That Cabinet gave approval for a report to be submitted to Council for approval to amend the Capital Programme to include a budget of £165k to fund the new build classroom space at Cwmfelin Primary, to be met from earmarked reserves, the school and Education and Family Support Directorate budgets.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is to seek approval from Cabinet to recommend to Council a revision to the Capital Programme for 2018 to 2028 to include a budget of £165,000 for the build of a new classroom at Cwmfelin Primary School.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1This report assists in the achievement of the following corporate priorities:-
Supporting a successful economy - taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county. Smarter use of resources - ensuring that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
Background
3.1On 3 March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend. Five key principles were set out to inform the organisation and modernisation of our schools. These are:
commitment to high standards and excellence in provision; equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend; inclusive schools, which cater for the learning needs of all their pupils; community-focused schools, where the school actively engages with its local community; and value for money.
3.2The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice.
3.3The principles which are particularly relevant are the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness (“narrowing the gap between the most and the least expensive provision currently”).
4. Current situation
4.1Despite staff making best use of the school premises, the insufficient size of classroom spaces at Cwmfelin Primary is putting pressure on teaching and learning opportunities for the school.
4.2The authority has recognised that the school needs additional space to aid the delivery of the foundation phase and undertake interventions.
4.3There have been a number of options considered to provide additional space at the school. However the options, which included the transfer of a mobile classroom from Betws Primary, internal adaptations to an existing mobile classroom and a new build single or double classroom, were all cost prohibitive.
4.4A scheme has since been developed for provision of accommodation suitable for groups of 20, which meets the school’s needs. It is proposed to proceed on the basis of providing this space as a new build on an area of land close to the nursery building on the school site. This provision will provide the school with the much needed additional space.
4.5This additional space will ease pressure on existing classes and support the delivery of interventions and group work. It is not anticipated that any additional classroom space will be required in the near future, as projected demographic growth is relatively low in this school’s catchment area. There is therefore no proposal to increase the published admission number for the school as a result of this proposal.
4.6This minimal enlargement does not require a statutory procedure as prescribed within the School Organisation Code.
5. Effect upon Policy Framework& Procedure Rules.
5.1There is no effect upon the policy framework or procedure rules.
6. Equality Impact Assessment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.