New Homes for Neighbourhoods - Windlesham House

Approved Committee 5 papers

Housing Committee approved this item on Wednesday 23 June 2021. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Housing Committee: 2.1 That the proposals to demolish Windlesham House and develop 17 new council homes at Windlesham Close, Portslade, under the NHFN programme be approved; and 2.2 That it be agreed that the project proceeds through the City Build Partnership, the council’s Strategic Construction Partnership with Morgan Sindall. 2.3 That Policy & Resources Committee be recommended to approve a capital budget of up to £5.300m to be included in the 2021/22 HRA Capital Programme and financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts. Policy & Resources Committee: 2.4 That a HRA Capital budget of up to £5.300m financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts be approved, to be included in the 2021/22 HRA Capital Programme. Housing Committee: 2.1 That the proposals to demolish Windlesham House and develop 17 new council homes at Windlesham Close, Portslade, under the NHFN programme be approved; and 2.2 That it be agreed that the project proceeds through the City Build Partnership, the council’s Strategic Construction Partnership with Morgan Sindall. 2.3 That Policy & Resources Committee be recommended to approve a capital budget of up to £5.300m to be included in the 2021/22 HRA Capital Programme and financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts. Policy & Resources Committee: 2.4 That a HRA Capital budget of up to £5.300m financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts be approved, to be included in the 2021/22 HRA Capital Programme.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Committee

Windlesham House Windlesham House Stage 2 Report June 2021 Stage 2 Report Miller Bourne Architects 87 2

Contents 1.0 Introduction 2.0 The Site 3.0 Architectural Report 4.0 Ecological and Tree Survey 5.0 Summary 88 3

1.0Introduction Opening Statement In July 2018 a high level feasibility study was undertaken by Miller Bourne Architects to consider a number of options for a development of flats on the site on the corner of Windlesham Close and Locks Crescent, currently occupied by Windlesham House. Different densities were explored through two options with sub-options providing additional flats in an additional storey.

Following a review of the options, it was decided in September 2019 to proceed with a Stage 2 concept design for the construction of 17 affordable flats over 3 and 4 storeys including 2No wheelchair accessible flats designed to Part M4(3) standard. In addition to the wheelchair accessible flats, the design included the following:

1 Bed 2 person flats @ 52m2 and 53m2 6No 2 Bed 3 person flats @ 71m2 3No 2 Bed 4 person flats @ 72m and 81m 2 2 6No 89

A public consultation was held and the design submitted for Pre-app advice. Following this, the designs were reconsidered to take into account some of the issues raised and a further Stage 2 concept with a smaller footprint was proposed. This document outlines the latest proposal and provides background information on the site. In addition to the 2No M4(3) flats, the latest proposal includes the following (same number and type of flats, but smaller footprints): 1 Bed 2 person flats @ 50m2 and 51m2 6No 2 Bed 3 person flats @ 67m 2 3No 2 Bed 4 person flats @ 72m2 and 73m2 6No

Total 17 flats over 3-4 storeys 4

2.0The Site Location The site is located on the corner of Windlesham Close and Locks Crescent in Portslade, Hove, to the south of the Portslade Village Centre, also to be

WINDLESHAM CLOSE developed as part of the New homes for Neighbourhoods Programme. Located across Windlesham Close to the west are the Camp Site allotments; to the north across Locks Crescent are senior’s council flats; and adjacent to the east are general needs council flats. The site slopes eastwards and the current one storey building is cut into the slope. A dense area of trees and bushes surround the building. There are no current tree protection orders. Massing in the local area is low rise, between one and three stories. The adjacent building to the east, further up the slope, is three stories. The Windlesham house site boundary is highlighted opposite and measures 0.11Hectares. As the areas highlighted in yellow show HRA freehold land, the site boundary, for the purposes of the concept design, can be adjusted to suit 90

local constraints i.e. encroachment into the area surrounding 1-17 Locks Crescent to achieve optimum use of the land. 5

2.0The Site Site Photographs and context The existing building on the site is currently leased to the Royal Voluntary Service who has advised of its intention to rescind the lease and pass the building back to the HRA and the process is underway. To the East of the site at the top of the hill is a yellow brick, 3 storey block of flats (1) and to the north are two storey flats (2). To the west is a sub-station and allotments, and to 1 4 the south car parking and houses which are some 30+ metres from the boundary wall (5). The general massing of the area is relatively low-rise but the three storey block at the feels higher as it is at the top of the hill.

Key Views Key views of the site are afforded from Locks Crescent (3 91

and 6) and from the grassed area in front of the 3 storey block of flats (4). The site is sloping and as such any development will need to be partially cut into the hill with a step in the structure. 2 5 Any wheelchair accessible flats will need to be located at the front (west) of the site.

3 6 6

3.0Architectural Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Homes for Neighbourhoods: Windlesham House APX. n 1Report 2.6 MB DownloadRead as text
PDF
New Homes for Neighbourhoods: Windlesham House APX. n 2Report 281 KB Download
PDF
New Homes for Neighbourhoods: Windlesham HouseReport 338 KB Download
PDF
View as HTML (10./3) 39 KBReport 39 KB Copy on its way
PDF
View item 10. as HTML 52 KBReport 52 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. New Homes for Neighbourhoods - Windlesham HouseThis decision
  2. New Homes for NeighbourhoodsDecided
  3. Next phase of New Homes for Neighbourhoods programmeDecided
  4. New Homes for Neighbourhoods Rotherfield Crescent - Procurement of ContractorAgreed
  5. New Homes for Neighbourhoods Frederick Street - Procurement of ContractorDecided
  6. Update on Sustainability Measures for New Homes and Housing Supply Sustainability PolicyDecided

More from Brighton and Hove Housing Committee

All decisions
MeetingDecisionOutcome
15 Mar 2023 Private Sector Housing: Discretionary licensing evidence2.1 That Housing Committee notes the findings of the Private Sector Housing: Housing Stock Condition & Stressors Repo... Approved Open
15 Mar 2023 Housing Repairs and Maintenance – Procurement of Materials Supply ChainThat Housing Committee delegates authority to the Executive Director of Housing, Neighbourhoods and Communities to: 2... Approved Open
15 Mar 2023 Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc... Approved Open
15 Mar 2023 Homes for Brighton & Hove – external communal area management at Coldean Lane, Brighton.That Housing Committee: 2.1 Recommends to Policy & Resources Committee that it delegates authority to the Executive D... Decided Open
15 Mar 2023 Develop a policy to incentives households to relinquish council tenancies as an alternative to right to buy2.1 That Housing Committee note this report. 2.2 That Housing Committee agree to a full report coming back to a futur... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies