That the changes to the capital budget, as set out in Appendix 1 of the report be approved. 2. That it be noted that the programme slipped by 3.48%, as set out in paragraph 3.3 of the report. 3. That the carrying forward of 2007/08 slippage (£1.407 million) into the 2008/09 capital programme, to meet on-going commitments on these schemes, be approved.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
CABINET Agenda 15 Item 15 Agenda Item Brighton & Hove City Council
Subject: Targeted Budget Management (TBM) Capital Outturn 2007/08 Date of Meeting: 12 June 2008 Report of: Director of Finance & Resources Contact Officer: Name: Stuart Taylor Tel: 29-1074 E-mail: [email protected] Key Decision: Yes Forward Plan Reference: CAB 0008 Wards Affected: All
FOR GENERAL RELEASE
1. SUMMARY AND POLICY CONTEXT: 1.1 This report sets out the capital outturn for 2007/08. 1.2 This report also highlights programme slippage, details budget changes and seeks approval for carry forwards to the 2008/09 programme.
2. RECOMMENDATIONS: (1) Approve the changes to the capital budget, as set out in Appendix 1 (2) Note the programme slipped by 3.48%, as set out in paragraph 3.3. (3) Approve the carrying forward of 2007/08 slippage (£1.407 million) into the 2008/09 capital programme, to meet on-going commitments on these schemes.
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS: 3.1 Capital Budget 2007/08 On 7 February 2008, Policy & Resources Committee considered the month 9 capital monitoring report and agreed a revised capital budget of £44.939 million. Appendix 1 to this report shows in detail the proposed changes to that budget since month 9, resulting in a final proposed 2007/08 capital budget of £40.444 million. Chart 1 shows the resources that make up that budget.
-57 57 - Chart 1 Capital Resources £ '000 Other External Council Resources Contributions £6,867 £991
Borrowing £10,545
Grants, £22,041
3.2Capital Outturn The table below shows the capital outturn for 2007/08
Total 44,939 249 169 (4,913) 40,444 38,796 1,407 241
- 58 58- The 2007/08 capital outturn is £38.796 million. A further £1.407 million of the budget is needed to complete these projects and is requested to be carried forward to the 2008/09 programme. Net savings have been made of £0.241 million. This relates to two areas of the programme: • Housing stock programme £0.184 million Cash incentive £0.080 million – there was no take-up of scheme in 2007/08. A further £0.080 million allocation has been made in 2008/09 budget, so this saving is to be returned to HRA reserves for future re- allocation. ICT fund £0.104 million - following the decision to retain the housing stock, a new ICT strategy has been in development. It has not therefore been appropriate to purchase individual solutions without fitting them into the overall strategy. This underspend will therefore be returned to HRA reserves for future re-allocation. • Children’s Centres £0.057 million Savings were identified in order to allow this ring-fenced grant to be re- allocated towards the nursery class at Moulsecoomb Primary School in 2008/09. The grant can be carried forward for use in 2008/09 without the loss of funding. 3.3 Capital Slippage The council endeavours to deliver its capital programme on time and within budget and as such monitors against a challenging target of spending at least 95% of the approved capital programme each year. The graph below shows how forecasts of slippage compare to previous years
4 % of budget
2005/06 3 2006/07 2007/08 2
0 1 2 3 4 5 6 7 8 9 10 11 12 Month
Total outturn slippage amounts to £1.407 million or 3.48% of the budget. No resources have been lost as a result of this slippage. Details of schemes with significant slippage are provided at appendix 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.