That Cabinet: · Approved pursuing the recommended way forward for the as outlined in section 4.4 of the Report, being the delivery of a blended solution of a demonstrator mine water scheme, serving Caerau Primary school, a district heat network with an alternative heat source serving homes on the Tudor Estate and a private wire power supply from Llynfi Afan Renewable Energy Park; · Delegated ... view the full minutes text for item 675.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is update Cabinet on recent activity in relation to the Caerau Heat Scheme, to seek a decision on the way forward and seek authority to submit a re-profiled scheme to the Welsh European Funding Office (WEFO).
2. Connection to corporate well-being objectives / other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objective/objectives under the Well-being of Future Generations (Wales) Act 2015:-
1. Supporting a successful sustainable economy – taking steps to make the county borough a great place to do business, for people to live, work, study and visit, and to ensure that our schools are focussed on raising the skills, qualifications and ambitions for all people in the county borough.
2. Smarter use of resources – ensure that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help to deliver the Council’s well- being objectives.
Background
3.1The Caerau Heat Scheme was established as a highly innovative project that proposed to extract heat from water contained within flooded former coal mine workings, to provide an energy resource for properties within Caerau. The water would be transported via a network of pipes to the properties with the temperature being boosted to the residents’ required level by a ground source heat pump.
3.2A report to Cabinet in January 2021 provided an update on the progress made in 2020 and the challenges (particularly financial), faced by the scheme at that time.
3.3It was agreed that an Options Appraisal would be undertaken to determine the viability and suitability of alternative delivery methods for delivering a low carbon heat scheme in Caerau that meets the requirements of the approved ERDF funding. The recommendations of the Options Appraisal would then be reported back to Cabinet.
3.4The scheme has a series of decision gateways, which form critical points where research undertaken to that point is used to determine whether the proposed method of delivery can, and should, proceed. At each stage the technical feasibility and financial viability are considered.
3.5Table 1 below shows these decision gateways, with their original estimated and revised dates. It also shows scheme outputs and outcomes that will be available in the event of the project being closed down at any one of the decision gates.
Table 1 – Decision Gateways
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.