107 1. Role of Internal Audit
1.1The full role and scope of the Council’s Internal Audit Service is set out within the Internal Audit Charter and Terms of Reference, the latest version of which is attached to this Strategy as Appendix 3.
1.2The mission of Internal Audit, as defined by the Chartered Institute of Internal Auditors (CIIA), is to enhance and protect organisational value by providing risk-based and objective assurance, advice and insight. Internal Audit is defined as “an independent, objective assurance and consulting activity designed to add value and improve an organisation’s operations. It helps an organisation accomplish its objectives by bringing a systematic, disciplined approach to evaluate and improve the effectiveness of risk management, control and governance processes.”
1.3The organisation’s response to internal audit activity should lead to a strengthening of the control environment, thus contributing to the overall achievement of organisational objectives.
2. Risk Assessment and Audit Planning
2.1The City County Council’s Internal Audit Strategy and Annual Audit Plan is updated annually and is based on a number of factors, especially management’s assessment of risk (including that set out within the strategic and departmental risk registers) and our own risk assessment of the Council’s major systems and other auditable areas. This allows us to prioritise those areas to be included within the audit plan on the basis of risk.
2.2Due to the uncertainty created by the impact of Covid 19, the 2021/22 plan focusses primarily on the core assurance areas (such as all key financial systems), the highest priority reviews across the council, grant claims and known key priority projects/programmes, with the remainder of the direct audit days earmarked as emerging risks/contingency . Appropriate provision will also be made for counter fraud activities, which will continue in 2021/22 as normal. By adopting this approach, as well as delivering the planned work on core assurance areas, we will add internal audit activities to our plans throughout the year as new risks and priorities emerge. All of this will be regularly and comprehensively reported to ELT and the Audit and Standards Committee and will enable us to maximise our responsiveness and focus our resources on the most relevant and priority areas.
2.3It is important to note that this slightly revised planning strategy for the year ahead will not result in any reduced internal audit coverage for the Council. The approach is simply intending to help ensure we remain as reactive as possible to the rapidly changing risk landscape across the Authority in such unprecedented times.
2.4The annual planning process has once again involved consultation with a range of stakeholders, to ensure that their views on risks and current issues, within individual directorates and corporately, are identified and considered. In order to ensure that the most effective use is made of available resources, to avoid duplication and to minimise service disruption, efforts will continue to be made to identify, and where possible, rely upon, other sources of assurance available. The following diagram sets out the various sources of information used to inform our 2021/22 audit planning process:
Brighton & Hove City Council
108 2.5 In order to ensure audit and assurance activity is properly focussed on supporting the delivery of the Council’s priorities, the audit plan has taken into account the outcomes that have been agreed in the Council Plan to make Brighton & Hove, a fairer city with a sustainable future. These are a:
City to call home; City working for all; Stronger city; Growing and learning city; Sustainable city; Healthy and caring city.
2.4In producing the audit plan (which is set out in Appendix A to this report) the following key principles continue to be applied:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Strategy and Annual Plan (2021/22) APX. n 1Report | 562 KB | DownloadRead as text |
PDF |
Internal Audit Strategy and Annual Plan (2021/22) APX. n 2Report | 298 KB | Download |
PDF |
Internal Audit Strategy and Annual Plan (2021/22) APX. n 3Report | 316 KB | Download |
PDF |
Internal Audit Strategy and Annual Plan (2021/22)Report | 223 KB | Download |
PDF |
View as HTML (56./2) 65 KBReport | 65 KB | Copy on its way |
PDF |
View as HTML (56./3) 53 KBReport | 53 KB | Copy on its way |
PDF |
View as HTML (56./4) 34 KBReport | 34 KB | Copy on its way |
PDF |
View item 56. as HTML 24 KBReport | 24 KB | Copy on its way |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.