Brighton and Hove City Council
Cabinet, Monday 29 June 2026 at 9.00am

Improving Fire Safety in Council Homes

Decided Executive 2 papers

AI summaryBrighton & Hove Cabinet approves £6m Homes England fire safety funding for up to 9 council blocks and a new £11.5m four-year Fire Safety Framework Contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCSS funding use, HRA capital budget, consultant team, framework
Money£6,007,500 HRA capital and £11.5m frameworkFully funded by Homes England CSS; framework over 4 years
What happens nextAppoint specialist project teamWithin 1 month of first grant payment per Homes England
Who it affectsResidents in 8 to 9 council high-rise blocksIncluding Bristol Estate, St James House, Normanhurst, Livingstone House

What was decided

Cabinet approved a £6,007,500 HRA capital budget, funded entirely by Homes England Cladding Safety Scheme grants, for fire safety improvement works. Report 2.2, 6.2

Cabinet approved the procurement and award of a team of specialist consultants to carry out design work and prepare tender documents for construction contractors. Report 2.3, 3.15

Cabinet approved delegation to establish a Brighton & Hove City Council Fire Safety Framework Contract valued at £11.5m over 4 years, an increase on the March 2026 Procurement Forward Plan. Report 2.5, 3.18

Why

The council must meet new duties under the Building Safety Act and Fire Safety (England) Regulations and progress façade remediation on high-rise blocks with elements that may pose a high risk of fire spread. Report 3.1, 3.11

Homes England CSS funding mitigates costs to the Housing Revenue Account and leaseholders, and must be used promptly or the opportunity is lost; Homes England expects mandatory project team roles in place within 1 month of first payment. Report 3.4, 3.5, 4.1

What happens next

Set up the specialist project team within 1 month and submit monthly progress reports to Homes England, with design and tendering completed within 6 months (9 months for BSR buildings). Report 3.4, 3.14, 3.15

If substantive works funding is later awarded, the team will move to delivery, with works to blocks following from months 12 to 24. Report P22

Procure the Fire Safety Framework Contract in line with the council's Contract Standing Orders and keep residents and leaseholders informed throughout. Report 3.19, 5.4

The money

  • £6,007,500 HRA capital budget for fire safety improvement works, fully funded by Homes England CSS Report 2.2, 6.2
  • £11.5m Value of new Fire Safety Framework Contract over 4 years, consolidating existing HRA spend areas Report 2.5, 3.18
  • £4,672,500 CSS pre-tender funding received to date (as at 16/06/26) for 7 blocks, allocated to HRA balance sheet Report 6.1
  • £667,500 Pre-tender CSS funding per block, inc. VAT Report 3.5, P23, P24
  • £7.994m Approved fire safety capital budget for 2026/27 Report 6.3
  • £12.842m Provisional fire safety capital budget across the next 4 years Report 6.3

Options considered

  • Chosen: Use Homes England CSS funding for the 8 to 9 funded blocks. Funding cannot be redirected elsewhere; meets new building safety duties and reduces HRA and leaseholder costs Report 2.1, 2.2, 4.1, 3.9
  • Rejected: Decline to use the funding. A missed opportunity to fund fire safety improvements Report 4.1
  • Rejected: Fund the works from the council's own Housing Revenue Account. Would come at a significant cost to Brighton & Hove City Council Report 4.2
  • Rejected: Use an existing national framework for the fire safety framework. A bespoke local framework allows use of more local contractors, better quality control, and a service tailored to residents Report P36

Implications

  • Financial: £6,007,500 of CSS grant is added to the HRA capital programme as a new cost centre; framework contract consolidates existing HRA fire safety spend rather than adding new budget. Report 6.2, 6.3, 3.18
  • Legal: Procurement of consultants and the new fire safety framework must comply with procurement legislation and the council's Contract Standing Orders, with legal services input on the works tender. Report 7.1, 7.2, 7.3, 12.1
  • Risk: No immediate risk to residents; existing mitigations such as waking watch and fire alarm systems remain in place while remediation is designed and tendered. Report 3.7, 8.1
  • Equalities: Equalities implications assessed as not applicable. Report 9.1
  • Climate: Sustainability implications assessed as not applicable. Report 10.1
  • Staffing: A specialist project team of external consultants is to be appointed, including Project Director, two Project Managers, Lead Designer, Fire Safety Engineer, Quantity Surveyor, Resident Engagement Lead, and Client Technical Advisor; the market for these roles is expected to reach capacity nationally. Report 3.15
  • Other: Residents and leaseholders must be kept informed; Homes England will review communications and escalate if standards are not met. Report 5.2, 5.3, 5.4

Who and where

  • Residents and leaseholders in up to 9 council high-rise blocks, including Livingstone House, St James House, Normanhurst, and Hazel, Hollyhock, Cherry, Damson and Viscaria blocks on the Bristol Estate Report 3.5, P23, P24, P26
  • Housing Revenue Account, as recipient of Homes England CSS funding and holder of the new capital cost centre Report 6.1, 6.2
  • East Sussex Fire & Rescue Service, the Regulator of Social Housing and the Building Safety Regulator, who are being kept updated Report 3.7
  • Local specialist consultants and contractors who may be appointed via the new Fire Safety Framework Contract Report 3.15, P36

Timeline

  • 10 July 2024: Cabinet Member for Housing wrote to the Secretary of State requesting separate funding for health and safety regulatory programmes Report 3.10
  • 14 May 2026: Cabinet Member Decision published covering pre-tender works at Livingstone House Report 3.13
  • As at 16/06/26: £4,672,500 of CSS pre-tender funding received for 7 blocks and allocated to the HRA balance sheet Report 6.1
  • Within 1 month of first grant payment: Mandatory specialist project team roles must be fully formed per Homes England requirement Report 3.4, 3.14
  • Within 6 months (9 months for BSR buildings 18m or 7+ storeys): Design and tendering expected to be complete and Works Package ready to submit to Homes England Report 3.14
  • Months 12 to 24 (if further funding awarded): Works to blocks expected to follow after design and tendering Report P22

Plain English for the jargon

  • CSS: Homes England Cladding Safety Scheme, a national government grant programme funding remediation of unsafe cladding and external wall systems on residential buildings in England
  • HRA: Housing Revenue Account, the council account that ring-fences income and spending on council housing
  • LPS: Large Panel System, a type of high-rise building construction, including St James House in Brighton & Hove
  • BSR: Building Safety Regulator, the body responsible for overseeing building safety under the Building Safety Act 2022
  • PTS: Pre-Tender Support, the Homes England funding used to set up a specialist project team and prepare design and tender documents
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

View the decision text for item 13.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet, 10 pages

Recommendations

2.1Cabinet delegates authority to Corporate Director for Homes & Adult Social Care, in consultation with Lead Member for Housing, to utilise allocated Homes England Cladding Safety Schemes funding for improvements to fire safety in Brighton & Hove for all buildings with successful future bids.

2.2Cabinet approves a HRA capital budget of £6,007,500 (funded entirely by Homes England CSS funding) to be allocated to the fire safety improvement works.

2.3Cabinet approves the procurement and award of a team of consultants (as set out in 3.15 below) to carry out the design works and the preparation of the tender documentation for the procurement of construction contractors to undertake the works, as set out in 3.3 below.

2.4Cabinet delegates authority to the Corporate Director for Homes & Adult Social Care, in consultation with the Cabinet Member for Housing, to enter into the contracts with the consultants for the 7 blocks that we have currently been allocated funding, the block where funding has been approved but not yet received and for any further blocks where Homes England Cladding Safety Scheme funding may be awarded in future.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Improving Fire Safety in Council HomesReport 10 pages DownloadRead as text
PDF
View item 13. as HTML 80 KBReport 80 KB Copy on its way

At this meeting

Whole meeting

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. Decided Open
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open