Resolved
View the decision text for item 80.
Environment, Transport & Sustainability Committee decided this item on Tuesday 20 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 80.
2.1That Committee approve the draft Local Strategy and associated documents for public consultation.
2.2That Committee note the Objectives and associated Action Plan described in the Local Strategy setting out current local flood risk management priorities and proposed timetable for their implementation.
173 3. CONTEXT/ BACKGROUND INFORMATION
Background 3.1 Following several years of national flood events, most notably in summer 2007, the Pitt Review 2008 was published, which highlighted lessons learnt from these events. It noted that the consequences of flooding could have been reduced through more effective local co-ordination between relevant parties and recommended that Local Authorities take the lead on managing local flood risk, supported by relevant stakeholders.
3.2The area of Brighton and Hove was designated nationally as being in the top 10 areas at risk of flooding due to the impact of flooding from rising groundwater in the underground chalk aquifers, combined with surface water flooding, having the potential to flood a significant number of properties. This resulted in funding being made available by Defra to support development initially of a Surface Water Management Plan and subsequently a Local Strategy. The Surface Water Management Plan was approved by this Committee in November 2013 and informs the Local Strategy.
Legislation 3.3 In 2009, an EU Floods Directive, introduced in response to cross border European flooding in 2000 and 2004, was transposed into English law through the Flood Risk Regulations 2009. This introduced the role of a LLFA , defined as either the unitary authority for the area or the County Council. Brighton and Hove City Council thus became a LLFA with a duty under the Flood Risk Regulations to prepare the following deliverables to the Environment Agency by specific dates:
• Preliminary Flood Risk Assessment – by 22nd June 2011 • Flood Hazard maps and Flood Risk Maps – by 22nd June 2013 (for publication by the Environment Agency by 22nd December 2013) • Flood Risk Management Plan – by 22nd December 2015
3.4The Preliminary Flood Risk Assessment was produced and published by the due date on the Environment Agency web site.
3.5The Flood Risk maps were published in December 2013 by the Environment Agency. These are third generation flood risk maps, with enhanced flood modelling showing a more accurate representation of areas at risk of flood than earlier editions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Flood Risk Management StrategyReport | 100 KB | DownloadRead as text |
PDF |
View item 80. as HTML 57 KBReport | 57 KB | Download |
Follow Environment, Transport & Sustainability Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2023 | Official Feed and Food Controls Service Delivery Plan 1 April 2023 - 31 March 2024View the decision text for item 86. | Decided | Open |
| 14 Mar 2023 | Public Toilet UpdateView the decision text for item 87. | Decided | Open |
| 14 Mar 2023 | City Environment Improvement Programme UpdateView the decision text for item 88. | Decided | Open |
| 14 Mar 2023 | Local Transport Plan 2023/24 Capital ProgrammeView the decision text for item 89. | Decided | Open |
| 14 Mar 2023 | Mini Holland feasibility study - Wish & WestbourneView the decision text for item 90. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.