Resolved
That Council gave approval to amend the Capital Programme to include a ... view the full minutes text for item 193.
Council approved this item on Wednesday 20 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That Council gave approval to amend the Capital Programme to include a ... view the full minutes text for item 193.
1.1The purpose of this report is to seek Council approval to revise the Capital Programme for 2018 to 2028 to include a budget of £165,000 for the build of a new classroom at Cwmfelin Primary School.
1.2In their meeting on 19 June 2018, Cabinet was asked to approve a report to be submitted to Council for approval to amend the Capital Programme to include a budget of £165,000 to fund the new-build classroom space at Cwmfelin Primary School, to be met from earmarked reserves, the school and Education and Family Support Directorate budgets.
2. Connection to corporate improvement objectives/other corporate priorities
2.1This report assists in the achievement of the following corporate priority/priorities:
Supporting a successful economy - taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county. Smarter use of resources - ensuring that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
3.1On 3 March 2015, Cabinet approval was received for the Council to adopt revised principles as a framework for school organisation in Bridgend. Five key principles were set out to inform the organisation and modernisation of our schools. These are:
commitment to high standards and excellence in provision; equality of opportunity, so that all pupils can access quality learning opportunities, regardless of which school they attend; inclusive schools, which cater for the learning needs of all their pupils; community-focused schools, where the school actively engages with its local community; and value for money. 3.2 The Policy and Planning Framework sets out 17 areas where these principles should be applied in practice.
3.3The principles which are particularly relevant are the size of primary schools (to ensure that “all Bridgend’s primary schools are large enough to make the full range of necessary provision”) and value for money, efficiency and effectiveness (“narrowing the gap between the most and the least expensive provision currently”).
4. Current situation/proposal
4.1Despite staff making best use of the school premises, the insufficient size of classroom spaces at Cwmfelin Primary School is putting pressure on teaching and learning opportunities for the school.
4.2The local authority has recognised that the school needs additional space to aid the delivery of the foundation phase and undertake interventions.
4.3There have been a number of options considered to provide additional space at the school. However, the options, which included the transfer of a mobile classroom from Betws Primary School, internal adaptations to an existing mobile classroom and a new-build single or double classroom, were all cost prohibitive.
4.4A scheme has since been developed for provision of accommodation suitable for groups of 20, which meets the school’s needs. It is proposed to proceed on the basis of providing this space as a new build on an area of land close to the nursery building on the school site. This provision will provide the school with the much needed additional space.
4.5This additional space will ease pressure on existing classes and support the delivery of interventions and group work. It is not anticipated that any additional classroom space will be required in the near future, as projected demographic growth is relatively low in this school’s catchment area. There is therefore no proposal to increase the published admission number for the school as a result of this proposal.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cwmfelin Primary School: Capital ProgrammeReport | 98 KB | DownloadRead as text |
Follow Council at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Sep 2023 | Approval of MinutesThat the minutes of a meeting of Council dated 19 July 2023, be approved as a true and accurate record. | Approved | Open |
| 20 Sep 2023 | South-East Wales Corporate Joint Committee Overview and Scrutiny ArrangementsCouncil agreed to defer this item in order to receive further information at the next scheduled meeting of Council. | Agreed | Open |
| 20 Sep 2023 | Appointment of Registered Representatives to the Overview and Scrutiny Subject CommitteesThat Council noted the report and approved the appointment of the following individuals as Registered Representatives... | Noted | Open |
| 20 Sep 2023 | Information Report for NotingThat Council acknowledged the publication of the report referred to in paragraph 3.1 of the report. | Decided | Open |
| 19 Jul 2023 | Approval of MinutesThat the minutes of the 21/06/2023 be approved as a true and accurate record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.