Brighton and Hove City Council
Cabinet, Thursday 12 February 2026 at 2.00pm

Lane Rental Scheme

Decided Executive 2 papers

AI summaryBrighton and Hove City Council Cabinet agreed to seek Lane Rental approval, with day rates up to £2,500 for work on the busiest roads and times, estimated annual costs of £0.36m and anticipated revenue of £1.1m- £1.6m, with an expected launch in April 2027. [2.1] [3.3] [6.1] [6.2] [3.12]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet seeks powers to introduce Lane Rental [2.1].
MoneyOperating costs £0.36m annually [6.1]Anticipated revenue £1.1m- £1.6m annually [6.2].
What happens nextDevelop, consult and apply [2.2]Application window: October 2026 [3.12].
Who it affectsPromoters and road users [3.11] [9.1]Charges target the busiest 10% [3.6].

What was decided

Cabinet agreed that an application should be made to the Secretary of State for the powers needed to introduce Lane Rental. Report 2.1

Cabinet delegated the Corporate Director of City Operations, in consultation with the Member for Transport and City Infrastructure, to develop the scheme, consult stakeholders and apply for approval. Report 2.2

Following approval, implementation will be delegated to the Corporate Director of City Operations, in consultation with the Member for Transport and City Infrastructure. Report 2.2

Why

The Permit Scheme must be cost neutral and its fees are capped. It gives no financial incentive to change working patterns or reduce time occupied on the highway. Report 3.2, 4.2

Lane Rental adds charges designed to promote behaviour change and reduce road work disruption. The Department for Transport accepts that it will generate a financial surplus for mitigation, highway improvements and related public benefits. Report 3.4, 3.7

The Department for Transport encourages Lane Rental. Trials in Kent and Transport for London have shown reduced disruption. Report 3.5

What happens next

Refresh the Traffic Sensitive Streets list and consult on it before developing the Lane Rental scheme. Report 3.6, 3.9

Consult utility companies, public transport operators, disability representative groups and equalities groups, then address concerns before the application. Report 5.1, 8.2, 9.1

Prepare the application for the October 2026 window. After approval, notify promoters 12 weeks before implementation, hold a trial, and work towards an April 2027 launch. Report 3.11, 3.12

The money

  • £0.36m Estimated annual operating costs Report 6.1
  • £1.1m- £1.6m Anticipated annual Lane Rental revenue Report 6.2
  • £0.37m- £0.62m Expected annual highway maintenance allocation Report 6.3
  • 50% Income after expenses directed to highway maintenance Report 6.3
  • 50% Remaining income entered into a ringfenced fund Report 6.4
  • £2,500 Maximum day rate charge for work on busy roads and times Report 3.3
  • £800,000 Approximate Permit Scheme income per annum Report 3.2

Options considered

  • Chosen: Pursue Lane Rental. It adds charges on the busiest 10% of the network to encourage behaviour change and reduce disruption. The Department for Transport accepts that it will generate a financial surplus for mitigation and improvements. Report 3.3, 3.4, 3.6, 3.7
  • Rejected: Continue with the Permit Scheme only. The Permit Scheme must be cost neutral and has capped fees, with no financial incentive to work differently or reduce the time occupied on the highway. Report 4.1, 4.2

Implications

  • Financial: Estimated operating costs are £0.36m annually, including additional staff, enforcement, operational costs and lost permit revenue. Revenue is anticipated at £1.1m- £1.6m annually. Report 6.1, 6.2
  • Financial: After expenses, 50% is directed to highway maintenance. The remaining 50% enters a ringfenced fund for network projects and reducing road work impacts. Report 6.3, 6.4
  • Legal: The Secretary of State must approve the scheme, and the application and later operation must follow detailed legal requirements, including local consultation. Report 3.10, 7.2
  • Legal: The Council's Permit Scheme continues, but an activity liable for Lane Rental cannot also attract a separate permit fee. Report 7.3
  • Legal: The application must show an existing Permit Scheme and full compliance, including fee reductions for joint works, incentives to work outside peak hours and caps for major works. Report 3.10
  • Equalities: Equalities groups will be consulted, and the scheme could reduce the frequency and timescales of road works affecting vulnerable road users. Report 9.1
  • Climate: Reducing the impact of road works is expected to reduce congestion and idling, work towards reducing unnecessary carbon emissions and support a more sustainable transport network. Report 10.1
  • Risk: DfT resource issues may delay the application, and DfT may not support it or stakeholders may object. Officers plan to use previous application learning and address consultation concerns. Report 8.1, 8.2

Who and where

  • Those requesting work on the network Report 3.3
  • Road work promoters Report 3.11
  • People needing highway permits Report 4.2
  • Road users Report 3.1
  • Vulnerable road users Report 9.1
  • Utility companies Report 5.1
  • Public transport operators Report 5.1
  • Disability representative groups and equalities groups Report 5.1, 9.1

Timeline

  • Before developing the Lane Rental scheme: Complete and consult on the Traffic Sensitive Streets refresh. Report 3.9
  • Once the Traffic Sensitive Streets have been agreed: Consult on the proposed Lane Rental Scheme before applying to the Secretary of State. Report 3.9
  • As of 5th January 2026: 50% of Lane Rental income is ringfenced towards highway maintenance. Report 3.8
  • From 5th January 2026: Street works legislation allows charges for weekend and holiday overruns, and doubles fixed penalties for overrunning permits, works without permits and breaches of permit conditions. Report 4.3
  • October 2026: Application window to the Secretary of State, following approximately 14 months of development. Report 3.12
  • 12 weeks ahead of the planned implementation date: Promoters are notified, followed by a trial before the scheme goes live. Report 3.11
  • April 2027: Expected go live date. Report 3.12
  • Annually: The scheme is reviewed for effectiveness. Report 3.11

Plain English for the jargon

  • Lane Rental: A charge for work on the network on busy roads and times, designed to reduce disruption. [3.3] [3.4]
  • Permit Scheme: The council's road works permit system, coordinated, inspected and enforced by the Street Works team. [3.1] [3.2]
  • Traffic Sensitive Streets: The street list used to select the busiest 10% of the network. [3.6]
  • Ringfenced fund: Money set aside for projects that reduce disruption and other adverse effects caused by street work. [3.8] [6.4]
  • Surplus Fund Board: The body that will allocate the remaining 50% of income. [3.8]
  • DfT: The Department for Transport. [3.2]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item130

Resolved

View the decision text for item 130.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet, 6 pages

Recommendations

2.1That Cabinet agrees that an application to the Secretary of State should be made to secure the required powers to introduce Lane Rental to Brighton and Hove City Council.

2.2That Cabinet delegates authority to the Corporate Director of City Operations to develop the Lane Rental Scheme in consultation with the Member for Transport and City Infrastructure, carry out stakeholder consultation on this scheme and apply to the Secretary of State for approval to introduce Lane Rental. 787 2.3 That the Committee delegates authority to the Corporate Director of City Operations, in consultation with the Member for Transport and City Infrastructure implement the Lane Rental Scheme following the Secretary of State approval.

3. Context and background information

3.1Network Management receives in the region of 20,000 requests to work on the network per annum, and these are coordinated, inspected, and enforced, by the Street Works team to reduce the impact on the travelling public.

3.2The BHCC Permit Scheme is required, under Department for Transport (DfT) guidance, to be cost neutral to the Authority. This Permit Scheme generates approximately £800,000 per annum. It is becoming increasingly difficult to maintain a neutral cost scheme as fees are capped by DfT.

3.3The Lane Rental scheme builds on this Permit Scheme and allows the Highway Authority to impose specific day rate charges up to £2,500 on those requesting to work on the network on our busiest roads at the busiest times.

3.4Developing Lane Rental is the next stage in the evolution of the Network Management by imposing additional charges designed to promote a range of behavioral changes that will reduce the impact of road works on the network.

3.5Lane Rental is being actively encouraged by the DfT as trials in Kent and Transport for London have been shown to deliver positive benefits in terms of reduced disruption from the financially incentivised behavioral change.

3.6In accordance with DfT guidance Lane Rental will only apply to the busiest 10% of the network. The 10 % will be selected from the list of traffic sensitive streets, which must be consulted upon prior to application.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lane Rental SchemeReport 6 pages DownloadRead as text
PDF
View item 130. as HTML 48 KBReport 48 KB Copy on its way

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. Decided Open
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies