Brighton and Hove City Council
Cabinet, Thursday 23 April 2026 at 2.00pm

The King Alfred Leisure Centre Regeneration Project - Progress Update

Decided Executive 2 papers

AI summaryCabinet agrees next stage of King Alfred leisure centre rebuild, releasing £3.5m for demolition and enabling works running to November 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDevelopment Management Agreements with Alliance Leisure
Money£3.5mbrought forward from £65m total capital budget
What happens nextFurther Cabinet paperSeptember or October 2026 for final budget
Who it affectsAll wardscitywide, site at Hove seafront

What was decided

Cabinet agreed the Council enters into Development Management Agreements with Alliance Leisure for enabling works, including demolition of the disused bowling alley, with Alliance then contracting Willmott Dixon Construction as main contractor. Report P17, 1.2, 4.3

Cabinet agreed to delegate authority to the Corporate Director City Operations, in consultation with the cabinet member for Sports, Recreation and Libraries, to finalise the terms of the Development Management Agreements. Report P17

Cabinet agreed to bring forward £3.5m from the previously agreed project capital budget to fund these works up to November 2026. Report P17, 1.3

Why

The project has completed the technical design stage (RIBA 4) and submitted its planning application, so needs to move to demolition and site enabling works before the main build can begin in November 2026. Report P12, 1.2, 1.4

The £3.5m sits within the £65m indicative capital budget approved by Cabinet on 25 September 2025, and is needed because bringing the enabling works forward avoids further delay to construction. Report P32

Replacing the centre supports the Council Plan 2023 to 2027 and the Sports Facilities Investment Plan, and prior approval for the demolition was granted on 2 February 2026. Report 1.5, P19

What happens next

Enabling works begin at the start of May 2026, with demolition of the bowling alley area starting on site from July 2026 and completing in autumn 2026. Report P22, P23

A further Cabinet paper in September or October 2026 will seek agreement for the final budget and a further Development Management Agreement with Alliance for construction of the new facility. Report 1.4, 14.2

Main construction of the new facility is scheduled to begin in November 2026, subject to planning approval, with a temporary car park on Hove Lawns No.1 to be delivered first. Report 1.4, P19

The money

  • £3.5m brought forward from the agreed project capital budget to fund enabling works to November 2026 Report 1.3, P32
  • £65 million overall indicative capital budget approved by Cabinet on 25 September 2025 Report P32
  • £5 million previously approved allocation to develop the scheme to RIBA stage 4, now expected to be used by end of April 2026 Report P32
  • £8.5 million total committed and spent prior to any final decision to proceed Report P32
  • £0.575m soft strip and removal of asbestos contamination in the bowling alley area Report P32
  • £0.680m advance payment to UK Power Networks for cable diversion Report P32
  • £0.016m UK Power Networks point of connection fee Report P32
  • £0.090m BT diversions Report P32
  • £0.194 million design revisions for insurance requirements, including hybrid steel and timber frame and sprinkler system Report P33
  • £0.094m design of temporary car park, including biodiversity net gain and habitat replacement Report P33
  • £0.170 million per annum revenue financing cost of the additional £3.5m over the life of the asset Report P33
  • £0.890 million per annum base assumption for ongoing net revenue funding gap from the new facility Report P33, P34
  • around £0.4m per year car park income that the temporary car park is intended to protect Report P33
  • £9.8 million contingency and tender price inflation within the £65m project estimate Report P33

Options considered

  • Chosen: Progress demolition and enabling works now, with a further Cabinet paper in autumn 2026 to approve the main construction contract. Allows the project to maintain its November 2026 construction start without delay, using allocation already within the £65m indicative budget Report 1.2, 1.4, P32

Implications

  • Financial: The £3.5m release is contained within the £65m indicative capital budget and carries an annual revenue cost of £0.170m; the project remains exposed to higher debt costs, possible grant funding changes and tender inflation. Report P32, P34
  • Legal: The Council relies on its powers under section 19 of the Local Government (Miscellaneous Provisions) Act 1976, the NHS Act 2006, and the general power of competence in section 1 of the Localism Act 2011, and is using the UK Leisure Framework Agreement for procurement. Report P35, 7.2
  • Equalities: The design includes a Changing Places facility, walk in steps and PoolPods in both pools, and has been informed by engagement with Possability People, the Sussex Sight Loss Council and the Dolphins Disabled Swimming Club. Report 9.3, P45, P46, P47, 9.5
  • Climate: The new facility is designed to meet the BREEAM 'excellent' standard, reflecting the UK Net Zero Carbon Buildings Standard, and biodiversity mitigation includes new nesting habitat, sand baths and lime rich water sources. Report P50
  • Risk: Headline risks include programme delays, planning determination delays, financial exposure, on site delivery issues, site management alongside the A259 and groyne replacement projects, and uncertainty over Homes England grant funding. Report P38, P39, P40, P41, P42
  • Other: The Council engaged Historic England, which decided on 20 January 2026 not to add the existing King Alfred Leisure Centre to the National Heritage List.

Who and where

  • Residents and visitors across all wards in Brighton and Hove, particularly users of leisure and community facilities in the west of the city Report P9, 1.5
  • Existing users of the King Alfred Leisure Centre, including sports clubs, community groups and the boxing club leaseholder Report 5.4
  • Disabled residents and visitors, with the new design prioritising accessibility and independent use Report 9.3, P45
  • Freedom Leisure as the current leisure operator, and the new leisure operator to be appointed in December Report P31
  • Local community groups including the West Hove Seafront Action Group, Hove Civic Society and the Friends of St Aubyns Report 5.4, 5.5
  • Alliance Leisure as development partner and Willmott Dixon Construction as main contractor Report 1.2, 7.2, 12.7

Timeline

  • 25 September 2025: Cabinet approved the £65m indicative budget, £5m initial allocation and demolition of redundant parts of the site Report P32
  • September to October 2025: Asbestos survey of the redundant bowling hall revealed high contamination Report P20
  • December 2025 to March 2026: Asbestos removal and soft strip works carried out on the bowling alley area Report P19
  • 4 December 2025: Application for prior approval of demolition of the disused bowling alley submitted Report P19
  • 20 January 2026: Historic England decided not to add the existing King Alfred Leisure Centre to the National Heritage List
  • 2 February 2026: Prior approval for demolition of the disused underground bowling alley granted, with one ecological condition Report P19
  • 27 February 2026: Main planning application for the new leisure centre submitted (reference BH2026/00490), including a temporary car park on Hove Lawns No.1 Report P19
  • April 2026: Final Ecological Mitigation Strategy due to be submitted to the planning authority
  • End of April 2026: Original £5m allocation now expected to be fully used, earlier than profiled Report P32
  • Beginning of May 2026: Enabling works scheduled to commence
  • July 2026: Demolition works scheduled to start on site after the Ecological Mitigation Strategy is discharged Report 4.3
  • September or October 2026: Further Cabinet paper to be brought forward on the final agreed budget and the main construction Development Management Agreement Report 1.4, 14.2
  • November 2026: Construction of the new leisure centre scheduled to begin, following completion of enabling works Report 1.3
  • 2027 nesting season: Ecological mitigation features on Hove Lawns No.1, including sparrow nesting habitat, sand baths and lime rich water sources, will be in place

Plain English for the jargon

  • RIBA 4: Royal Institute of British Architects Plan of Work Stage 4, the technical design stage of a building project
  • BNG: Biodiversity Net Gain, an approach requiring development to leave biodiversity in a better state than before
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability rating for buildings
  • ACM: Asbestos Containing Materials
  • RAMS: Risk Assessment and Method Statement
  • WDC: Willmott Dixon Construction, the appointed main contractor
  • UKPN: UK Power Networks
  • HSE: Health and Safety Executive
  • PCSA: Pre Construction Services Agreement
  • CDM Principal Designer: The duty holder under the Construction (Design and Management) Regulations responsible for health and safety design coordination
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item168

Resolved

View the decision text for item 168.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet, 18 pages

Brighton & Hove City Council

Cabinet Agenda Item 168

Subject: The King Alfred Leisure Centre Regeneration Project

Date of meeting: Thursday, 23 April 2026

Report of: Cabinet Member for Sports, Recreation & Libraries

Lead Officer: Name: Corporate Director - City Operations

Contact Officer: Name: Mark Healy

Email: [email protected]

Ward(s) affected: (All Wards);

Key Decision: Yes

Reason(s) Key: Expenditure which is, or the making of savings which are, significant having regard to the expenditure of the City Council’s budget, namely above £1,000,000 and Is significant in terms of its effects on communities living or working in an area comprising two or more electoral divisions (wards).

For general release 1. Purpose of the report and policy context 1.1 This paper seeks Cabinet agreement to progress the King Alfred Regeneration Project to the next stage of implementation following the completion of the technical design stage (Royal Institute of British Architects Plan of Work Stage 4 or RIBA 4) and the submission of the planning application.

1.2Specifically, the paper seeks agreement to allow the Council to enter into the Development Management Agreement with Alliance Leisure Services (“Alliance”). Alliance will then enter into the building contract directly with the chosen main contractor Willmott Dixon Construction (WDC) to take forward the on-site enabling works including the demolition of the disused bowling alley area.

1.3The paper also seeks agreement to bring forward the allocation of £3.5m from the total agreed capital budget to fund these works up to November 2026, when construction of the new facility is scheduled to begin.

1.4Ahead of the full construction works commencing, a further paper will be presented to Cabinet in September or October to seek agreement for the final agreed budget and to enter into a further Development Management Agreement with Alliance for the construction of the new facility.

1.5The replacement of the King Alfred Leisure Centre aligns with the Council Plan 2023-2027, particularly Outcome 1 A city to be proud of, which sets out a commitment to ‘Deliver improvements to leisure facilities across the city’ and Outcome 3, ‘A healthy city where people thrive’. Replacing the facility is 49 also a specific commitment of the council’s Sports Facilities Investment Plan (SFIP).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The King Alfred Leisure Centre Regeneration Project: Progress UpdateReport 18 pages DownloadRead as text
PDF
View item 168. as HTML 146 KBReport 146 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. The King Alfred Leisure Centre Regeneration Project - Progress UpdateThis decision
  2. King Alfred Leisure Centre Regeneration ProjectDecided
  3. King Alfred Development - UpdateDecided
  4. King Alfred DevelopmentDecided
  5. King Alfred DevelopmentNoted
  6. King Alfred Leisure Centre - Redevelopment and Urgent WorksNoted

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. Decided Open
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies