That Cabinet: 1. Authorised the Executive Director for Growth and Regeneration in consultation with the Cabinet Member for Transport, to spend an additional £989,940 funding on existing highways maintenance priorities as outlined in this report including to procure and award the contract(s) necessary which may be above the key decision threshold.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Highways Maintenance Works - Additional Pothole Funding
Ward(s) City Wide Author: Philip Davies Job title: Strategic Highways Maintenance Team Manager Cabinet lead: Councillor Donald Alexander, Executive Director lead: John Smith, Interim Executive Director Cabinet Member for Transport Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: To seek approval to spend an additional £989,940 on existing highways maintenance priorities as described in the report. Background: 1. To assist with the depreciating road condition, ongoing maintenance pressures and to keep the network safe, additional funding has been made available from the recent budget announcement. The government are investing an extra £200m into repairing roads. WECA has been allocated £2.8m of the investment. Bristol’s allocation from this is £989,940.
2. Potential sites have been identified though digital condition surveys, which employ a RAG rating, enabling us to target the additional funding to those areas highlighted as Red. The list of sites will be further prioritised by existing methods, where road condition, road hierarchy (usage), the number of defect repairs, number of enquiries and other factors are considered and scored accordingly.
3. The work will mostly comprise of smaller resurfacing sites, typically junctions and roundabouts, which are areas which are not suitable for preventive maintenance such as surface dressing and micro asphalt, which is regarded as our default option and is in line with national guidance (HMEP - Well Managed Highways).
4. Bristol City Council repair on average over 2,500 potholes each year. The work will be targeted at sites where there is significant potholing and where we are frequently having to carryout response repairs. That should significantly improve the condition of those sites, impacting the local environment and reducing the number of response repairs, so that resource can be better allocated in the future.
5. To advise; carriageway preventive maintenance is already funded for this financial year.
6. A well-maintained highway network is critical for fulfilling our statutory obligations in accordance with the Highways Act. Failure to maintain our roads may breach Health and Safety legislation and pose severe risks to the public and damage the reputation of the authority and wider economy.
1 Version Feb 2022
OFFICIAL Cabinet Member / Officer Recommendations
That Cabinet 1. Authorises the Executive Director for Growth and Regeneration in consultation with the Cabinet Member for Transport, to spend an additional £989,940 funding on existing highways maintenance priorities as outlined in this report including to procure and award the contract(s) necessary which may be above the key decision threshold. Corporate Strategy alignment: The corporate strategy objectives of this funding would be fulfilment of some of the corporate strategic themes with regard to the Theme, Transport and Connectivity and business as usual functions. The funding will specifically meet the Physical infrastructure strategy to:
Plan, prioritise and begin a refreshed and long-term (25-year+) programme of maintenance, repair, and renewal of the city’s infrastructure, such as roads and bridges. This will help make sure that the city is safer, more climate- resilient, nature-friendly, and able to grow its economy in an inclusive and sustainable way.
The repairs to the carriageway will also fulfil the Councils main overall statutory duties, as Local Highway Authority and will benefit the local community and users of the highway.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.