2.1 That the Housing Committee note the progress on the programme of works for the replacement of non-complaint (Manse Masterdors) front entrance doors and frames. 2.2 That the Housing Committee approve the recommended approach with regard to charging of leaseholders for replacement of non-compliant front entrance doors and frames. 2.1 That the Housing Committee note the progress on the programme of works for the replacement of non-complaint (Manse Masterdors) front entrance doors and frames. 2.2 That the Housing Committee approve the recommended approach with regard to charging of leaseholders for replacement of non-compliant front entrance doors and frames.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That the Housing Committee note the progress on the programme of works for the replacement of non-complaint (Manse Masterdors) front entrance doors and frames.
2.2That the Housing Committee approve the recommended approach with regard to charging of leaseholders for replacement of non-compliant front entrance doors and frames.
129 3. CONTEXT/ BACKGROUND INFORMATION
3.1Emerging building and fire safety legislation, regulation and potential investment requirements with regard to Council homes has been reflected in the Housing Revenue Account (HRA) Budget & Capital Investment Programme 2022/23 and will be the subject of future reports to Housing Committee.
3.2During the period up to 2010 we undertook a programme of replacement flat entrance doors to upgrade to a fire door that was suitably certified. The product selected at the time was Manse Masterdor, which was of a suitable certification to meet the requirements.
3.3Following the Grenfell tragedy Manse Masterdors were tested as part of the rigorous investigation and failed the classification regime and hence we now have a requirement to replace these to all properties where previously installed.
3.4Following the appointment of our planned works contractors in April 2021 we commenced a process of identifying and approving a door and frame set that met the new standard and requirements and met the rigorous certification necessary under the new regulations, we concluded the certification process in August 2021 and suppliers were appointed.
3.5Our contractor for the replacement doors programme is A D Construction Group.
3.6Our replacement programme commenced October 2021. We have 1,980 Manse Masterdors to replace, this is made up of 1,888 front doors and 92 rear doors, we have treated the replacement of these as priority within our programmes and we anticipate completing the upgrades in 2024.
3.7The 2022/23 budget for the replacement door programme which will incorporate Manse Master doors is £1.20m, the estimated cost to replace the Manse Masterdors is £2.97m over 3 financial years.
3.8As this programme is over a number of years we have carried out additional fire risk assessments on all of our high-rise buildings where Masterdors are installed. We have specifically looked at the potential impacts of the door failing within 30 minutes and the assessments have confirmed that the risk is low.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.