Resolved
That Cabinet: · Noted the projected revenue position for 2019-20; · Recommended that Council approve the virements over £100,000 as outlined in paragraph 4.1.4 of the report.
Cabinet noted this item on Tuesday 23 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: · Noted the projected revenue position for 2019-20; · Recommended that Council approve the virements over £100,000 as outlined in paragraph 4.1.4 of the report.
3.1On 20th February 2019, Council approved a net revenue budget of £270.809 million for 2019-20, along with a capital programme for the year of £36.157 million. Council also approved a new Capital Strategy, which demonstrates that the Authority takes capital expenditure and investment decisions in line with service objectives and properly takes account of stewardship, value for money, prudence, sustainability and affordability. Given the importance of this, and the level of investment the Council makes in capital schemes, from 2019-20 onwards a separate quarterly report to Cabinet will be provided on capital expenditure, including monitoring of spend, and performance indicators, to provide more detailed information on schemes and how the Council spends its capital funding. This report will therefore focus specifically on the revenue budget. 3.2 As part of the Performance Management Framework, budget projections are reviewed regularly and reported to Cabinet on a quarterly basis. The delivery of agreed budget reductions is also kept under review and reported to Cabinet as part of this process.
4.0Current Situation / Proposal
4.1Summary financial position at 30th June 2019
4.1.1 The Council’s net revenue budget and projected outturn for 2019-20 is shown in Table 1 below.
Table 1- Comparison of budget against projected outturn at 30th June 2019
Projected Projected Over / Original Revised Projected Over / (Under) (Under) Directorate/Budget Area Budget Budget Outturn Q1 Spend Spend 2019-20 2019-20 2019-20 2019-20 Q1 2018-19 £'000 £'000 £'000 £'000 £'000 Directorate
Education and Family Support 116,208 113,858 114,406 548 (168) Social Services and Wellbeing 70,834 70,916 71,190 274 2,006 Communities 25,331 25,511 26,070 559 75 Chief Executive's 18,609 18,579 17,961 (618) (1,621) Total Directorate Budgets 230,982 228,864 229,627 763 292 Council Wide Budgets
Capital Financing 7,430 7,329 7,329 0 0 Levies 7,376 7,134 7,134 0 16 Apprenticeship Levy 700 700 620 (80) (98) Council Tax Reduction 14,854 14,854 14,692 (162) (486) Scheme Insurance Premiums 1,588 1,588 1,331 (257) 0 Repairs & Maintenance 870 870 870 0 0 Pension Related Costs 430 430 430 0 (826) Other Corporate Budgets 6,579 9,040 9,040 0 (107) Total Council Wide Budgets 39,827 41,945 41,446 (499) (1,501)
Total 270,809 270,809 271,073 264 (1,209)
4.1.2 The overall projected position at 30th June 2019 is a net over spend of £264,000, comprising £763,000 net over spend on directorates and £499,000 net under spend on corporate budgets. A detailed analysis of the more significant projected under and over spends is set out in section 4.3.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2019-20 MTFS Budget Reductions Risk Tracker June 2019Appendix 2 | 157 KB | Download |
PDF |
Budget Mon. Appendix 1: Monitoring of Prior Year Budget Reductions Carried Forward into 2019-20Appendix | 128 KB | Download |
PDF |
Budget Mon. Appendix 3 Revenue Budget Monitoring end June 2019Appendix | 22 KB | Download |
PDF |
Budget Monitoring 2019-20: Quarter 1 Revenue ForecastReport | 624 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.