Cabinet: (1) approved in principle the financial commitment required for Band B of the school Modernisation Programme. The approval would be subject to sufficient resources being identified and allocated to meet the match funding commitment; (2) approved that a report be submitted to Council to amend the capital programme for Band B of the School Modernisation Programme.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is to seek Cabinet endorsement of the financial commitment required for Band B of the School Modernisation Programme prior to submission to Council.
2. Connection to corporate improvement objectives/other corporate priorities
2.1This report relates to the following Corporate Improvement Plan priorities:
Supporting a successful economy Smarter use of resources
2.2On 3 March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend. Five key principles were set out to inform the organisation and modernisation of our schools. These are:
commitment to high standards and excellence in provision; equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend; inclusive schools, which cater for the learning needs of all their pupils; community-focused schools, where the school actively engages with its local community; and value for money.
2.3The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice.
2.4The principles which are particularly relevant in the context of Band B are the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness (“narrowing the gap between the most and the least expensive provision currently”).
Background
3.1In September 2006, the Council approved a vision for the county borough’s schools in which they would be fit for the 21st century and achieve the best use of resources. It was recognised that we need to modernise our schools and get a closer match between our aspiration for schools, the quality of their accommodation and the projected number of pupils.
3.2Since then, school modernisation has been established as one of the Council’s main strategic programmes. The programme has been planned and implemented in accordance with the agreed policy and planning framework and has been matched to capital resources identified within the capital programme.
3.3In November 2010, Cabinet was informed of the work which had been undertaken in determining the strategic priorities for school modernisation to enable the aims of the programme to be met.
3.4The School Modernisation Programme was established to deliver on several objectives including:
developing first-class learning environments; locating the right number of schools, of a viable size, in the best places to serve their communities; making schools an integral part of the life and learning of their communities; reducing surplus places and achieving best value for money; and make schools more efficient and sustainable.
3.5In November 2010, Cabinet approved the recommended schemes included in each of the four bands (A-D) which were subsequently detailed in Bridgend’s 21st Century Schools Strategic Outline Programme (SOP). The SOP was submitted to Welsh Government in 2011 and ministerial ‘approval in principle’ was received, subject to the completion of the Welsh Government business case process.
3.6Band A schemes, which are funded on a 50/50 basis with Welsh Government, are due for completion in 2018-2019 and are at various stages. The SEN provision at Bryncethin Campus, Coety Primary School, two additional teaching spaces at Heronsbridge Special School and Betws Primary School schemes have been completed. Work is well underway on the remaining schemes within Band A (ie the replacement YGG Cwm Garw, Brynmenyn Primary School and Pencoed Primary School).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.