2.1 That Committee approves the procurement and award of a four-year multi contractor framework agreement for the specialist works as described in paragraphs 4.2 and 4.3 below. 2.2 That Committee grants delegated authority to the Executive Director of Housing, Neighbourhoods and Communities to take all necessary steps to implement recommendation 2.1 and to award call-off contracts using the framework. 2.3 That Committee approves the tendering of Asbestos Surveys via the Council’s Construction Related Consultancy Dynamic Purchasing System (DPS). 2.4 That Committee approves the use of the Council Highways Works Framework for road surfacing works required in Council managed Housing car parks and garages. 2.1 That Committee approves the procurement and award of a four-year multi contractor framework agreement for the specialist works as described in paragraphs 4.2 and 4.3 below. 2.2 That Committee grants delegated authority to the Executive Director of Housing, Neighbourhoods and Communities to take all necessary steps to implement recommendation 2.1 and to award call-off contracts using the framework. 2.3 That Committee approves the tendering of Asbestos Surveys via the Council’s Construction Related Consultancy Dynamic Purchasing System (DPS). 2.4 That Committee approves the use of the Council Highways Works Framework for road surfacing works required in Council managed Housing car parks and garages.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
The Procurement Advisory Board is requested to provide recommendations to Housing Committee that it recommends:
The procurement and award of a four-year multi-contractor framework agreement for the specialist works as detailed in section 3.3 of this report.
35 That the Executive Director of Housing, Neighbourhoods and Communities is granted delegated authority to take all necessary steps to implement the framework agreement and to award call-off contracts using the framework.
The tendering of Asbestos Surveys via the Council’s Construction Related Consultancy Dynamic Purchasing System (DPS)
The use of the Council Highways Works Framework for road surfacing works required in Council managed Housing car parks and garages
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1Background In order to enable the Repairs & Maintenance (R&M) service to be up and running by the 1st of April 2020, the council relied on the use of contract waivers to procure a works management system, a vehicle fleet and a supply chain for materials and subcontractors.
These decisions were made under the delegated authority agreed at Housing Committee and the New Homes Committee, September 2018, and Policy Resources and Growth Committee, October 2018, to award contracts required to implement the recommendations set out in that report.
Appropriate legal and procurement advice were taken and waivers were approved by the Executive Director and lead councillors on the Housing Committee. Members were also informed of the intention to enter into these contracts by a report to the January 2020 Housing Committee
A waiver to continue to use Mears approved list of suppliers, a specified list of 21 subcontractors, was agreed (Waiver CP341), as procurement of a council works supply chain was not possible in early 2020 and due to the continued use of the Mears legacy IT works management systems. The waiver for the use of contractors expires on the 31st March 2022.
In line with recommendations arising from Internal Audit of Repairs & Maintenance service reported to January 2020 Audit & Standards Committee and Housing Committee (20 January 2021) this procurement aligns to the agreed audit actions, that: The service will ensure that any additional procurements are planned in such a way to avoid the use of waivers. Procurements should be scheduled to replace the existing waiver arrangements as soon as existing contracts allow.
36 The service will procure additional subcontractors to meet the requirements of the housing repairs service. Procurements will be in accordance with the councils Contract Standing Orders.
The Council’s own separately procured IT system, Northgate Housing Contractor portal is scheduled to go live in the summer of 2021, allowing for the procurement of a contractor solution for the Council to enter into contract with all the additional services required by the Repairs & Maintenance team. With the Northgate Housing Contractor portal in place, the service will be able to issue works and payments to contractors.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.