Resolved
(1) Cabinet approves the allocation of £3.35 million worth of funding for the 2011/12 Local Transport Plan capital programme to the Maintenance and Integrated Transport work programmes set out in Appendix 1 of this report.
Cabinet (pre 2012) approved this item on Thursday 7 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) Cabinet approves the allocation of £3.35 million worth of funding for the 2011/12 Local Transport Plan capital programme to the Maintenance and Integrated Transport work programmes set out in Appendix 1 of this report.
2.1That Cabinet approves the allocation of £3.35 million worth of funding for the 2011/12 Local Transport Plan capital programme to the Maintenance and Integrated Transport work programmes set out in Appendix 1 of this report.
1 3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1The basis on which the proposed 2011/12 allocation of funds set out in Appendix 1 has been prioritised is described briefly below, and is consistent with the 3 principles established for the LTP3 Delivery Plan – maintain, manage and improve.
3.2The programme includes a number of projects that is was not possible to deliver during 2010/11, owing to in-year reductions in LTP2 grant funding during that year, in addition to continued and new projects. In revising the 2010/11 capital programme in July 2010, the Cabinet agreed to defer a number of projects that had not yet commenced ‘with a view to re-profiling them into future year’s programmes should they still remain a priority’. A number of other budgets were removed or reduced, or alternative sources of funding were identified. These decisions have been taken into account in developing the 2011/12 programme.
MAINTENANCE FUNDING BLOCK
3.3A programme of £1.65 million for this area of work reflects the government’s expectation that approximately 50% of the LTP allocation should be spent on maintenance, based on its revised formula for calculating LTP funds. In previous years, this indicative amount has been nearer to 20% of the LTP allocation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2011/12 Local Transport Plan Capital ProgrammeReport | 88 KB | DownloadRead as text |
PDF |
Item 220 Appendix 1Appendix | 81 KB | Download |
PDF |
View as HTML (220./2) 90 KBAppendix | 90 KB | Download |
PDF |
View item 220. as HTML 77 KBReport | 77 KB | Download |
Follow Cabinet (pre 2012) at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 May 2012 | Procedural BusinessRESOLVED – That the press and public be excluded from the meeting during consideration of the item listed in Part Two... | Decided | Open |
| 10 May 2012 | Minutes of the previous meetingRESOLVED - That the minutes of the meeting held on 17 th April 2012 be approved as a correct record. | Approved | Open |
| 10 May 2012 | Items reserved for discussionRESOLVED – That all the items be reserved for discussion. | Decided | Open |
| 10 May 2012 | PetitionsThat the petition be noted. 259.5 The Chair then invited [name removed] to come forward and present her petition. 259... | Noted | Open |
| 10 May 2012 | Findings and Recommendations of the Brighton & Hove Living Wage Commission(1) That the findings of the Living Wage Commission and support their recommendations, as listed in paragraph 3.7 be ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.