Cabinet: · Noted the outcome of the published statutory notice in respect of the proposed enlargement of Mynydd Cynffig Primary School as detailed in the Objection Report (Appendix A); · Gave approval to publish the Objection Report; · Determined to implement the proposal with effect from the beginning of the autumn term 2025; and Gave approval to issue and publish a decision letter.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
inform Cabinet of the outcome of the published statutory notice in respect of the proposed enlargement of Mynydd Cynffig Primary School, as detailed in the Objection Report (Appendix A);
seek approval to publish the Objection Report, as prescribed by the School Organisation Code 2018 (Code);
seek approval to implement the proposal with effect from the beginning of the autumn term 2025; and
seek approval to issue and publish a decision letter, as prescribed by the Code.
2. Connection to corporate well-being objectives/other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objectives under the Well-being of Future Generations (Wales) Act 2015:
Supporting a successful sustainable economy - taking steps to make the county borough a great place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions for all people in the county borough.
Smarter use of resources – ensure that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help deliver the Council’s well-being objectives. 3. Background
3.1In April 2009, Cabinet approved a number of individual projects that emerged from a feasibility study, which reviewed 3 to 18 learning provision in the Cefn Cribwr, Cornelly, Kenfig Hill and Pyle area. Approval was received to progress a project to cater for a proposed amalgamation and enlargement of Mynydd Cynffig Infant and Junior Schools.
3.2In December 2010, the Council’s Strategic Outline Programme (SOP) for the 21st Century Schools Programme was submitted to Welsh Government (WG) and a replacement Mynydd Cynffig Primary School scheme was identified as a Band A project. In 2011, the project was again confirmed as a priority Band A scheme in a further SOP submission to WG.
3.3A feasibility study was undertaken in 2011 to establish the most suitable site for the primary school. That study considered the establishment of primary provision on Mynydd Cynffig Infant and Junior Schools’ sites plus the site of Cynffig Comprehensive School, the outcome of which determined that the preferred site was that of the Junior School.
3.4Following the establishment of Mynydd Cynffig Primary School in September 2015, a decision was made to undertake further feasibility work to explore the potential Cynffig Comprehensive School, to accommodate Mynydd Cynffig Primary School at that location.
3.5The feasibility study showed that Cynffig Comprehensive School site allowed for suitable alternative solutions to the critical issues of sufficient developable area and appropriate site access. It also offered sufficient space to develop a 2- form entry (FE) school plus nursery and remove some secondary surplus places.
3.6The outcome of the feasibility study was reported to Cabinet in July 2016 and approval was provided to commence the consultation process to relocate the primary school to the secondary school site.
3.7The outcome of the consultation was reported to Cabinet in January 2017. The community strongly opposed the proposal and Cabinet determined to consider a counter proposal from the objectors (that is, to locate the new school on the school’s junior site).
3.8In March 2017, the outcome of a review of the 2011 feasibility study and the counter proposal was reported to Cabinet together with concerns regarding revised budget estimates for the new school development at the secondary school site. Cabinet determined to abandon the proposal, as there was insufficient funding available to take forward the scheme at the comprehensive or junior site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.