Housing & New Homes Committee decided this item on Wednesday 19 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 13.
That Housing & New Homes Committee notes the progress with the Programme for the future delivery of responsive repairs and empty property refurbishments, planned maintenance and improvement programmes and major capital projects to council housing stock which is outlined in the body of this report.
3. CONTEXT/ BACKGROUND INFORMATION
3.1The council (Housing department) currently operates a ten year partnering contract with Mears Limited (‘Mears’) under which the following services and works are provided for the council’s housing stock:
155 Responsive repairs and empty properties refurbishments Planned maintenance and improvement programmes Major capital projects
Decisions for future delivery
3.2PRG made the decisions set out below on 11th October 2018 following detailed debate at Housing & New Homes Committee on 26th September 2018.
That: Customer service and quality assurance services are brought in house Responsive repairs and empty property refurbishments works to council housing stock are brought in-house Planned maintenance and improvement programmes are procured through at least one contract for a term of five years with the option to extend for up to a further two years A multi-contractor framework agreement is procured for major capital projects with a term of four years That specialist works will continue to be delivered through individual contracts, with reports coming back to committee in accordance with the council’s Constitution Affirmed its intention to review whether further elements of the services and works may be brought in-house in such a way that any timescales would ensure thorough preparation and a smooth transition
For a full list of decision please see Appendix 1.
Strategic objectives for the future delivery
3.3Feedback from all stakeholders enabled the programme team to develop clear strategic objectives for the future delivery of the services and works as follows:
Excellent customer service including the ability to self-serve and greater direct customer access to repairs and maintenance services A strong focus on investment in pro-active maintenance of existing assets Increased transparency, control and accountability around cost and programme information and quality assurance Clear demonstration of value for money A social value offer that reflects priorities around work opportunities and skills building for the construction sector, and maximised local investment
KEY AREAS OF PROGRESS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Future repairs and maintenance delivery: updateReport | 285 KB | DownloadRead as text |
PDF |
View item 13. as HTML 67 KBReport | 67 KB | Copy on its way |
Follow Housing & New Homes Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2024 | Moulsecoomb Hub and Housing ProjectView the decision text for item 61. | Decided | Open |
| 13 Mar 2024 | Private Sector Housing: Discretionary Additional Licensing SchemeView the decision text for item 62. | Decided | Open |
| 13 Mar 2024 | Private Sector Housing: Discretionary Selective Licensing SchemeView the decision text for item 63. | Decided | Open |
| 13 Mar 2024 | Draft Housing Strategy 2024 to 2029View the decision text for item 64. | Decided | Open |
| 13 Mar 2024 | Housing, Health & Safety Update ReportView the decision text for item 65. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.