CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Brighton and Hove City Council
Housing Committee, Wednesday 15 March 2023 at 4.00pm

Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2022/23

Decided Committee 4 papers

Housing Committee decided this item on Wednesday 15 March 2023. Below is the council's own wording, with the papers it was decided on.

Item75

Resolved

2.1 That Housing Committee notes the report.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Committee

Committee workplan progress update and Housing performance report Quarter 3 2022/23 This report provides updates on the Housing Committee priorities and work plan for 2019 to 2023, as well as a range of performance indicators. There continue to be areas of strong performance, with 25 Housing Committee Work Plan objectives on track for delivery and 13 performance indicators on target. Furthermore, there has been an improvement in 16 of the performance indicators since the previous quarter. However, some delivery challenges remain. The report highlights actions being taken to improve services.

Performance areas Page Housing Committee priorities and work plan Additional council homes 4, 6, 19 Other additional affordable homes 4 Council home buy backs 4, 8, 9, 20 Right to Buy sales 6, 19 Sites identified for Community Land Trust development 6 Requests For Assistance received 7, 16 Rough sleepers 8 Housing First placements 8 Energy efficiency rating of council homes 10, 24 Private sector empty homes returned to use 12, 16 Compliments and complaints – all Housing Services 15

Private sector housing Houses in Multiple Occupation (HMO) licensing 16 Private sector vacant dwellings returned to use 16 Property inspections completed 16

Page 1 of 25

143 Performance areas Page Housing major adaptations 17 Private housing – time to approve applications 17 Council housing – time to approve applications 17 Housing Options and allocations Homelessness preventions 17 Homelessness acceptances 17 Social housing waiting list 17 Temporary and emergency accommodation Households placed 18 Rent collected 18 Empty homes 18 Gas safety compliance (Seaside Homes and leased) 18 Council housing supply Additional homes by rent level 19 Council housing management Rent collected 21 Universal Credit 21 Tenants evicted 21 Anti-social behaviour (ASB) 21 Calls answered (Housing Customer Services) 22 Tenancies sustained 22 Re-let times 22 Empty homes 22 Council housing repairs and maintenance Repairs completed in time 23 Satisfaction with completed repairs 23 Calls answered (Repairs Helpdesk) 23 Council housing investment and asset management Decent Homes Standard 24 Gas safety compliance (council homes) 24 Lift breakdowns 24 Leaseholder disputes 25

Page 2 of 25

144 This housing performance report covers Quarter 3 (Q3) of the 2022/23 financial year. It uses red, amber and green ratings to provide an indication of performance.

Part one provides an update of performance against the Housing Committee work plan objectives for 2019 – 2023:

1 Work plan objectives 3 3% 9%

25 are green (on track) 5 15% 5 are amber (slightly off track) 3 are red (off track)

25 1 is no longer applicable 73%

Part two presents results for a range of performance indicators across Housing and similarly uses red, amber and green ratings, as well as trend arrows. Commentary has been included for indicators which are red. During Quarter 3, the ratings and trends were as follows:

Green – on target Improved since last time G (13 indicators) (16 indicators)

Amber – near target Same as last time A (7 indicators) (0 indicators)

Red – off target Poorer than last time R (6 indicators) (8 indicators)

Performance indicators

6 13 are green (on target) 23%

7 are amber (near target) 13 50% 6 are red (off target) 7 27%

Page 3 of 25

145 Part one: Housing Committee priorities and work plan 2019-23

1. Provide additional affordable homes 1.1 Off track: Achieve 800 additional council homes (including develop the existing Hidden Homes strategy) Regular updates on progress are provided to Housing Supply Member Board.

A total of 493 homes are projected for completion between April 2019 and March 2023, including 384 already completed. The projected total for 2022/23 (164) exceeds all previous years, and this programme has been delivered during a period of unprecedented complexity due to the Covid-19 pandemic and recovery phase

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2022/23 APX. n 1Report 896 KB DownloadRead as text
PDF
Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2022/23Report 296 KB Download
PDF
View as HTML (75./2) 372 KBReport 372 KB Copy on its way
PDF
View item 75. as HTML 43 KBReport 43 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2022/23This decision
  2. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 2 2022/23Decided
  3. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 1 2022/23Noted
  4. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 4 and end of year 2021/22Decided
  5. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 3 2021/22Decided
  6. Housing Committee Workplan Progress Update and Housing Performance Report Quarter 2 2021/22Decided

More from Brighton and Hove Housing Committee

All decisions
MeetingDecisionOutcome
15 Mar 2023 Private Sector Housing: Discretionary licensing evidence2.1 That Housing Committee notes the findings of the Private Sector Housing: Housing Stock Condition & Stressors Repo... Approved Open
15 Mar 2023 Housing Repairs and Maintenance – Procurement of Materials Supply ChainThat Housing Committee delegates authority to the Executive Director of Housing, Neighbourhoods and Communities to: 2... Approved Open
15 Mar 2023 Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc... Approved Open
15 Mar 2023 Homes for Brighton & Hove – external communal area management at Coldean Lane, Brighton.That Housing Committee: 2.1 Recommends to Policy & Resources Committee that it delegates authority to the Executive D... Decided Open
15 Mar 2023 Develop a policy to incentives households to relinquish council tenancies as an alternative to right to buy2.1 That Housing Committee note this report. 2.2 That Housing Committee agree to a full report coming back to a futur... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies