That the nature of the representations made to the original Core Strategy Preferred Options document (appendix 2 of the report) be noted. 2. That the officer responses and recommendations to the representations set out in the schedule attached to the Statement of Consultation placed in the Members’ rooms be approved. 3. That the Revised Core Strategy and supporting documents for the purposes of a minimum six week period of public consultation, subject to any minor editorial changes agreed by the Cabinet Member for Environment in consultation with the Director of Environment be approved; and 4. That it be noted that the final version of the Core Strategy would be brought back to the Cabinet and Council in January 2009 for approval for submission to the Secretary of State following a final formal period of consultation to take place during February and March 2009 (the exact procedure would be subject to the publication of The Town and Country Planning (Local Development) (England) (Amendment) Regulations anticipated May/June 2008.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
The Revised Core Strategy Preferred Options Document
A Quick Reference Guide 167
12 June 2008
Agenda Item 18 City Planning Environment Directorate Brighton & Hove City Council
- 139 - The Revised Core Strategy
Ø The Core Strategy is part of Brighton & Hove’s Local Development Framework, a suite of planning documents that will guide planning and development of the city over the next twenty years and will eventually replace the Local Plan. Ø The purpose of the Core Strategy is to provide the overall strategic vision for the future of Brighton & Hove through to 2026. It will set out how the council will respond to local priorities and meet the challenges of the future and identify the broad locations, scale and type of development and supporting infrastructure that will take place. Ø It addresses important city-wide matters such as delivering more sustainable development and neighbourhoods and sets out the council’s strategic approach to housing, the economy, shopping and transport. Ø The council has made good progress in preparing the Core Strategy. A very wide ranging debate was initiated about the city’s future, at the ‘Issues and Options’ stage (October 2005). These ideas were developed into the ‘Preferred Options’ stage which was published for public consultation in October 2006. Ø Following the responses to the consultation and advice from the Government Office for the South East (GOSE), the Revised Preferred Option has been prepared and has taken into account: • further research and evidence gathering required by recently published national planning policy; 168
• more details on the location, scale and type of development to be delivered by the Core Strategy to the period 2026; • a more area-based approach to planning, setting out how the council will respond to the local priorities of specific areas of the city and meet the challenges of the future (‘place-shaping’).
Timetable for Preparing the Core Strategy
Issues and Options – early community involvement October 2005 – May 2006 Preferred Options - formal public consultation November – December 2006 Revised Preferred Options - informal public consultation June – August 2008 Submission Document - formal public consultation February – March 2009 Submission of Core Strategy to Government May 2009 Examination in public by the Planning Inspectorate October 2009 (estimated) Adoption of the Core Strategy January 2010 (estimated)
- 140 - The Preferred Options Stage
The purpose of the Preferred Options stage is for the council to seek the views of the public and stakeholders on the p proposals it is recommending for the Core Strategy before the final version is submitted to the Secretary of State for Approval. Where, through consultation responses and background evidence, different options could be considered to address a particular issue, the document sets out the options favoured by the council as the ‘preferred options’
The Structure of the Revised Core Strategy
Part One - Context, Vision and Objectives. This section sets out the key issues facing the city over the next twenty years, and summarises the policy context for the Core Strategy. It also sets out a vision of the city that we are aiming for in 2026 and lists our strategic spatial objectives, from which all future planning policies will flow.
Part Two - Spatial Strategy sets out our preferred approach and locations for future sustainable development in the city. This is structured as follows: 169
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.