CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Brighton and Hove City Council
Housing Committee, Wednesday 28 September 2022 at 4.00pm

Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23

Noted Committee 8 papers

Housing Committee noted this item on Wednesday 28 September 2022. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

2.1 That Housing Committee note the Housing performance report Quarter 1 - 2022/23 and Housing Committee Work Plan progress update. 2.2 That Housing Committee note the additional performance indicators relating to private sector housing included in the Housing Committee Work Plan progress update and Housing performance report, Appendix 1, page 16 of 25. 2.3 That Housing Committee approve the re-scheduled and reviewed Housing Committee Work Plan attached in Appendix 2. 2.4 That Housing Committee note progress on each area of work set out in the 2019-2023 Housing Programme under Appendix 3. 2.1 That Housing Committee note the Housing performance report Quarter 1 - 2022/23 and Housing Committee Work Plan progress update. 2.2 That Housing Committee note the additional performance indicators relating to private sector housing included in the Housing Committee Work Plan progress update and Housing performance report, Appendix 1, page 16 of 25. 2.3 That Housing Committee approve the re-scheduled and reviewed Housing Committee Work Plan attached in Appendix 2. 2.4 That Housing Committee note progress on each area of work set out in the 2019-2023 Housing Programme under Appendix 3.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Committee

Committee workplan progress update and Housing performance report Quarter 1 2022/23 This report provides updates on the Housing Committee priorities and work plan for 2019 to 2023, as well as a range of performance indicators. Delivery of a complex housing service during the Covid-19 pandemic and recovery phase had been a challenge, and gratitude is expressed to residents for the patience and understanding they have shown.

While there continue to be areas of strong performance, with 21 Housing Committee Work Plan objectives on track for delivery and 8 performance indicators on target, some delivery challenges remain. The report highlights actions being taken to improve services where performance has been adversely impacted by the Covid-19 pandemic and recovery phase, and resource capacity issues.

Performance areas Page Housing Committee priorities and work plan Additional council homes 4, 6, 19 Other additional affordable homes 5 Council home buy backs 4, 8, 9, 20 Right to Buy sales 6, 19 Sites identified for Community Land Trust development 6 Private sector housing ‘requests for assistance’ received 7 Rough sleepers 8 Housing First placements 8 Energy efficiency rating of council homes 10, 24 Private sector empty homes returned to use 12, 16 Compliments and complaints – all Housing Services 15

Page 1 of 25

139 Performance areas Page Private sector housing Houses in Multiple Occupation (HMO) licensing 16 Private sector vacant dwellings returned to use 16 Housing major adaptations 17 Private housing – time to approve applications 17 Council housing – time to approve applications 17 Housing Options and allocations Homelessness preventions 17 Homelessness acceptances 17 Social housing waiting list 17 Temporary and emergency accommodation Households placed 18 Rent collected 18 Empty homes 18 Gas safety compliance (Seaside Homes and leased) 18 Council housing supply Additional homes by rent level 19 Council housing management Rent collected 21 Universal Credit 21 Tenants evicted 21 Anti-social behaviour (ASB) 21 Calls answered (Housing Customer Services) 21 Tenancies sustained 21 Re-let times 22 Empty homes 22 Council housing repairs and maintenance Repairs completed in time 23 Satisfaction with completed repairs 23 Calls answered (Repairs Helpdesk) 23 Council housing investment and asset management Decent Homes Standard 24 Gas safety compliance (council homes) 24 Lift breakdowns 24 Leaseholder disputes 25

Page 2 of 25

140 This housing performance report covers Quarter 1 (Q1) of the 2022/23 financial year. It uses red, amber and green ratings to provide an indication of performance.

Part one provides an update of performance against the Housing Committee work plan objectives for 2019 – 2023:

1 Work plan objectives 4 3% 12%

21 are green (on track) 8 are amber (slightly off track) 8 4 are red (off track) 23% 21 62% 1 is no longer applicable

Part two presents results for a range of performance indicators across Housing and similarly uses red, amber and green ratings, as well as trend arrows. Commentary has been included for indicators which are red. During Quarter 1, the ratings and trends were as follows:

Green – on target Improved since last time G (8 indicators) (11 indicators)

Amber – near target Same as last time A (10 indicators) (2 indicators)

Red – off target Poorer than last time R (8 indicators) (13 indicators)

Performance indicators

8 are green (on target) 8 8 31% 31% 10 are amber (near target)

8 are red (off target)

10 38%

Page 3 of 25

141 Part one: Housing Committee priorities and work plan 2019-23

1. Provide additional affordable homes 1.1 Off track: Achieve 800 additional council homes (including develop the existing Hidden Homes strategy) Regular updates on progress are provided to Housing Supply Member Board.

A total of 497 homes are projected for completion between April 2019 and March 2023, including 343 already completed:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23 APX. n 1Report 889 KB DownloadRead as text
PDF
Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23 APX. n 2Report 397 KB Download
PDF
Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23 APX. n 3Report 359 KB Download
PDF
Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23Report 297 KB Download
PDF
View as HTML (30./2) 359 KBReport 359 KB Copy on its way
PDF
View as HTML (30./3) 41 KBReport 41 KB Copy on its way
PDF
View as HTML (30./4) 68 KBReport 68 KB Copy on its way
PDF
View item 30. as HTML 46 KBReport 46 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23This decision
  2. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2022/23Decided
  3. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 2 2022/23Decided
  4. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 4 and end of year 2021/22Decided
  5. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2021/22Decided
  6. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 2 2021/22Decided

More from Brighton and Hove Housing Committee

All decisions
MeetingDecisionOutcome
15 Mar 2023 Private Sector Housing: Discretionary licensing evidence2.1 That Housing Committee notes the findings of the Private Sector Housing: Housing Stock Condition & Stressors Repo... Approved Open
15 Mar 2023 Housing Repairs and Maintenance – Procurement of Materials Supply ChainThat Housing Committee delegates authority to the Executive Director of Housing, Neighbourhoods and Communities to: 2... Approved Open
15 Mar 2023 Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc... Approved Open
15 Mar 2023 Homes for Brighton & Hove – external communal area management at Coldean Lane, Brighton.That Housing Committee: 2.1 Recommends to Policy & Resources Committee that it delegates authority to the Executive D... Decided Open
15 Mar 2023 Develop a policy to incentives households to relinquish council tenancies as an alternative to right to buy2.1 That Housing Committee note this report. 2.2 That Housing Committee agree to a full report coming back to a futur... Agreed Open