Bridgend County Borough Council
Cabinet, Tuesday 19 June 2018

Cwmfelin Primary School Capital Project

Approved Executive 1 paper

Cabinet approved this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.

Item218

Resolved

That Cabinet gave approval for a report to be submitted to Council for approval to amend the Capital Programme to include a budget of £165k to fund the new build classroom space at Cwmfelin Primary, to be met from earmarked reserves, the school and Education and Family Support Directorate budgets.
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1The purpose of this report is to seek approval from Cabinet to recommend to Council a revision to the Capital Programme for 2018 to 2028 to include a budget of £165,000 for the build of a new classroom at Cwmfelin Primary School.

2. Connection to Corporate Improvement Objectives/Other Corporate Priorities

2.1This report assists in the achievement of the following corporate priorities:-

Supporting a successful economy - taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county. Smarter use of resources - ensuring that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.

Background

3.1On 3 March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend. Five key principles were set out to inform the organisation and modernisation of our schools. These are:

 commitment to high standards and excellence in provision;  equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend;  inclusive schools, which cater for the learning needs of all their pupils;  community-focused schools, where the school actively engages with its local community; and  value for money.

3.2The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice.

3.3The principles which are particularly relevant are the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness (“narrowing the gap between the most and the least expensive provision currently”).

4. Current situation

4.1Despite staff making best use of the school premises, the insufficient size of classroom spaces at Cwmfelin Primary is putting pressure on teaching and learning opportunities for the school.

4.2The authority has recognised that the school needs additional space to aid the delivery of the foundation phase and undertake interventions.

4.3There have been a number of options considered to provide additional space at the school. However the options, which included the transfer of a mobile classroom from Betws Primary, internal adaptations to an existing mobile classroom and a new build single or double classroom, were all cost prohibitive.

4.4A scheme has since been developed for provision of accommodation suitable for groups of 20, which meets the school’s needs. It is proposed to proceed on the basis of providing this space as a new build on an area of land close to the nursery building on the school site. This provision will provide the school with the much needed additional space.

4.5This additional space will ease pressure on existing classes and support the delivery of interventions and group work. It is not anticipated that any additional classroom space will be required in the near future, as projected demographic growth is relatively low in this school’s catchment area. There is therefore no proposal to increase the published admission number for the school as a result of this proposal.

4.6This minimal enlargement does not require a statutory procedure as prescribed within the School Organisation Code.

5. Effect upon Policy Framework& Procedure Rules.

5.1There is no effect upon the policy framework or procedure rules.

6. Equality Impact Assessment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cwmfelin Primary School Capital ProjectReport 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 13 attended
GL
Gill LewisOfficer, in attendance
KW
Kelly WatsonOfficer, in attendance
CH
Cynghorydd Huw DavidChairperson, present
CC
Cynghorydd Charles SmithCommittee Member, apologies
CP
Cynghorydd Philip WhiteCommittee Member, present
CH
Cynghorydd Hywel WilliamsCommittee Member, apologies
DM
Darren MephamOfficer, in attendance
MS
Mark ShephardOfficer, in attendance
SC
Susan CooperOfficer, in attendance
MG
Mark GalvinOfficer, in attendance
LH
Lindsay HarveyOfficer, in attendance
CD
Cynghorydd Dhanisha PatelCommittee Member, present

All 13 on the meeting page

On this subject at Bridgend

Search all
  1. Cwmfelin Primary School Capital ProjectThis decision
  2. Cwmfelin Primary School - Capital ProgrammeApproved

More from Bridgend Cabinet

All decisions
MeetingDecisionOutcome
17 Oct 2023 Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... Noted Open
17 Oct 2023 Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... Noted Open
17 Oct 2023 Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... Noted Open
17 Oct 2023 Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... Approved Open
17 Oct 2023 Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies