently, on 28 February 2017, Cabinet delegated authority to the Corporate Director, Education and Family Support to conduct negotiations, with the lowest-priced tenderer, in accordance with procurement legislation.
4. Current situation
4.1It was originally anticipated that works would start on site at the end of March 2017, in order to complete the school in readiness for opening on 1 April 2018.
4.2However, delays to the commencement of construction have been incurred due to the processes associated with negotiating the construction contract tendered sum with the lowest priced tenderer down to an amount that is within the approved scheme budget.
4.3The delay in commencement has resulted in a planned start date of 17 July 2017. Based on this revised start-on-site date, the construction programme currently estimates completion as 16 July 2018. The September school opening date proposed will be the start of the new school year following the summer break (decant activities will take place during the school holidays, between July and September).
4.4The Headteacher and the Chair of Governors have been consulted regarding the revised opening date of 5th September 2018 and both the school and the Governing body is in agreement with the proposed modification to the school opening date.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
School Modernisation Programme: Pencoed Primary School: Modification of School Opening Date from 1 April 2018 to 5 September 2018Report | 68 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.