Future Repairs & Maintenance to Council Housing Stock

Noted Committee 2 papers

Housing Committee noted this item on Wednesday 11 March 2020. Below is the council's own wording, with the papers it was decided on.

Item65

Resolved

That the Committee notes the progress with the programme which is outlined in the body of the report. The Committee noted the progress with the programme which is outlined in the body of the report.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Committee

Recommendations

2.1That the Committee notes the progress with the programme which is outlined in the body of this report.

3. CONTEXT/BACKGROUND INFORMATION

3.1Brighton & Hove City Council currently operates a ten year partnering contract with Mears Limited (‘Mears’) under which the following services and works are provided for the council’s housing stock:

 Responsive repairs and empty property refurbishments  Planned maintenance and improvement programmes  Major capital projects

3.2Following extensive consultation, a special Housing & New Homes Committee held on 28 September 2018 and Policy, Resources & Growth Committee on 11 October 2018, the following recommendations were approved for the delivery of the above services following the expiry of the contract with Mears from April 2020:

That:

51  Customer service and quality assurance services are brought in-house  Responsive repairs and empty property refurbishment works to council housing stock are brought in-house  Planned maintenance and improvement programmes are procured through at least one contract for a term of five years with the option to extend for up to a further two years  A multi-contractor framework agreement is procured for major capital projects with a term of four years

For a full list of decisions please see Appendix 1.

4. KEY AREAS OF PROGRESS

Setting up the in-house responsive repairs service

4.1Approximately 140 Mears staff will transfer into the council on 1 April 2020. TUPE (Transfer of Undertaking Protection of Employment) protects the terms and conditions of employment of transferring staff, which will mean the staff will maintain their current contractual terms and conditions.

4.2Onboarding activities have been taking place over January and February, including the issuing of the formal measures letter to all transferring staff. This letter sets out anything which will change for staff as part of the transfer, for example transferring staff will become eligible to join the Local Government Pension Scheme (LGPS). The use of First Care to report sickness absence is a further measure which transferring staff will adopt from April.

4.3Following the issuing of the measures letter, all transferring staff have had 1-2-1 meetings with the programme team and HR, to discuss the contents of the letter and any other questions they have about the transfer.

4.4The set up and testing of the IT software and equipment for the service has been carried out in February, including the use of new handheld PDA (Personal Digital Assistant) devices for the operatives. The continued use of the MCM software under a contract with Mears will enable the staff transferring over to schedule jobs, purchase and collect materials, replenish van stock, and track the costs of jobs in the same way as is currently done. This will allow for a smoother transition as the service transfers into the council and minimise the impact on service levels currently received by residents.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Future Repairs & Maintenance to Council Housing StockReport 354 KB DownloadRead as text
PDF
View item 65. as HTML 36 KBReport 36 KB Download

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Future Repairs & Maintenance to Council Housing StockThis decision
  2. Future repairs & maintenance to council housing stock.Decided
  3. Future Repairs and Maintenance to Council Housing StockNoted
  4. Programme for the future delivery of responsive repairs and empty property refurbishments, planned maintenance and improvement programmes, and major capital projects to council housing stockDecided
  5. Future repairs and maintenance delivery – updateDecided
  6. Options for future delivery of housing repairs, planned maintenance and capital worksDecided

More from Brighton and Hove Housing Committee

All decisions
MeetingDecisionOutcome
15 Mar 2023 Private Sector Housing: Discretionary licensing evidence2.1 That Housing Committee notes the findings of the Private Sector Housing: Housing Stock Condition & Stressors Repo... Approved Open
15 Mar 2023 Housing Repairs and Maintenance – Procurement of Materials Supply ChainThat Housing Committee delegates authority to the Executive Director of Housing, Neighbourhoods and Communities to: 2... Approved Open
15 Mar 2023 Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc... Approved Open
15 Mar 2023 Homes for Brighton & Hove – external communal area management at Coldean Lane, Brighton.That Housing Committee: 2.1 Recommends to Policy & Resources Committee that it delegates authority to the Executive D... Decided Open
15 Mar 2023 Develop a policy to incentives households to relinquish council tenancies as an alternative to right to buy2.1 That Housing Committee note this report. 2.2 That Housing Committee agree to a full report coming back to a futur... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies