(1) That the Cabinet Member for Environment approves the allocation of the £5.79 million 2009/10 Local Transport Plan settlement to specific Integrated Transport and Maintenance schemes as set out in Appendix A of the report. (2) That the Cabinet Member for Environment approves the allocation of the Road Safety Grant of £476,000 to the Sussex Safer Roads Partnership to continue the important funding of casualty reduction measures in the area.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
ENVIRONMENT CABINET Agenda Item 128 MEMBER MEETING Brighton & Hove City Council
Subject: 2009/10 Local Transport Plan Capital Programme Date of Meeting: 26 March 2009 Report of: Director of Environment Contact Officer: Name: Andrew Renaut Tel: 29-2477 E-mail: [email protected] Key Decision: Yes Forward Plan No. ENV9071 Wards Affected: All
FOR GENERAL RELEASE
This report could not be completed until the council had agreed its 2009/10 budget at the council meeting on Thursday 26 February. It was therefore not included on the Forward Plan. It is essential that a decision on funding allocations is taken prior to the beginning of 2009/10 to enable the development or construction a number of schemes or projects to continue uninterrupted from 2008/09 into 2009/10, and therefore be delivered on time and to budget.
1. SUMMARY AND POLICY CONTEXT:
1.1The City Council has been given permission to invest £6.058 million in transport projects during 2009/10 through the government’s Local Transport Plan [LTP] process to be funded through grant of £1.573m and supported borrowing of £4.485m. The Policy & Resources Committee approved the use of capital funding for a 5-year programme of LTP projects for 2006/07 to 2010/11 on 1 March 2006. This report enables the Cabinet Member for Environment to consider and approve the allocation of the 2009/10 funding to specific works areas and individual schemes within them.
1.2In addition, the Department for Transport is to pay the City Council a specific Road Safety Grant of £476,000 for 2009/10 to fund road safety measures. This replaces the funding providing for safety cameras via the netting off funding arrangement, which was previously in place. The use of this funding from the LTP process for the Sussex Road Safety Partnership was approved in the Policy & Resources Committee report of 18 January 2007.
1.3The LTP is a statutory document and the proposed investment programme is consistent with government policy and the objectives of the council’s Sustainable Transport Strategy [STS], which include improving safety, providing alternatives and choices for some journeys by encouraging use of sustainable transport, and ensuring the highway network is maintained to a high standard.
19 2. RECOMMENDATIONS:
2.1(1) That the Cabinet Member for Environment approves the allocation of the £5.79 million 2009/10 Local Transport Plan settlement to specific Integrated Transport and Maintenance schemes as set out in Appendix A of the report.
2.2(2) That the Cabinet Member for Environment approves the allocation of the Road Safety Grant of £476,000 to the Sussex Safer Roads Partnership to continue the important funding of casualty reduction measures in the area.
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1The council’s 2009/10 LTP settlement was announced by the government in November 2007 and is based on the achievements set out in the LTP Delivery Report for the period 2001/02 - 2005/06, which was submitted to the Government Office for the South East in July 2006, and on the second Full Local Transport Plan [LTP2] for 2006/7 - 2010/11, approved and submitted in March 2006.
3.2The Government has awarded £4.715 million for Integrated Transport Schemes (ITS) and £1.343 million for Maintenance schemes. The government’s indicative allocation of funds for Maintenance schemes, calculated using a complex formula, fell well below the amount included in the LTP2 for 2009/10. Therefore, it is proposed that the council continues to use its discretion to increase the allocation to Maintenance, as it has done in recent years, by just over £0.5 million to £1.87 million, to ensure National Indicators [NIs] and local targets can be met within certain timescales.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment Cabinet Member Meeting at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingRESOLVED – That, having been signed by the previous Cabinet Member as a correct record, the minutes of the meeting he...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.