That the above application be granted, subject to the Conditions contained in the report of the Corporate Director – Communities. Proposal Use of land for storage of end of life timber for a temporary period of 3 years Subject to the temporary consent elapsing after two years instead of three and Condition 3 being amended to reflect this change.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
REFERENCE: P/20/553/FUL APPLICANT: South West Wood Products Limited Clifton Moor, Clifton, Penrith CA10 2EY LOCATION: Lock Complex, south east of South West Wood Products site, Heol Llan, Coity CF35 6BU PROPOSAL: Use of land for storage of end of life timber for a temporary period of 3 years RECEIVED: 31 July 2020 SITE INSPECTED: 1 October 2020
UPDATE SINCE MEETING OF COMMITTEE ON 21 JANUARY Before it could be considered, this application was deferred from the Development Control Committee on 21 January 2021 to allow for a virtual site visit to be undertaken. The Virtual Site visit will take place via Teams on Wednesday 3 March 2021 at 2pm in the form of drone footage with commentary from the Officer. The Speakers that would have commented on this application at the last meeting will be allowed to speak at the start of this meeting.
Since the last DC Committee meeting, National Planning policy has seen the publication of two new documents - Future Wales – the National Plan 2040 and Planning Policy Wales (Ed 11) on 24 February, 2021. The application has been re-considered under these new policy documents and the recommendation remains as per the original report.
Also, since the last Committee an issue has arisen on the former Bryncethin Nursery part of the site relating to a suspected leak in the 4m deep private gas pipe that serves Mount Pleasant Bungalow. Wales and West Utilities have investigated the leak and whilst they have not been able to identify the source of the leak to date, they will carry on with their investigations and have confirmed that due to the depth and thickness of the gas main and the individual gas service pipe supplying Mount Pleasant Bungalow being plastic, they have no current safety concerns for the gas network located in the former Bryncethin Nursery part of the site. A copy of the Wales and West Utilities letter to Huw Irranca- Davies MS is attached as an Appendix to this report.
There have been calls for the application to be deferred again until this issue has been resolved however, Members will note that this particular application relates to the southernmost part of the site away from the Former Bryncethin Nursery area and is therefore far removed from the location of the private gas pipe. In addition, the applicant will not be able to access this area of Crown land until the consent has been issued and the NRW permit has been amended to include it.
As explained in the report, this application will define what operations are allowed to occur on this part of the site so that they can be more easily enforced and in order to allow the applicant to remove the old, polluting legacy wood from the Crown land. In effect, the applicant cannot lawfully deal with the stockpiles without the temporary consent.
It is considered that there is no benefit in deferring the application again as any further delay may prejudice the chances of achieving a satisfactory resolution to the issues on this site by stalling the removal of the historic waste wood from the Crown land. In addition, a deferral could also result in an appeal against non-determination.
Reproduced below is a copy of the original report:- APPLICATION/SITE DESCRIPTION The application seeks Planning consent to regularise the use of this land for the storage of end of life timber for a temporary period of 3 years (P/20/553/FUL). This area has been the subject of unauthorised storage of poor quality waste wood and it is intended to mix or blend this wood with better quality wood in order to get it to a standard that can be accepted and used at Kronospan or Margam.
As it stands there is no requirement for the applicant to remove and process this end of life timber as the company responsible for depositing the wood there has gone into administration and the land has reverted to the Crown.
Fig. 1 – Aerial View of Site
Fig. 2 – Proposed Site Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.