INTERNAL AUDIT ANNUAL REPORT & OPINION 2023/2024
Brighton & Hove City Council
93 1. Internal Control and the Role of Internal Audit
1.1All local authorities must make proper provision for internal audit in line with the 1972 Local Government Act (S151) and the Accounts and Audit Regulations 2015. The full role and scope of the Council’s Internal Audit Service is set out within our Internal Audit Charter.
1.2It is a management responsibility to establish and maintain internal control systems and to ensure that resources are properly applied, risks appropriately managed and outcomes achieved.
1.3Annually the Chief Internal Auditor is required to provide an overall opinion on the Council’s internal control environment, risk management arrangements and governance framework to support the Annual Governance Statement.
2. Delivery of the Internal Audit Plan
2.1The Council’s Internal Audit Strategy and Plan is updated each year based on a combination of management’s assessment of risk (including that set out within the departmental and strategic risk registers) and our own risk assessment of the Council’s major systems and other auditable areas. The process of producing the plan involves extensive consultation with a range of stakeholders to ensure that their views on risks and current issues, within individual departments and corporately, are identified and considered.
2.2In accordance with the audit plan for 2023/24, a programme of audits was carried out covering all Council departments and, in accordance with best practice, this programme was reviewed during the year and revised to reflect changes in risk and priority. All adjustments to the audit plan were agreed with the relevant departments and reported throughout the year to the Executive Leadership Team (ELT) and the Audit and Standards Committee as part of our periodic internal audit progress reports. Full details of the adjustments to the plan can be found in Appendix D.
2.3It should be noted that whilst there were some audit reports in progress or at draft report stage at year-end, outcomes from this work have been taken into account in forming our annual opinion. Full details of these audits will be reported to the Corporate Leadership Team (CLT) and the Audit, Standards and General Purposes Committee once each of the reports have been finalised with management.
3. Audit Opinion
3.1No assurance can ever be absolute; however, based on the internal audit work completed, the Chief Internal Auditor can provide partial (1) assurance that the Council has in place an adequate and effective framework of governance, risk management and internal control for the period 1 April 2023 to 31 March 2024.
3.2Further information on the basis of this opinion is provided below. Although the majority of audit opinions issued in the year were generally positive, there was an increase in the number of partial assurance reports and internal audit activities have identified a number of key areas where the operation of internal controls has not been fully effective. A number of these relate to key financial or corporate systems and link to risks identified in the Council’s strategic risk register. It should also be noted that in some of these cases the audits were delivered at the request of management in order to obtain assurance over areas where it felt there was the potential need for improvement. This demonstrates a positive organisational culture which utilises Internal Audit to help support service improvement.
1 This opinion is based on the activities set out in the paragraphs below. It is therefore important to emphasise
that it is not possible or practicable to audit all activities of the Council within a single year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Annual Report and Opinion 2023-24 APX. n 1Report | 791 KB | DownloadRead as text |
PDF |
Internal Audit Annual Report and Opinion 2023-24 APX. n 2Report | 1 MB | Download |
PDF |
Internal Audit Annual Report and Opinion 2023-24Report | 228 KB | Download |
PDF |
View as HTML (9./2) 142 KBReport | 142 KB | Copy on its way |
PDF |
View as HTML (9./3) 145 KBReport | 145 KB | Copy on its way |
PDF |
View item 9. as HTML 43 KBReport | 43 KB | Copy on its way |
Follow Audit, Standards & General Purposes Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | External Audit Plan 2025/26View the decision text for item 7. | Decided | Open |
| 23 Jun 2026 | Informing the Audit Risk Assessment 2025/26View the decision text for item 8. | Decided | Open |
| 23 Jun 2026 | Internal Audit Annual Report and Opinion 2025/26View the decision text for item 9. | Decided | Open |
| 23 Jun 2026 | Counter Fraud Annual Report 2025/26View the decision text for item 10. | Decided | Open |
| 23 Jun 2026 | Counter Fraud StrategyView the decision text for item 11. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.