Internal Audit and Counter Fraud Quarter 2 Progress Report 2021/22

Decided Finance 4 papers

Audit & Standards Committee decided this item on Tuesday 25 January 2022. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

View the decision text for item 38.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Audit & Standards Committee

Appendix 1

Internal Audit and Counter Fraud Quarter 2 Progress Report 2021/22

CONTENTS 1. Summary of Completed Audits

2. Counter Fraud and Investigation Activities

3. Action Tracking

4. Amendments to the Audit Plan

5. Internal Audit Performance

Brighton & Hove City Council

61 1. Summary of Completed Audits

Procurement Compliance (Phase 1) – Minimal Assurance

1.1The purpose of this audit was to obtain assurance that where suppliers have been paid more than £75,000, Contract Standing Orders (CSOs) have been complied with and value for money has been demonstrated.

1.2Our review used data analytics and revealed a high number of instances where there has been supplier expenditure above £75k but where there was no match to the Contracts Register. The initial scope for this audit had not anticipated this, or therefore the extent of Internal Audit resources required to investigate the individual procurements and their compliance with CSO’s. As a result, we have split our work into phases, with this phase one review, focusing on the quality of data captured on the Contracts Register. Additional internal audit resources have been set aside to deliver a second phase of work, seeking to provide assurance over whether there has been appropriate compliance with CSO’s in relation to competitive tendering arrangements. This audit is progressing and will be reported on in future updates.

1.3This initial review examined data for a 12 month period ending 30/11/2020 and just focused on suppliers with expenditure of more than £75k. This period coincided with the start of the Council response to COVID-19 and includes emergency procurement decisions.

1.4Our review found that data held in the corporate Contracts Register is incomplete and omits contract arrangements with a significant number of contractors. This is a breach of Contract Standing Order 17 (Contracts Register and Records). The absence of this information significantly hampers the ability of the corporate centre and individual directorates to plan and monitor procurements so that they deliver value for money. It also means that the Council is unable to comply with the Public Contracts Regulations 2015 transparency requirement to publish contract information on the Council website.

1.5Our review identified that 43% of suppliers where we had purchased goods, works or services above £75k could not be matched to the Contracts Register. Officers had raised purchase orders to the value of £42.6m with these suppliers in the twelve-month period examined.

1.6Our follow-up enquires with contract officers identified that in some cases the absence of the information indicated that tendering had not taken place in accordance with Contract Standing Orders. However, in most cases officers explained that a process had taken place, but the information had not been added to the Contracts Register. We are therefore, at this stage unable to provide assurance in this area until such time as we have completed the second phase of our review, focussing on the details of individual procurements.

Brighton & Hove City Council

62 1.7 We found that many of the contracts let under emergency powers, through Gold Command arrangements, to provide goods and services related to the COVID -19 pandemic, are not on the Contracts Register. This accounted for 30 of the suppliers that we had not been able to match to the Contracts Register. Waivers were not approved retrospectively to provide a central record of these procurements. There is likely to be public interest and scrutiny on these purchasing decisions and reporting of them would be expected.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit and Counter Fraud Quarter 2 Progress Report 2021/22 APX. n 1Report 448 KB DownloadRead as text
PDF
Internal Audit and Counter Fraud Quarter 2 Progress Report 2021/22Report 327 KB Download
PDF
View as HTML (38./2) 111 KBReport 111 KB Copy on its way
PDF
View item 38. as HTML 22 KBReport 22 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Internal Audit and Counter Fraud Quarter 2 Progress Report 2021/22This decision
  2. Internal Audit Annual Report and Opinion 2025/26Decided
  3. Internal Audit and Counter Fraud Quarter 4 Progress Report 2025/26Decided
  4. Internal Audit Strategy and Annual Audit Plan 2026-27Decided
  5. Internal Audit and Counter Fraud Quarter 3 Progress Report 2025/26Decided
  6. Internal Audit and Counter Fraud Quarter 2 Progress Report 2025/26Decided

More from Brighton and Hove Audit & Standards Committee

All decisions
MeetingDecisionOutcome
26 Sep 2023 Audit Findings Report 2022/23View the decision text for item 21. Decided Open
26 Sep 2023 Audited Statement of Accounts 2022/23View the decision text for item 22. Decided Open
26 Sep 2023 External Auditors Annual Report 2022/23View the decision text for item 23. Decided Open
26 Sep 2023 Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. Decided Open
26 Sep 2023 Standards UpdateView the decision text for item 25. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies