Brighton & Hove Highways Winter Service Plan 2016-17
This Highways Winter Service Plan incorporates the policy and operational provision of Brighton & Hove City Council’s service for clearance of snow and ice on the city’s streets. It also provides advice and information for residents and businesses.
71 Contents list
1. Summary 4
2. Objective 4
3. Service Overview 4
4. Winter Weather Conditions 5
5. Highways Winter Service 5 5.1 Gritting 5 5.2 Routes 5 5.3 Pavements 6 5.4 Treatments 6 5.5 Materials 7 5.6 Salt storage 7 5.7 Our equipment 7
6. What the Council Does 8 6.1 Responsibility for the Highway Winter Service 8 6.2 Decision making 8 6.3 Other teams involved in the winter gritting work 8 6.4 Weather forecasting 9 6.5 Communications 9
7. Salt/grit bins 10
8. Other Highway Authorities 11 8.1 Brighton & Hove/other authorities’ boundaries 11 8.2 Co-ordination with neighbouring Highway Authorities 11
9. Frequently Asked Questions 11 Grit or Salt? 11 What does salting the roads do? 12 When and how do you salt the roads? 12 Which areas of the city are salted? 12 Why are gritted roads sometimes still icy/Why does snow settle? 13 Do you close roads in icy weather? 13 Do you salt the pavements? 14 What are salt / grit bins for? 14 How do I ask for a refill of a salt / grit bin? 15 What can I do to help? 15 Driving advice 15 Walking advice 16
72 Appendix 1: Gritting Routes 17
Appendix 2: Grit Bin Criteria 18
Appendix 3: Pavement gritting 19
73 1 Summary
This document provides detailed information about the council’s highway winter service, specifically relating to public roads and pavements. It is worth noting that other agencies and council sections also have winter plans and policies which support their service objectives.
2 Objective
The Railways & Transport Act 2003: Section 111 – Highways, Snow & Ice, amends the Highways Act to give local authorities a duty, as far as is reasonably practicable, to ensure that the safe passage along a highway is not endangered by snow and ice.
The Traffic Management Act 2004 places a network management duty on the local authority to secure the expeditious movement of all users.
The objective is to provide a winter service which will permit, as far as is reasonably possible, the movement of traffic on designated roads throughout Brighton and Hove. It also aims to keep to a minimum delays and accidents brought about by adverse cold-weather conditions.
The Highways Winter Plan and budget are specifically targeted at dealing with cold weather events (i.e. ice, frost, sleet and snow). However, the identified gritting network (the city’s ‘critical road network’) and associated operations also helps inform the highway authority’s response to other severe weather events such as storms or flooding.
3 Service overview
The service covers all main roads and all bus routes within the city, plus access to emergency service depots.
In normal winter conditions, this is achieved by pre-salting the road network to prevent ice or frost forming.
In snow conditions, it is unachievable to spread sufficient salt to melt more than a very thin layer of snow and/or ice. Under such circumstances, the aim is to reclaim the network as soon as possible and particularly once snow has ceased falling.
Pavement clearance will also be carried out during snow events. Grit bins are provided across the coldest, steepest areas of the city for the public to use.
The service operates from 1 November until the end of March, 24 hours a day, 7 days a week. The period may be extended on a day-to-day basis by the Head of Highway Asset & Network Management in cases of severe cold weather continuing into April or starting earlier in October.
74 4 Winter Weather Conditions
Winter weather conditions which are managed are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for Highways Winter Service Plan 2016-17Report | 20 pages | DownloadRead as text |
PDF |
Enc. 2 for Highways Winter Service Plan 2016-17Report | 4 pages | Download |
PDF |
Highways Winter Service Plan 2016-17Report | 6 pages | Download |
PDF |
View item 29. as HTML 28 KBReport | Download |
Follow Environment, Transport & Sustainability Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2023 | Official Feed and Food Controls Service Delivery Plan 1 April 2023 - 31 March 2024View the decision text for item 86. | Decided | Open |
| 14 Mar 2023 | Public Toilet UpdateView the decision text for item 87. | Decided | Open |
| 14 Mar 2023 | City Environment Improvement Programme UpdateView the decision text for item 88. | Decided | Open |
| 14 Mar 2023 | Local Transport Plan 2023/24 Capital ProgrammeView the decision text for item 89. | Decided | Open |
| 14 Mar 2023 | Mini Holland feasibility study - Wish & WestbourneView the decision text for item 90. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.