Resolved
View the decision text for item 12.
2.1That the Committee note the report.
3 CONTEXT/BACKGROUND INFORMATION 3.1 In 2014, the council’s contractor for providing cash collection services, Coin Co International Plc (‘CCI’), entered into administration owing the council £3.243 million. The company, locally based in Burgess Hill, had been in operation for over 30 years and had been the council’s security carrier provider for over 5 years from 2008. CCI’s contract required payment of cash and coin collected from many council establishments and parking machines within 10 banking days.
3.2A number of delays in payments over to the council were experienced in 2012/13 and CCI were accordingly requested to improve performance. CCI notified the council that they had changed banks and were experiencing processing difficulties with a new system. However delays lengthened to an unacceptable level in early 2014, and the council again took steps with the contractor to improve performance.
3.3These improvements included clearing payment backlogs quickly and demanding payment over of all sums owing to the council within an agreed period. Backlog payments were made and received on arrangement for a period of months but then performance and payment delays again became unacceptable and, following formal legal exchanges, CCI were given notice with the contract terminating in August 2014.
201 3.4 The council continued to seek recovery of all sums owing at the point of termination but CCI subsequently went into administration in November 2014 owing the council £3.243m within a total debt of over £10m. It is now clear that during 2014 other creditors had also given notice, presumably due to similar performance concerns, and this ultimately resulted in the company’s insolvency.
3.5During the period of performance concerns there was constant communication from officers to the company and its directors, including site visits. Following termination of the contract, the council (and other major creditors) instructed CCI to provide them with independent reports concerning its financial health and its processing operations and seeking assurances over the recovery of sums owing. The report provided to the council was negative and very shortly afterward, CCI went into administration.
3.6The provider was collecting between £200,000 and £300,000 per week and therefore sums collected built up quickly and the security carrier would therefore legitimately be holding between £400,000 and £600,000, under the terms of the contract, before payment over to the council. Security Carrier contractors operate in this way because they are handling cash for many organisations and can negotiate very favourable banking terms as well as providing trained and accredited security staff, appropriately modified vehicles and secure bullion facilities and premises. The terms of the contract with CCI were therefore in common with most security carrier contracts for large public or private sector clients.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cash Collection: Company Administration UpdateReport | 234 KB | DownloadRead as text |
PDF |
View item 12. as HTML 21 KBReport | 21 KB | Download |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.