DFT - Structures Bid - King Arches Phases 6 & 7

Decided Executive 5 papers

AI summaryBrighton and Hove Cabinet is asked to approve a £40.9 million bid to the DfT Structures Fund to reconstruct 38 Victorian seafront arches on the A259 Kings Road, with construction planned between March 2028 and March 2030.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet item seeking approval of DfT Structures Fund bid
Money£40,915,500 requested from DfTPlus £4,000,000 local authority contribution
What happens nextConstruction March 2028 to March 2030Subject to DfT funding award
Who it affectsA259 Kings Road seafront, Brighton38 Victorian arches in Phases 6 and 7

What was decided

Cabinet is asked to approve submission of a bid to the DfT Structures Fund for the A259 Seafront Arches Phase 6 and 7 reconstruction scheme. Report P3, P89

The total scheme cost is £41,065,500, comprising £40,915,500 of requested DfT investment and a £4,000,000 local authority contribution. Report P89

The scheme would deliver a 120-year life extension of the structure, replacing failing filler joist slab decks built around 1880 with reinforced concrete frames. Report P11, P27

Why

Structural inspections in June 2026 confirmed the arches are in poor condition, with high confidence that traffic restrictions and propping will be required by the end of 2029/30 if no action is taken. Report P22, P25, P26

Failure of the arches would close the westbound A259 carriageway and adjacent National Cycle Route 2, severely affecting an area home to over 100,000 residents with diverted traffic. Report P25, P52, P58

Average annual maintenance spend on Brighton and Hove's highway structures is around £350,000, far below the £5.3 million recommended by the Code of Practice, making external funding essential. Report P91

What happens next

If the bid succeeds, procurement will use the Hampshire County Council GEN5 Construction Framework, with construction starting March 2028 and ending March 2030. Report P72, P99, P101

Planning, conservation and heritage approvals will be required because the arches are designated heritage assets in a conservation area. Report P108

The money

  • £40,915,500 Requested DfT investment across 2027/28 to 2029/30 Report P89
  • £4,000,000 Local authority contribution in 2029/30 Report P89
  • £41,065,500 Total scheme cost Report P89
  • £6,213,100 DfT funding profile 2027/28 Report P89
  • £15,426,200 DfT funding profile 2028/29 Report P89
  • £19,426,200 DfT funding profile 2029/30 Report P89
  • 41,841,771 Present Value Costs in 2023 market prices Report P60
  • 804,526,799 Present Value Benefits in 2023 market prices Report P60

Options considered

  • Chosen: Submit bid to DfT Structures Fund for Phase 6 and 7 reconstruction. Internal budgets cannot fund the urgent replacement works, and further delay risks structural failure and A259 closure. Report P41, P91
  • Rejected: Do nothing and continue emergency repairs and monitoring. High confidence that propping, traffic restrictions and tenant removal will be needed by 2029/30, and past failures on similar arches caused months of disruption. Report P25, P26, P92

Implications

  • Financial: A 25% optimism bias, 10% construction risk allowance and 15% inflation allowance are built into the cost estimate based on Phase 4 and 5 benchmark rates. Report P60, P92
  • Financial: Estimated Benefit to Cost Ratio is 19.2, based on present value costs of 41,841,771 and benefits of 804,526,799. Report P60
  • Legal: The Council has powers under the Highways Act to carry out works regardless of private owner views, though 12 of 38 arches are privately owned by 5 separate owners who are supportive. Report P12, P87
  • Equalities: Strategic traffic diversions would affect areas with higher proportions of over-65s and more deprived households, and the existing cycle route is the only high-quality facility for many trips. Report P57, P58
  • Climate: Avoiding structural failure prevents increased vehicle emissions from diverted traffic, and a Carbon Management Plan and Whole Life Carbon Assessment informed earlier phase designs. Report P112
  • Risk: The 38 arches were built at the same time as past phases, and in 2012 and 2014 similar arches collapsed, causing 12 months of disruption; filler beam failure mechanism is sudden and catastrophic. Report P25, P27

Who and where

  • Westbound A259 road users (11,922 vehicles daily, 2024 AADT) Report P55
  • Cyclists on National Cycle Route 2 (1,466 cycles on the route) Report P56
  • Pedestrians on the seafront upper and lower promenades Report P56
  • Approximately 152 employees currently working in arch commercial spaces Report P30
  • Five private owners of 12 of the 38 arches Report P12
  • Over 100,000 residents in areas affected by diversion routes Report P58

Timeline

  • June 2026: Structural inspections confirmed poor condition of Phases 6 and 7 arches Report P22
  • 2026: Works on Phases 4 and 5 planned to start Report P42
  • March 2028: Anticipated construction start for Phases 6 and 7 Report P99
  • End of 2029/30: DfT funding deadline for scheme completion Report P89
  • March 2030: Anticipated construction end date Report P101

Plain English for the jargon

  • BCI: Bridge Condition Indicator, a score used to rate structural condition
  • MRN: Major Road Network, a category of local authority roads of national importance
  • DMRB: Design Manual for Roads and Bridges, the standards used for highway structures
  • NEC4 ECC Option A: A construction contract where the contractor carries out work for priced activities with shared risk via compensation events
  • AADT: Annual Average Daily Traffic flow
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50

Resolved

View the decision text for item 50.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet

Public

Structures Fund template This template is for local authorities proposing schemes for investment from the Structures Fund. Before completing the template, local authorities should read the Structures Fund guidance and associated documents. Alongside the template, local authorities must also complete the economic toolkit for the proposed scheme.

Part 1 – Details of the Structure Being Promoted 1.1 Scheme Information This section captures the key information on the scheme that is being proposed to the Structures Fund. a) Local highway authority (LHA) name: Brighton & Hove City Council b) Scheme / structure name and LHA bridges number: A259 Seafront Arches Phase 6 and 7 c) Location (OS Grid Reference) of the scheme/structure (to identify location on map): Easting: 530822 Northing: 103951 d) Name of Project Manager: Nick Bean e) Email address: [email protected] f) Phone number: [phone removed] g) What type of eligible structure would your scheme address? (select all that apply)

☒ Bridges ☐ Cutting/embankment

☐ Fly-overs ☐ Tunnels

☐ Retaining walls ☐ Local highway repairs due to landslip

☐ Culverts ☐ Local highway repairs due to collapse

☐ Other structure type (please specify): Click or tap here to enter text.

h) Provide an overview of the structure proposed for intervention and the nature of the problem. (Maximum 250 words) This could include, for example, the age, construction type, feature carried and feature crossed of the relevant structure and if the structure has listed heritage status. The A259 Kings Road is a major arterial route passing along the seafront at Brighton. The route is of vital importance to the highway network and to the economic health of the area. This main road is supported by Victorian arches which are approaching the end of their useful life and are in urgent need of replacement to avoid collapse and the closure of the road which would bring

OFFICIAL 239 Public

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DFT: Structures Bid: King Arches Phases 6 & 7 APX. n 1Report 4.4 MB DownloadRead as text
PDF
DFT: Structures Bid: King Arches Phases 6 & 7Report 349 KB Download
PDF
SBSA Letter Of Support: APX. n 2 King Arches Phases 6 & 7Report 126 KB Withheld: personal details
PDF
TfSE support Letter APX. n 3 King Arches Phases 6 & 7Report 68 KB Download
PDF
View item 50. as HTML 67 KBReport 67 KB Copy on its way

At this meeting

Whole meeting

Who was there

10 of 10 attended
BS
Councillor Bella SankeyChair, present
JT
Councillor Jacob TaylorDeputy Chair, present
MA
Councillor Mitchie AlexanderCommittee Member, present
JA
Councillor Jacob AllenCommittee Member, present
ED
Councillor Emma DanielCommittee Member, present
DM
Councillor David McGregorCommittee Member, present
TM
Councillor Trevor MutenCommittee Member, present
AR
Councillor Alan RobinsCommittee Member, present
TR
Councillor Tim RowkinsCommittee Member, present
GW
Councillor Gill WilliamsCommittee Member, present

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Royal Pavilion Gardens Restoration ProjectView the decision text for item 56. Decided Open
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies