Resolved
RESOLVED – That the report and the above information be noted.
Greater Brislington Neighbourhood Partnership noted this item on Monday 13 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report and the above information be noted.
To note the current position of the Local Traffic, Section 106 and Grant Funded highway schemes in Greater Brislington.
1. The Partnership had four outstanding schemes from previous financial years:
Improved pedestrian crossing facilities along Birchwood Road, funded through Section 106 developer contributions;
Footway and cycleway improvements in Emery Road, funded through Section 106 developer contributions;
The review and implementation of appropriate parking restrictions in and around the non-residential length of Broomhill Road (to include the industrial area), funded through the Investing in Bristol’s Future Fund (IBFF) initiative;
The introduction of additional parking restrictions in Latimer Close and along Birchwood Road, funded through Section 106 developer contributions.
2. At its meeting in September 2014, the Partnership prioritised two new local traffic schemes to be progressed in the current and next financial years: The review and implementation of parking restrictions in the residential area to the west of Wick Road;
A feasibility and design study to identify possible road safety improvements along Wick Road/Newbridge Road
3. The Partnership also approved £1,500 for minor lines and signs (to be spent at officer’s discretion) and £3,000 for minor works.
4. Minor works are measures that do not need significant design, consultation or legal work. Examples could include footway bollards, coloured surfacing, benches or dropped kerbs to aid pedestrian access. All requests will be reviewed by highway officers and reported for approval at the next Neighbourhood Partnership meeting.
Scheme Progress
Scheme name Birchwood Road
Measures Improved pedestrian crossing facilities
Progress Informal consultation stage – December 2015
Scheme name Emery Road
Measures Footway and cycleway improvements
Progress Completed
Scheme name Broomhill Road (non-residential length, including the industrial area)
Measures The review and introduction of appropriate parking restrictions
Progress Currently with the TRO team ready for traffic regulation order in June/July 2016
Scheme name Latimer Close and Birchwood Road,
Measures The introduction of additional parking restrictions
Progress Complete
Scheme name West of Wick Road (parking restrictions)
Measures The review and implementation of appropriate parking restrictions in the residential area to the west of Wick Road
Progress Further design stage – possible formal consultation in August (or later) 2016
Scheme name Wick Road/Newbridge Road
Measures A feasibility and design study to identify possible road safety improvements
Progress Preliminary Investigations Site visit by Highways and NP on 12th February 2016 along the full length of the road to feed into information already provided by local residents and Councillors. Further meeting with Highways and NP coordinator in May 2016 to add further issues into the proposed scheme. Requests for Minor Works
No Location Request Progress
Installation of 3 wooden 1 Callington Rd bollards to prevent over- Completed running of grass verge
Equalities impact assessment
5. An Equalities Impact Relevance Check has been undertaken and determined that due to the fact that this decision has no impact on those with protected characteristics in the following ways a full equalities impact assessment is not required:
• access to or participation in a service; • levels of representation in BCC workforce; or • reducing quality of life (i.e. health, education, standard of living)
6. Further Equalities Impact Relevance Checks will be undertaken during the development of each scheme so that the specific impact of that scheme can be considered as the detail evolves.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Update 2015/16Report | 125 KB | DownloadRead as text |
Follow Greater Brislington Neighbourhood Partnership at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Dec 2016 | Minutes of Previous MeetingAgreed as an accurate record pending the addition of Elizabeth Benn to attendance list, as she was present but not li... | Agreed | Open |
| 12 Dec 2016 | Sandy Park Road Consultation UpdateIt was agreed that there was a need for a community hub approach and the right type of developments. | Agreed | Open |
| 26 Sep 2016 | Chairing ArrangementsIt was agreed that Councillor Jos Clark would chair the meeting. | Agreed | Open |
| 26 Sep 2016 | NP Budget RequestsRESOLVED that the following grant applications be approved: 1. Parish Church of St Anne’s Church Hall Floor £2,140 2.... | Approved | Open |
| 13 Jun 2016 | Minutes of Previous MeetingRESOLVED – That the minutes of the meeting of the partnership held on 14 March 2016 be confirmed as a correct record ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.