Bristol City Council
Cabinet, Tuesday 4 September 2018

Bristol Heat Networks – 2018 update on progress and proposed expansion

Approved Executive 6 papers

Cabinet approved this item on Tuesday 4 September 2018. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

Cabinet: 1. Approved the allocation of £2 million of Prudential Borrowing and reallocation of £4.5 million of City Centre Phase 1 heat network Prudential Borrowing for the further expansion of the council’s heat network. 2. Delegated authority to the Executive Director responsible for the Energy Service, in consultation with the Cabinet Member for Energy, the Cabinet Member for Finance, the Chief Finance Officer and the Monitoring Officer, to apply for and accept any government revenue and capital grant funding where available (including Heat Network Investment Project (HNIP) capital grant funding from the Department of Business, Energy & Industrial Strategy (BEIS), European Regional Development Fund (ERDF) and Heat Network Delivery Unit (HNDU) funding) and, where grant funding has been successfully applied for, this would constitute additional capital funding over and above the Prudential Borrowing sought within this Cabinet report and dedicated to the heat network. 3. Delegated authority to the Executive Director responsible for the Energy Service, in consultation with the Cabinet Member for Energy, the Chief Finance Officer and the Monitoring Officer, to determine the appropriate delivery model with potential investment partners should opportunities arise as part of the City Leap Prospectus. 4. Delegated authority to the Executive Director responsible for the Energy Service, in consultation with the Cabinet Member for Energy, the Chief Finance Officer and the Monitoring Officer, to carry out potential enabling works, with prospective funding appropriately identified from the funding approved by this Cabinet Report in order to future proof the infrastructure for potential cross border strategic heat networks, should such opportunities arise. 5. Delegated authority to the Executive Director responsible for the Energy Service to approve all necessary operational decisions associated with delivering the council’s heat network expansion programme, including signing of heat connection agreements with customers. 6. Delegated authority to the Executive Director responsible for the Energy Service, in consultation with the Cabinet Member for Energy, the Chief Finance Officer and the Monitoring Officer, to undertake and approve the procurement of all goods, works and services referenced in paragraphs 22 to 55 of Appendix A to the Cabinet Report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet report: Further essential info and backgroundAppendix A 5 MB Copy on its way
PDF
Risk RegisterAppendix D 25 KB Copy on its way
PDF
Cabinet Report Equalities: FinalAppendix E 113 KB Copy on its way
PDF
Eco checklist v5 (Vr 2)Appendix F 54 KB Copy on its way
PDF
Implications on ICTAppendix L 34 KB Copy on its way
PDF
Bristol Heat Networks: 2018 update on progress and proposed expansionReport 162 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bristol

Search all
  1. Bristol Heat Networks – 2018 update on progress and proposed expansionThis decision
  2. The Proposed Central Bristol Heat Network ZoneNoted
  3. Bristol Heat Pump Ready ProjectNoted
  4. Transfer of Heat Network assets from the Council to Bristol Heat Networks LimitedApproved
  5. Bristol Heat Network Project UpdateAgreed
  6. Bristol Heat NetworksDecided

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies