Resolved
View the decision text for item 11.
Policy, Resources & Growth Committee decided this item on Thursday 18 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 11.
2.1That the committee notes the progress on work associated with the Central Hub.
2.2That committee agree the increased budget allocation for the Downsview and Hill Park projects.
2.3That Committee grants delegated authority to the Assistant Director of Property & Design to procure the capital projects and enter into contracts within these budgets, as required, in accordance with Contract Standing Orders in respect of the Downsview and Hill Park projects.
3. CONTEXT/ BACKGROUND INFORMATION
3.1At its meeting in March the PR&G committee considered the Education Capital Resources and Capital Investment Programme 2019/2020 report. This report contained details relating to the projects being taken forward as a result of the SEND review.
3.2Amendments were proposed to the recommendations of that report which were accepted by the committee.
3.3The amendments were that the committee agreed to a minimum budget of £12million for the three SEND projects and that officers would bring a further report to the PR&G committee setting out plans for any additional refurbishment required at Downsview School in order to ensure that the entire estate is fit for
209 purpose. The report was to identify additional funding required and potential funding opportunities and options to meet this.
3.4A further recommendation required that officers also report to this meeting a broad strategy and plan for the central hub setting out the likely allocation of the £4million funding identified.
3.5This report addresses these two issues.
Downsview and Hill Park Projects
3.6Officers have continued to work with both Hill Park and Downsview on the projects. Amendments have been made to the plans for Downsview which has resulted in a further area of the school being refurbished and providing the school with an additional 3 classrooms.
3.7The school accepts that this is an increase in the level of work proposed and has said that they prefer the revised scheme. However the school remains concerned that the remainder of the existing school is not being refurbished.
3.8The head teacher and governors of Hill Park School are happy that the scheme for their two sites will meet the needs of their pupils.
3.9Planning consent has been granted for the two projects.
3.10In addition to this work the projects have been being priced by the Strategic Partnerships cost consultants following the Agreed Maximum Price (AMP) submission from the constructor.
3.11This work has identified that the cost of the two projects is greater than the budget estimate of £8million. This reflects costs from the additional design plans developed
3.12The cost consultant has been able to issue a Best Value report in respect of both the Downsview and Hill Park projects with construction costs of £5,420,000 and £2,290,000 respectively.
3.13When fees and the cost of furniture, fitting and equipment (FF&E) are added to these costs this would result of a total project cost of £6.6 million for Downsview and £2.8million for Hill Park.
3.14It is now recommended that the budget for these two projects is increased to £9.4million. The necessary additional funding can be allocated from the unallocated Basic Need funding that is set aside for wider contingencies across the school estate (identified in Appendix 3 of the March PR&G report).
Central Hub
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on the capital works undertaken as part of the SEND ReviewReport | 232 KB | DownloadRead as text |
PDF |
View item 11. as HTML 76 KBReport | 76 KB | Download |
Follow Policy, Resources & Growth Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jul 2019 | BAi360 June 2019 PaymentView the decision text for item 6. | Decided | Open |
| 18 Jul 2019 | Targeted Budget Management (TBM) Provisional Outturn 2018/19View the decision text for item 7. | Decided | Open |
| 18 Jul 2019 | Targeted Budget Management (TBM) 2019/20: Month 2View the decision text for item 8. | Decided | Open |
| 18 Jul 2019 | Treasury Management STrategy Statement 2018/19 - End of Year ReviewView the decision text for item 9. | Decided | Open |
| 18 Jul 2019 | Revenue & Capital Budget Planning and Resource Update 2020/21 to 2023/24View the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.