Resolved
View the decision text for item 13.
Audit & Standards Committee decided this item on Tuesday 24 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 13.
2.1That Audit & Standards Committee note the report.
3. CONTEXT/ BACKGROUND INFORMATION
3.1The Council and Mears entered into a long term partnership agreement in 2010 for the provision of a full range of property maintenance services and other associated works primarily but not exclusively for those properties held within the Council’s Housing Revenue Account. This report relates solely to domestic rewire activities undertaken as part of the planned maintenance programme set out in that Contract.
3.2In 2016/17 finance officers raised queries about the charges relating to domestic rewires undertaken under the Contract. These queries were initially investigated as a desktop exercise by Housing who reviewed contract and works order information stored within the Mears job management system (“MCM”). The results were flagged up with Internal Audit colleagues who carried out a small number of site visits alongside Housing surveyors to verify the accuracy of the data.
3.3The audit review identified nine areas for further investigation as follows:
1 - Sealed lights
207 2 - Duplication 3 - Incorrect code (full rewire code charged) 4 - Incorrect code (kitchen rewire after full rewire) 5 - Consumer units 6 - No actuals (incurred on job or located elsewhere) 7 - Other 8 - No actuals (incurred on job but may be located elsewhere) 9 - Electrical tests
3.4Of the nine categories some relate to the interpretation of the specification and the application of the contract schedule of rates as amended and updated since the commencement of the contract in 2010. The issues in respect of each are set out in the confidential Appendix 1 together with the concluding positions in relation to electrical work streams.
3.5As reported to committee in March 2018 through the course of detailed review of each category significant changes to contract management arrangements have been implemented.
3.6The committee meeting in March 2018 recommended “That the Audit & Standards Committee support officers in robustly pursuing Brighton & Hove City Council claims in relation to all nine categories where the legal position justifies it whilst robustly and fairly defending the city’s tenants should Mears make a counterclaim.”
3.7Senior officers have subsequently had a series of negotiation meetings with Mears and have sought legal advice on the relative strengths of the positions identified by both the council and Mears. This advice is reflected in the comments in Appendix 1.
4. ANALYSIS & CONSIDERATION OF ANY ALTERNATIVE OPTIONS
4.1None directly related to this report.
5. COMMUNITY ENGAGEMENT & CONSULTATION
5.1None directly related to this report.
6. CONCLUSION
6.1This report sets out the actions undertaken to review each of the nine categories identified. It also sets out the concluding position for each of the categories of work reviewed in line with the contractual terms.
7. FINANCIAL & OTHER IMPLICATIONS:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Electrical WorksReport | 223 KB | DownloadRead as text |
PDF |
View item 13. as HTML 47 KBReport | 47 KB | Download |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.