Resolved
That Cabinet: (1) Noted the progress to date of the Caerau Mine Water Heat Project; (2) Delegated ... view the full minutes text for item 387.
Cabinet noted this item on Tuesday 23 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: (1) Noted the progress to date of the Caerau Mine Water Heat Project; (2) Delegated ... view the full minutes text for item 387.
1.1The purpose of this report is to:
1.1.1. update Cabinet on the Caerau Mine Water Heat Project; 1.1.2. delegate authority to the Section 151 Officer, subject to the approval of the and Head of Legal and Regulatory Services, to accept a revised funding offer from the Welsh European Funding Office (WEFO); and 1.1.3. delegate authority to the Chief Executive, in consultation with the Section 151 Officer and the Head of Legal and Regulatory Services, to enter into any funding and/or legal agreements required as a result of accepting the revised funding offer from WEFO.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1This report supports the following corporate priorities:
• Supporting a successful economy – taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county.
• Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
3.1Bridgend County Borough Council (BCBC) was selected as a demonstrator for the Smart Systems Heat (SSH) Programme in October 2014. One of the key deliverables of this programme was the adoption by Cabinet in February 2019 of the Local Area Energy Strategy (LAES) and the Smart Energy Plan (SEP). This was developed in partnership with the Energy Systems Catapult (ESC). Overall, the SSH programme was divided into 3 phases, outlined below in relation to the development of the Caerau Mine Water Heat Project:
o Phase 1 2015 - 2018 - This phase involved using the EnergyPath Network suite of tools to create a Low Carbon Transition Strategy for Bridgend County Borough, detailing how the County Borough can meet the UK decarbonisation targets by 2050. o Phase 2 Development 2016 – 2019 - This phase involves the development of the funding package for the project, establishing the scope of the demonstrator schemes, engaging with residents and commercial stakeholders and creating the delivery structure for the programme.
o Phase 3 Delivery 2019 and beyond – this phase will be the construction and monitoring phase of the programme which will test the concept and methodology of the project, and most importantly that the approach can be adopted nationally and provide an evidence base for future UK and Welsh Government (WG) policy.
3.2BCBC proposed the Caerau Mine Water Heat Project as one of the demonstrator projects for the SSH Programme. The project is highly innovative and proposes to extract heat from water contained within flooded former coal mine workings to provide a resource for properties within Caerau. The mine water will have heat extracted and transferred to a clean water circuit. This water would be transported via a network of pipes to local energy centres where the temperature would be boosted to the required temperature by ground source heat pumps and then circulated to the residents’ houses.
4. Current Situation / Proposal
4.1BCBC submitted an Operation Logic Table (OLT) to WEFO on the 3rd June 2016 for the Caerau Mine Water Heat Project. WEFO then took the OLT to their Programme Management Group who approved the OLT and BCBC were invited to submit a business plan as part of the ERDF funding process.
4.2Work on the business plan commenced in September 2016 in partnership with the ESC. The business plan went through several versions during an ongoing dialogue with WEFO and the final plan for approval was submitted in September 2017 under ERDF Priority 3 Renewable Energy and Energy Efficiency – SO3.2: Increasing the number of commercially viable small scale renewable energy schemes.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Caerau Minewater Heat ProjectReport | 101 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.